Data centers in Illinois
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 55 data center projects in Illinois as of November 2026: 32 operating, 10 under construction and 7 approved, totaling about 5,561 MW announced where a figure is published.
Illinois has 55 tracked data centers. Their announced capacity totals about 5,561 MW where a figure is published. Of those, 32 operating, 10 under construction and 7 approved. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
HydraVault Chicago video · 2 min 13 sec
Data center projects in Illinois
- Aligned Chicago Campus (ORD-01, ORD-02)
OperatingNorthlake48 MW announced
- Aligned Elk Grove Village Campus (ORD-03)
ProposedElk Grove Village96 MW announced
- Centersquare ORD2 (Elk Grove Village)
OperatingElk Grove Village
- Centersquare ORD4 (Lisle)
OperatingLisle
- Chirisa Volo Data Center
OperatingVolo
- CloudHQ Mount Prospect Campus (Mount Prospect Technology Campus)
Under constructionMount Prospect
- Compass Datacenters Chicago Campus (Hoffman Estates; 200 MW campus)
OperatingHoffman Estates200 MW announced
- Compass Hoffman Estates Campus (former Sears HQ)
Under constructionHoffman Estates
- CoreSite Chicago Campus (CH1, CH2)
OperatingChicago
- CyrusOne Aurora Bilter Road Campus
Under constructionAurora40 MW announced
- CyrusOne Aurora Campus (CHI1-CHI3)
OperatingAurora
- CyrusOne CHI-11 West Yorkville Campus
ApprovedYorkville540 MW announced
- CyrusOne Lombard (CHI5)
OperatingLombard12 MW announced
- CyrusOne Sangamon County
Proposed
- CyrusOne Sangamon County Campus
Approved636 MW announced
- CyrusOne Wood Dale Campus
Under constructionWood Dale18 MW announced
- CyrusOne Yorkville Technology Campus (Yorkville)
ApprovedYorkville
- DataBank ORD1 (600 South Federal)
OperatingChicago1 MW announced
- DataBank ORD2 (840 South Canal)
OperatingChicago2 MW announced
- DataBank ORD3 (Chicago)
OperatingChicago
- DataBank ORD4 (Oak Brook)
OperatingOak Brook9 MW announced
- Digital Realty Elk Grove Village Campus (CH1/CH2/CH3)
OperatingElk Grove Village
- Digital Realty Franklin Park Campus (ORD12/ORD13/ORD14)
OperatingFranklin Park
- Digital Realty ORD10 (350 East Cermak)
OperatingChicago
- Digital Realty ORD11 (600 South Federal)
OperatingChicago
- Digital Realty ORD23 (Northlake)
OperatingNorthlake
- EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)
OperatingElk Grove Village
- Edged Chicago Campus (ORD01)
OperatingAurora96 MW announced
- Equinix CH4 (Chicago)
OperatingChicago
- Equinix CH7 (Chicago)
OperatingChicago
- Equinix Elk Grove Village Campus (CH3, CH5)
ExpandingElk Grove Village
- HydraVault Chicago
Under constructionChicago20 MW announced
- Iron Mountain CHI-1 (Des Plaines)
OperatingDes Plaines56 MW announced
- Iron Mountain Data Centers Iron Mountain Chicago (Chicago)
OperatingChicago
- Joliet Technology Center
ApprovedJoliet1,800 MW announced
- Meta DeKalb Data Center
OperatingDeKalb
- Metro Edge IMD1 (Illinois Medical District)
ApprovedChicago
- Microsoft Elk Grove Village Campus
Under constructionElk Grove Village
- Microsoft Hoffman Estates Campus
ExpandingHoffman Estates
- Microsoft Northlake Data Center (CH1)
OperatingNorthlake
- NTT Chicago Campus (Itasca)
OperatingItasca104 MW announced
- Pioneer Project Cardinal Yorkville
ApprovedYorkville
- Prime ORD Chicago Campus
Under constructionElk Grove Village180 MW announced
- Prologis Project Steel Yorkville
ApprovedYorkville
- QTS Chicago Mega Data Center
OperatingChicago125 MW announced
- Serverfarm CH1 (840 South Canal)
OperatingChicago32 MW announced
- STACK CHI01 (Elk Grove Village)
OperatingElk Grove Village
- STACK CHI02
AnnouncedElk Grove Village36 MW announced
- Stream Chicago I (Elk Grove Village)
OperatingElk Grove Village
- Stream Chicago II (Elk Grove Village)
OperatingElk Grove Village
Who serves this place
- Not collected yet.
