Utility
ComEd
Legal name: Commonwealth Edison CompanyWebsite
Draft research, not yet verified: traced to sources by an AI research agent.
Roles on projects we track
Electric utility
Compass Hoffman Estates Campus (former Sears HQ)Under constructionElectric utility
CyrusOne Aurora Bilter Road CampusUnder constructionElectric utility
Joliet Technology CenterApprovedElectric utility
Meta DeKalb Data CenterOperatingElectric utility
Prime ORD Chicago CampusUnder constructionElectric utility
STACK CHI02AnnouncedElectric utility
Stream ORDC CampusUnder constructionElectric utility
T5@Chicago IV Grayslake CampusUnder construction
Lobbying and political contributions
Lobbying and political giving are legal. These are the disclosures the law requires, shown as filed and matched to this company by the identifiers in the filings. We draw no conclusions about motive or effect.
Lobbying filings: 0
None in our records.
Political contributions: 0
None in our records.
Sources
- 1ComEd Announces New Agreements Signed to Ensure Large Load Customers Pay their Fair Share to Connect with and Use the Grid
ComEd (Business Wire)Tier 4 · Open the source - 2Compass Datacenters marks milestone with Building 1 topping off at Hoffman Estates campus
Chicago Construction NewsTier 3 · Open the source - 3
- 4Construction of $350M CyrusOne data center sets to begin in Aurora
Chicago TribuneTier 3 · Open the source - 5Approval given to $20bn data center near Chicago, Illinois
Data Center DynamicsTier 3 · Open the source - 6Governor Pritzker Announces Meta DeKalb Data Center Now Fully Operational
Office of the Governor, State of IllinoisTier 1 · Open the source - 7Prime Data Centers Breaks Ground on $1B Chicago Data Center Campus in Elk Grove Village
Prime Data CentersTier 4 · Open the source - 8STACK Infrastructure Announces New 36MW Data Center in Chicago
STACK InfrastructureTier 4 · Open the source - 9Stream, ComEd and Elk Grove Village Break Ground on New Substation for Stream's Third Campus (ORDC)
Stream Data CentersTier 4 · Open the source - 10Data Center Could Be Largest Lake County, Ill., Development
Chicago Tribune (via Government Technology)Tier 3 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "ComEd." Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/companies/comed
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page