Data centers in Cook County, Illinois

Last checked Nov 13, 2026

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 36 data center projects in Cook County, Illinois as of November 2026: 24 operating, 7 under construction and 2 expanding, totaling about 832 MW announced where a figure is published.

Cook County has 36 tracked data centers. Their announced capacity totals about 832 MW where a figure is published. Of those, 24 operating, 7 under construction and 2 expanding. Every figure comes from the public record linked on this page.

HydraVault Chicago video · 2 min 13 sec

Full project file: HydraVault Chicago

36Data center projects we track
0.384Real property tax rate, USD per 100 USD of assessed value, 2023

Data center projects in Cook County

Who serves this place

  • Not collected yet.

A data center is proposed in Cook County

2 projects here are at the announced or proposed stage. Before the hearing, the resident checklist walks through what to check: the proposal's documents, the local rules where you live, the tax agreement, and the recorded votes.

Open the resident checklist

Places in and around Cook County

Cook County is part of Illinois.

Cities and towns

Nearby places

Taxes and budget over time

As published by the county, not adjusted for inflation. Projections are labeled.

Total property tax revenue

Total property tax revenue by year
FY 2024$670.5 million
FY 2023$672.1 million

Real property tax rate

Real property tax rate by year
20230.384 USD per 100 USD of assessed value
20220.431 USD per 100 USD of assessed value

Tax breaks and payments

  • 2020 · STACK CHI01 (Elk Grove Village)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for STACK CHI01 (Elk Grove Village)
  • 2020 · T5@Chicago (Chicago I and II)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for T5@Chicago (Chicago I and II)
  • 2021 · QTS Chicago Mega Data Center

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for QTS Chicago Mega Data Center
  • 2021 · Digital Realty Elk Grove Village Campus (CH1/CH2/CH3)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Digital Realty Elk Grove Village Campus (CH1/CH2/CH3)
  • 2021 · Microsoft Hoffman Estates Campus

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Microsoft Hoffman Estates Campus
  • 2021 · Microsoft Northlake Data Center (CH1)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Microsoft Northlake Data Center (CH1)
  • 2020 · Microsoft Elk Grove Village Campus

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Microsoft Elk Grove Village Campus
  • 2021 · Aligned Chicago Campus (ORD-01, ORD-02)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Aligned Chicago Campus (ORD-01, ORD-02)
  • 2020 · CoreSite Chicago Campus (CH1, CH2)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for CoreSite Chicago Campus (CH1, CH2)
  • 2020 · Digital Realty Franklin Park Campus (ORD12/ORD13/ORD14)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Digital Realty Franklin Park Campus (ORD12/ORD13/ORD14)
  • 2023 · Serverfarm CH1 (840 South Canal)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Serverfarm CH1 (840 South Canal)
  • 2023 · Metro Edge IMD1 (Illinois Medical District)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Metro Edge IMD1 (Illinois Medical District)
  • 2023 · EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)
  • 2023 · Prime ORD Chicago Campus

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Prime ORD Chicago Campus
  • 2023 · Aligned Elk Grove Village Campus (ORD-03)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Aligned Elk Grove Village Campus (ORD-03)
  • 2024 · Equinix Elk Grove Village Campus (CH3, CH5)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Equinix Elk Grove Village Campus (CH3, CH5)
  • 2021 · CloudHQ Mount Prospect Campus (Mount Prospect Technology Campus)

    Property tax classification incentive (Cook County Class 6b); Village resolutions supporting the application

    All tax records for CloudHQ Mount Prospect Campus (Mount Prospect Technology Campus)
  • 2025 · Centersquare ORD2 (Elk Grove Village)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Centersquare ORD2 (Elk Grove Village)
  • 2025 · EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)
  • 2024 · Iron Mountain CHI-1 (Des Plaines)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Iron Mountain CHI-1 (Des Plaines)
  • 2025 · HydraVault Chicago

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for HydraVault Chicago
  • 2024 · T5@CHI III Northlake

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for T5@CHI III Northlake

Court cases and commission dockets in Illinois (3)

Bills and laws in Illinois

All 28 in Bill Watch

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Questions people ask

How many data centers are in Cook County?
Data Center Fact Check tracks 36 data center projects in Cook County as of November 2026. Of those, 24 operating, 7 under construction and 2 expanding.
What is the biggest data center in Cook County?
By announced capacity, the biggest data center in Cook County is Compass Datacenters Chicago Campus (Hoffman Estates; 200 MW campus), announced at 200 MW. It is operating.
How much power do data centers in Cook County use?
The 36 projects tracked in Cook County have announced about 832 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.

Sources

  1. 1
    Annual Comprehensive Financial Report for the fiscal year ended November 30, 2024
    Cook County, Illinois
    Tier 1 · Open the source
  2. 2
    Data Center Investment Program 2025 Annual Report
    Illinois Department of Commerce and Economic Opportunity
    Tier 1 · Open the source
  3. 3
    Cloud HQ Data Center | Village of Mount Prospect
    Village of Mount Prospect
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Cook County." Last checked 2026-11-13. Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-il-cook

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page