What the record shows
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
Per SpaceX's Form 424B4, xAI Colossus 2 in Memphis runs two clusters online: about 110,000 GB200 processors at about 210 MW, and 110,000 GB300 processors at 220 MW, 430 MW in total.
By Bear Harper · Published November 22, 2026
Per SpaceX's Form 424B4, xAI Colossus 2 in Memphis runs two clusters online: about 110,000 GB200 processors at about 210 MW, and 110,000 GB300 processors at 220 MW, 430 MW in total. The first Colossus campus, also in Memphis, is listed at 300 MW. The filing's stated next phase for Colossus 2, at least 220,000 additional GB300 processors and over 400 additional MW, is described as expected once fully operational. It is not online, and this article does not count it.
The count comes from the final prospectus SpaceX filed with the U.S. Securities and Exchange Commission on June 12, 2026, after acquiring xAI in February 2026. Writing about the campus it calls COLOSSUS II, in Whitehaven, Memphis, the filing states that the company "brought online the first cluster of approximately 110,000 GB200 processors, approximately 210 megawatts of compute power," in 91 days, and then "the second cluster of 110,000 GB300 processors and 220 megawatts of compute power in 64 days." Together the two clusters total 220,000 processors and 430 MW online. Data Center Fact Check's record holds the filing, the permits, and the utility documents behind both Memphis campuses, and this article lays them side by side.
xAI Colossus 2 video · 2 min 19 sec
| Cluster | Processors | Compute power | Days to online |
|---|---|---|---|
| First cluster, GB200 | About 110,000 | About 210 MW | 91 |
| Second cluster, GB300 | 110,000 | 220 MW | 64 |
Colossus 2, from the record
430
MW online (IT load)
IT load the record states as brought online at this project
1,240.16
MW of dedicated generation
Permitted capacity of this project's dedicated generating plant

The first campus
Colossus came first. The Greater Memphis Chamber announced on June 5, 2024, that xAI would build its supercomputer at the former Electrolux plant on Paul R. Lowry Road in southwest Memphis, on 552 leased acres. The record's project entry, sourced to the Chamber, puts the campus live on August 8, 2024, 64 days after the announcement, reaching 100,000 GPUs in September 2024 and 200,000 in December 2024, at about 300 MW. In May 2026, Anthropic and xAI posts put the campus's accessible capacity at more than 300 MW and over 220,000 NVIDIA GPUs, naming H100, H200, and GB200 accelerators. Those are the companies' own posts, and the record labels them as such.
xAI Colossus video · 2 min 5 sec

Where the power comes from
Colossus draws on the grid and on its own turbines. The Tennessee Valley Authority board approved a 150 MW firm power arrangement for the site in November 2024, delivered by Memphis Light, Gas and Water. MLGW's May 2025 update describes two successive 150 MW increments requested for the facility, 300 MW in total, with new substations built at xAI's expense. Beside the grid supply, a Shelby County construction permit issued July 2, 2025, covers 15 Solar gas turbines at 16.48 MW each, 247.2 MW of on-site generation. The record carries a caveat on that permit: the county's own copy returned an error when checked, and the staged text was read from a complete hosted copy of the issued permit, so the record grades the turbine figure reported, not confirmed.
Colossus 2's power sits in another state. MLGW's statement gives the Whitehaven campus only a small general-services supply. Its main power is generated behind the meter at a dedicated plant at 2875 Stanton Road in Southaven, Mississippi, permitted by the Mississippi Department of Environmental Quality. The permit, issued March 11, 2026, covers 41 gas turbines in three groups totaling 1,240.16 MW of generating capacity, with Tesla battery packs for backup and peak demand, and no export to the grid. That 1,240.16 MW is the plant's capacity. The campus it feeds is the 430 MW the filing counts, and the two figures are not interchangeable.
The public record around the campuses
The benefit side is in the same documents. The Colossus campus pays full property taxes, and in August 2025 the Memphis City Council voted to steer part of that revenue to the surrounding area, per the council minutes in the record. No tax break or incentive agreement for either campus appears in any record read for the project's file, and Colossus 2's tax bills are not published.
The contested side is also documentary. Shelby County commissioners urged a public hearing before the Colossus turbine permit decision, citing the South Memphis site. For the Southaven plant, the Mississippi record holds a public comment period and a noticed public hearing before the permit issued, an evidentiary hearing on the issued permit set for November 9, 2026, and a federal lawsuit noted in the project's record. Both campuses also run on water the record can describe only narrowly: MLGW supplies Colossus, where xAI is building a recycled water plant next door, and Colossus 2 is served through a pre-existing 8-inch water main with no request for more in the utility's records.
What the record does not show
No record read for Colossus 2 states a jobs or investment figure for that campus alone, and no community payment or benefit agreement for it appears in the records read. The processor counts are the filing's own statements; no independent count exists. The record also cannot show the campuses as they stand today from the air: the only aerial frames staged for either site are USDA NAIP frames from October 2021, before either campus was built, and the videos below carry the current views instead. The project pages hold the full files: xAI Colossus and xAI Colossus 2. A reader who wants to price a cluster of this size can run the GPU cluster power calculator against the filing's megawatt figures.
xAI Colossus 2 video · 2 min 19 sec
Sources
- Form 424B4 final prospectus (SpaceX, filed June 12, 2026) · Space Exploration Technologies Corp, filed with the U.S. Securities and Exchange Commission · June 12, 2026 · Business section, COLOSSUS II cluster passage
- 2025 xAI Update (MLGW published briefing, May 2025) · Memphis Light, Gas and Water · May 2, 2025
- Greater than 100 MW firm power arrangement with CTC Property LLC (xAI), TVA Board of Directors presentation, November 7, 2024 · Tennessee Valley Authority · November 7, 2024 · Greater than 100 MW firm power arrangement with CTC Property LLC
- Air Pollution Control Permit and Prevention of Significant Deterioration (PSD) Authority to Construct Air Emissions Equipment, Permit No. 0680-00119, MZX Tech LLC, issued March 11, 2026 · Mississippi Department of Environmental Quality · March 11, 2026 · PSD Permit No. 0680-00119, MZX Tech LLC
- Construction Permit No. 01156-01PC, CTC Property LLC (Colossus Data Center), issued July 2, 2025 · Shelby County Health Department · July 2, 2025 · Construction Permit No. 01156-01PC, CTC Property LLC; text read from a hosted copy of the issued permit
- Velocity Meets Potency: xAI Announces Memphis as New Home (press release, June 5, 2024) · Greater Memphis Chamber · June 5, 2024
- Higher limits and a new compute partnership with SpaceX (Anthropic news post, May 6, 2026) · Anthropic · May 6, 2026 · The companies' own posts (Tier 2)
- Minutes, Meeting of the City Council, City of Memphis, August 19, 2025 · City of Memphis · August 19, 2025
- Staged record: projects.csv, project_capacity.csv, document_facts.csv, and impact_statements.csv rows for proj-xai-colossus and proj-xai-colossus-2 · Data Center Fact Check · Checked November 22, 2026
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days." Published 2026-11-22. Accessed 2026-11-29. https://datacenterfactcheck.org/articles/ai-training-colossus