Counties and cities in Illinois
Counties
- Cook County36 data center projects tracked
- DeKalb County1 data center project tracked
- DuPage County6 data center projects tracked
- Kendall County6 data center projects tracked
- Lake County2 data center projects tracked
- Macon County1 data center project tracked
- Sangamon County2 data center projects tracked
- Will County1 data center project tracked
Cities and towns
- Chicago13 data center projects tracked
- Elk Grove Village13 data center projects tracked
- Northlake4 data center projects tracked
- Yorkville4 data center projects tracked
- Aurora3 data center projects tracked
- Hoffman Estates3 data center projects tracked
- DeKalb1 data center project tracked
- Decatur1 data center project tracked
- Des Plaines1 data center project tracked
- Franklin Park1 data center project tracked
- Grayslake1 data center project tracked
- Itasca1 data center project tracked
- Joliet1 data center project tracked
- Lisle1 data center project tracked
- Lombard1 data center project tracked
- Mount Prospect1 data center project tracked
- Oak Brook1 data center project tracked
- Volo1 data center project tracked
- Wood Dale1 data center project tracked
For homeowners
What the projects here mean if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
Property tax
Meta DeKalb Data Center:The campus pays property tax, with 55 percent of the tax on new construction abated for 20 years per phase under the Enterprise Zone.
Comes to the community
Tax breaks
Meta DeKalb Data Center:Three tax deals cover this campus: a 20-year 55 percent property tax abatement, exemptions DCEO estimates at $50 million, and a capped electricity tax.
Comes to the community
Money for schools and services
Meta DeKalb Data Center:Meta gives local grants, including $50,000 to the school district for STEM materials in 2022, and partners with NIU on a STEAM studio.
Comes from the community
Electricity bill
Meta DeKalb Data Center:ComEd supplies the campus's power; its city electricity tax is capped for 20 years, and Meta reports 372,339 megawatt-hours used in 2024.
Comes to the community
Water
Meta DeKalb Data Center:City water serves the campus and the Kishwaukee district takes its wastewater; withdrawals rose from zero in 2021 to 105 million liters in 2024.
Comes to the community
Jobs
Meta DeKalb Data Center:The campus supports more than 200 jobs in operation and created more than 1,200 construction jobs, per the Governor's office at the 2023 opening.
Comes from the community
Next door: height, setbacks, noise
Meta DeKalb Data Center:Approved as a planned development under a city-approved site plan; its height and setback numbers are in plan sheets the ordinance omits.
Not known yet
Your say
Meta DeKalb Data Center:Residents could testify at public hearings in April 2020 before the council approved the annexation, rezoning, and development agreement, each by an 8-0 vote.
How to take part
Tax breaks and payments
2020 · Meta DeKalb Data Center
Municipal electricity tax exemption (City of DeKalb Ordinance 2020-031; Annexation and Development Agreement Section 5.5(a))
The City exempts the percentage of its electricity tax on electricity used or consumed by the project that is necessary to make the effective rate $0.00045 per kWh, for 20 calendar years beginning the first full calendar year that is two years after the project is fully energized; the company pays the City at least $125,000 per year during the exemption.
All tax records for Meta DeKalb Data Center2021 · Meta DeKalb Data Center
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
Sales and use tax exemptions (and in some cases tax credits) for up to 20 years under a Data Center Investment Program memorandum of understanding entered in 2021; exemption certificates are issued in 5-year renewable terms.
All tax records for Meta DeKalb Data Center2020 · Meta DeKalb Data Center
Property tax abatement (DeKalb County Enterprise Zone, 20 ILCS 655)
55 percent of the property taxes on the increased assessed valuation attributable to new construction is abated, for taxes levied in years 1 through 20 of abatement, for each phase of the project (Ordinance 2020-003, Section 2.F.5).
All tax records for Meta DeKalb Data CenterSales and use tax exemptions and credits (20 ILCS 605/605-1025)
Under a memorandum of understanding with the Department of Commerce and Economic Opportunity, a qualifying data center is exempt from the Retailers' Occupation Tax, the Use Tax, the Service Use Tax, and the Service Occupation Tax, all state-administered local retailers' occupation taxes, and the Chicago non-titled use tax on qualifying purchases. Exemption certificates are issued in five-year increments, renewable up to 20 years in total. A project in an underserved area may also receive a credit equal to 20 percent of the wages paid to construction workers.
