Project File
Prime ORD Chicago Campus
Elk Grove Village,Cook County,IllinoisUnder constructionFirst public 2021Last checked Nov 13, 2026
Prime Data CentersDeveloper and operatorClune ConstructionBuilderComEdElectric utilityElk Grove VillagePublic partner
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Prime ORD Chicago Campus is a under-construction data center project in Elk Grove Village, Cook County, Illinois. Prime Data Centers is named as operator. It was first public in 2021. It was announced at 180 MW.
Prime ORD Chicago Campus is an under-construction data center project in Elk Grove Village, Cook County, Illinois. Prime Data Centers is named as operator. It was announced at 180 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Elk Grove Village, Cook County, Illinois. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
Prime ORD Chicago Campus video · 2 min 26 sec
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Timeline
- · Tax dealTax agreement approved: Sales and use tax exemptions and credits (20 ilcs 605/605-1025) for Elk Grove Village Property LLC (Phase 1)State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benef...
- · New projectFirst public record of Prime ORD Chicago CampusUnder construction
Bills and laws in Illinois
- HB 5826 · Filed · Oct 19, 2026Requires hourly energy accounting and clean certificates for covered data centers
- SB 2181 · In committee · May 22, 2026Would require annual energy and water reporting by Illinois data centers
- SB 3120 · In committee · May 22, 2026Would tie the state data center incentive to a water stewardship strategy
- SB 3030 · In committee · May 22, 2026Would require cryptocurrency mining facilities to use noise-reduction techniques
- SB 4016 · In committee · May 22, 2026Would set environmental, water and energy rules for hyperscale data centers
- SB 3761 · In committee · May 22, 2026Requires data center disclosures and creates a clean energy self-direct program
Who's involved
- Developer and operatorPrime Data Centers
- BuilderClune Construction
- Electric utilityComEd
- Public partnerElk Grove Village
Power
Capacity, as announced or filed
- 150 MW · Sep 2021 · what the figure measures is not stated
- 175 MW · Nov 2022 · what the figure measures is not stated
- 72 MW · ORD-01Nov 2022 · what the figure measures is not stated
- 180 MW · Nov 2026 · what the figure measures is not stated
Public records
1 records found so far. 8 kinds of record are still being collected.
See every recordQuestions people ask
- Where is Prime ORD Chicago Campus?
- Prime ORD Chicago Campus is a data center project in Elk Grove Village, Cook County, Illinois.
- Who operates Prime ORD Chicago Campus?
- Prime Data Centers is named as the operator of Prime ORD Chicago Campus.
- How big is Prime ORD Chicago Campus?
- Prime ORD Chicago Campus was announced at 180 MW of capacity.
- What stage is Prime ORD Chicago Campus?
- Prime ORD Chicago Campus is under construction. It was first public in 2021.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Data Center Investment Program 2025 Annual Report
Illinois Department of Commerce and Economic OpportunityTier 1 · Captured 2026-11-09 · Open the source - 2Prime Data Centers Breaks Ground on $1B Chicago Data Center Campus in Elk Grove Village
Prime Data CentersTier 4 · Captured 2026-11-08 · Open the source - 3Prime tops out first Chicago data center
Data Center DynamicsTier 3 · Captured 2026-11-08 · Open the source - 4This Week's Chicago Deal Sheet (Prime Data Centers, Elk Grove Village)
BisnowTier 3 · Captured 2026-11-08 · Open the source - 5Elk Grove Village Project Developments
Village of Elk Grove VillageTier 1 · Captured 2026-11-08 · Open the source - 6U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page