Elk Grove Village,Cook County,IllinoisAnnouncedFirst public 2025Last checked Nov 8, 2026
STACK InfrastructureDeveloper and operatorRiverbend IndustriesDeveloperComEdElectric utility
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
STACK CHI02 is an announced data center project in Elk Grove Village, Cook County, Illinois. STACK Infrastructure is named as operator. It was first public in 2025. It was announced at 36 MW.
STACK CHI02 is an announced data center project in Elk Grove Village, Cook County, Illinois. STACK Infrastructure is named as operator. It was announced at 36 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Elk Grove Village, Cook County, Illinois. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of STACK CHI02Announced
Bills and laws in Illinois
- HB 5826 · Filed · Oct 19, 2026Requires hourly energy accounting and clean certificates for covered data centers
- SB 2181 · In committee · May 22, 2026Would require annual energy and water reporting by Illinois data centers
- SB 3120 · In committee · May 22, 2026Would tie the state data center incentive to a water stewardship strategy
- SB 3030 · In committee · May 22, 2026Would require cryptocurrency mining facilities to use noise-reduction techniques
- SB 4016 · In committee · May 22, 2026Would set environmental, water and energy rules for hyperscale data centers
- SB 3761 · In committee · May 22, 2026Requires data center disclosures and creates a clean energy self-direct program
Who's involved
- Developer and operatorSTACK Infrastructure
- DeveloperRiverbend Industries
- Electric utilityComEd
Power
Capacity, as announced or filed
- 36 MW · Mar 2025 · what the figure measures is not stated
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is STACK CHI02?
- STACK CHI02 is a data center project in Elk Grove Village, Cook County, Illinois.
- Who operates STACK CHI02?
- STACK Infrastructure is named as the operator of STACK CHI02.
- How big is STACK CHI02?
- STACK CHI02 was announced at 36 MW of capacity. The site covers 18 acres.
- What stage is STACK CHI02?
- STACK CHI02 is announced. It was first public in 2025.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1STACK Infrastructure Announces New 36MW Data Center in Chicago
STACK InfrastructureTier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page