2020 · STACK CHI01 (Elk Grove Village)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for STACK CHI01 (Elk Grove Village)2020 · T5@Chicago (Chicago I and II)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for T5@Chicago (Chicago I and II)2021 · QTS Chicago Mega Data Center
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for QTS Chicago Mega Data Center2021 · Digital Realty Elk Grove Village Campus (CH1/CH2/CH3)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Digital Realty Elk Grove Village Campus (CH1/CH2/CH3)2021 · Microsoft Hoffman Estates Campus
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Microsoft Hoffman Estates Campus2021 · Microsoft Northlake Data Center (CH1)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Microsoft Northlake Data Center (CH1)2020 · Microsoft Elk Grove Village Campus
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Microsoft Elk Grove Village Campus2021 · Aligned Chicago Campus (ORD-01, ORD-02)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Aligned Chicago Campus (ORD-01, ORD-02)2020 · CoreSite Chicago Campus (CH1, CH2)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for CoreSite Chicago Campus (CH1, CH2)2020 · Digital Realty Franklin Park Campus (ORD12/ORD13/ORD14)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Digital Realty Franklin Park Campus (ORD12/ORD13/ORD14)2020 · NTT Chicago Campus (Itasca)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for NTT Chicago Campus (Itasca)2023 · Serverfarm CH1 (840 South Canal)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Serverfarm CH1 (840 South Canal)2023 · Metro Edge IMD1 (Illinois Medical District)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Metro Edge IMD1 (Illinois Medical District)2022 · CyrusOne Aurora Campus (CHI1-CHI3)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for CyrusOne Aurora Campus (CHI1-CHI3)2023 · EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)2023 · Prime ORD Chicago Campus
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Prime ORD Chicago Campus2023 · Aligned Elk Grove Village Campus (ORD-03)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Aligned Elk Grove Village Campus (ORD-03)2024 · Equinix Elk Grove Village Campus (CH3, CH5)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Equinix Elk Grove Village Campus (CH3, CH5)2025 · T5@Chicago IV Grayslake Campus
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for T5@Chicago IV Grayslake Campus2024 · CyrusOne Aurora Campus (CHI1-CHI3)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for CyrusOne Aurora Campus (CHI1-CHI3)2024 · CyrusOne Wood Dale Campus
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for CyrusOne Wood Dale Campus2024 · CyrusOne CHI-11 West Yorkville Campus
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for CyrusOne CHI-11 West Yorkville Campus2021 · CloudHQ Mount Prospect Campus (Mount Prospect Technology Campus)
Property tax classification incentive (Cook County Class 6b); Village resolutions supporting the application
All tax records for CloudHQ Mount Prospect Campus (Mount Prospect Technology Campus)2023 · Chirisa Volo Data Center
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Chirisa Volo Data Center2025 · Centersquare ORD2 (Elk Grove Village)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Centersquare ORD2 (Elk Grove Village)2025 · EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)2025 · Centersquare ORD4 (Lisle)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Centersquare ORD4 (Lisle)2024 · Iron Mountain CHI-1 (Des Plaines)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Iron Mountain CHI-1 (Des Plaines)2025 · HydraVault Chicago
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for HydraVault Chicago2024 · T5@CHI III Northlake
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for T5@CHI III Northlake
Recent cases and dockets in Illinois
- Court case · DismissedCaruthers et al. v. County of Sangamon, Sangamon County Board, and C1 Sangamon I LLC (CyrusOne conditional use permit)
- Utility commission · DecidedCommonwealth Edison Company, changes to new service requests for large demand project applicants or customers and revisions to Rider DE
- Utility commission · Pending before the commissionInvestigation of possible ratepayer protections and cost recovery mechanisms for servicing large demand project applicants or customers of Commonwealth Edison Company
Bills and laws in Illinois
- HB 5826 · Filed · Oct 19, 2026Requires hourly energy accounting and clean certificates for covered data centers
- SB 4016 · In committee · May 22, 2026Environmental, water, and energy rules for hyperscale data centers
- SB 3761 · In committee · May 22, 2026Data center disclosure to the Commerce Commission and water reporting
- SB 3830 · In committee · May 22, 2026Would establish the data center self-direct program and related data center provisions
- SB 3120 · In committee · May 22, 2026Would tie the state data center incentive to a water stewardship strategy
- SB 3030 · In committee · May 22, 2026Would require cryptocurrency mining facilities to use noise-reduction techniques
- SB 2181 · In committee · May 22, 2026Would require annual energy and water reporting by Illinois data centers
- SB 3761 · In committee · May 22, 2026Requires data center disclosures and creates a clean energy self-direct program
- SB 4004 · In committee · May 22, 2026Would create the Data Center Water Transparency and Aquifer Protection Act
- SB 4016 · In committee · May 22, 2026Would set environmental, water and energy rules for hyperscale data centers
- SB 4203 · In committee · May 13, 2026Would change the data center incentive program, including the data center certificate of exemption
- HB 5755 · In committee · May 5, 2026Would require referendum approval for the siting of a data center under the Municipal Code
- HB 5513 · In committee · Mar 27, 2026Environmental, water, and energy rules for hyperscale data centers
- HB 5513 · In committee · Mar 27, 2026Would set environmental, water and energy rules for hyperscale data centers
- HB 5607 · In committee · Mar 27, 2026Would require each covered data center to self-generate or procure and then retire eligible energy attribute certificates
- HR 744 · In committee · Mar 24, 2026Urges all data centers in Illinois to provide their own energy
- HB 4989 · In committee · Feb 6, 2026Requires heat reuse plans and liquid cooling for large data centers
- SB 3578 · In committee · Feb 5, 2026Would bar a foreign adversary company from constructing a data center in Illinois unless a joint state study certifies the energy used is a new self-generated load
- HB 4116 · In committee · Oct 15, 2025Would set new large load energy and water reporting requirements, an investigation into colocation and rate design, and an Interconnection Working Group and Interconnection Monitor
- HB 4120 · In committee · Oct 15, 2025Would set new large load energy and water reporting requirements, an investigation into colocation and rate design, and an Interconnection Working Group and Interconnection Monitor
- SB 2008 · In committee · Jul 2, 2025Grocery Initiative bill whose House Committee Amendment No. 1 synopsis makes changes concerning data centers
- SB 2290 · In committee · Jun 2, 2025Would provide that a data center, for the sales and use tax provisions amended, also includes a quantum research facility
- HB 3574 · In committee · Jun 2, 2025Would require State data storage contracts to keep State data within the United States, with bid credits for storage in Illinois and in opportunity zones; contains provisions concerning data centers
- SB 2502 · In committee · Apr 11, 2025Would require State data storage contracts to keep State data within the United States, with bid credits for storage in Illinois and in opportunity zones; contains provisions concerning data centers
- HB 3565 · In committee · Mar 21, 2025Would add an income tax credit equal to 5 percent of investment in a qualifying Illinois data center in an opportunity zone or developed by a minority-owned, women-owned, or disability-owned business
- HB 3587 · In committee · Feb 18, 2025Would require State data storage contracts to keep State data within the United States, with bid credits for storage in Illinois and in opportunity zones; contains provisions concerning data centers
- SB 0227 · In committee · Jan 22, 2025Would add an income tax credit equal to 5 percent of investment in a qualifying Illinois data center in an opportunity zone or developed by a minority-owned, women-owned, or disability-owned business
- SB 0094 · In committee · Jan 17, 2025Would bar a foreign adversary company from constructing a data center in Illinois unless a joint state study certifies the energy used is a new self-generated load
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Illinois?
- Data Center Fact Check tracks 55 data center projects in Illinois as of November 2026. Of those, 32 operating, 10 under construction and 7 approved.
- What is the biggest data center in Illinois?
- By announced capacity, the biggest data center in Illinois is Joliet Technology Center, announced at 1,800 MW. It is approved.
- How much power do data centers in Illinois use?
- The 55 projects tracked in Illinois have announced about 5,561 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Ordinance 2020-003 Amending the Property Tax Abatement Qualifying Criteria and Definitions in the DeKalb County Enterprise Zone
City of DeKalb, IllinoisTier 1 · Open the source - 2Ordinance 2020-023 Approving an Annexation and Development Agreement with Ventus Tech Services, LLC (Project Ventus)
City of DeKalb, IllinoisTier 1 · Open the source - 3Data Center Investment Program 2025 Annual Report
Illinois Department of Commerce and Economic OpportunityTier 1 · Open the source - 4Ordinance 2020-031 Authorizing an Effective Electrical Utility Tax Rate for Electricity Used or Consumed by Ventus Tech Services, LLC (Project Ventus) in the City of DeKalb, Illinois
City of DeKalb, IllinoisTier 1 · Open the source - 5
- 6Governor Pritzker Announces Meta DeKalb Data Center Now Fully Operational
Office of the Governor, State of IllinoisTier 1 · Open the source - 7
- 8DCEO: Facebook Announces $800 Million Investment in Illinois Community for New Data Center (Illinois DCEO release, 2020-06-30, republished)
Illinois Department of Commerce and Economic OpportunityTier 1 · Open the source - 9
- 10Ordinance 2020-026 (Ventus rezoning to PD-I, planned development plans and plat, UDO text amendment)
City of DeKalb, IllinoisTier 1 · Open the source - 11Minutes of the Regular City Council Meeting of April 27, 2020
City of DeKalb, Illinois (Office of the City Clerk)Tier 1 · Open the source - 12Ordinance 2020-025 Approving the Annexation of Certain Property to the City of DeKalb, Illinois for the Ventus Tech Services, LLC
City of DeKalb, IllinoisTier 1 · Open the source - 13Data Center Investment Program, 2025 Annual Report
Illinois Department of Commerce and Economic OpportunityTier 1 · Open the source - 14Data Center Investment Program (program page)
Illinois Department of Commerce and Economic OpportunityTier 1 · Open the source - 15
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Illinois." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-il
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page