Meta DeKalb Data Center

DeKalb,DeKalb County,IllinoisOperatingFirst public 2020Filing entity: Ventus Tech Services, LLCLast checked Nov 9, 2026

MetaDeveloper and operatorGoldframeDeveloperKrusinski ConstructionBuilderComEdElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Electric utility
  • Confirmed: First public date
  • Still to confirm: Capacity
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Meta DeKalb Data Center is an operating data center project in DeKalb, DeKalb County, Illinois. Meta is named as operator. It was first public in 2020. No site capacity figure is published for this project.

Meta DeKalb Data Center is an operating data center project in DeKalb, DeKalb County, Illinois. Meta is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in DeKalb, DeKalb County, Illinois. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

22Public records we have found
3Tax agreements on record

For homeowners

What this project means if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

    The campus pays property tax, with 55 percent of the tax on new construction abated for 20 years per phase under the Enterprise Zone.

    Comes to the community
  2. Tax breaks

    Three tax deals cover this campus: a 20-year 55 percent property tax abatement, exemptions DCEO estimates at $50 million, and a capped electricity tax.

    Comes to the community
  3. Money for schools and services

    Meta gives local grants, including $50,000 to the school district for STEM materials in 2022, and partners with NIU on a STEAM studio.

    Comes from the community
  4. Electricity bill

    ComEd supplies the campus's power; its city electricity tax is capped for 20 years, and Meta reports 372,339 megawatt-hours used in 2024.

    Comes to the community
  5. Water

    City water serves the campus and the Kishwaukee district takes its wastewater; withdrawals rose from zero in 2021 to 105 million liters in 2024.

    Comes to the community
  6. Jobs

    The campus supports more than 200 jobs in operation and created more than 1,200 construction jobs, per the Governor's office at the 2023 opening.

    Comes from the community
  7. Next door: height, setbacks, noise

    Approved as a planned development under a city-approved site plan; its height and setback numbers are in plan sheets the ordinance omits.

    Not known yet
  8. Your say

    Residents could testify at public hearings in April 2020 before the council approved the annexation, rezoning, and development agreement, each by an 8-0 vote.

    How to take part

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows DeKalb County, Illinois.See every project on the map

The land, to scale

One football field
505.33 acres, about 382 football fields. Drawn as a square for scale; the real shape is not known.

Timeline

  1. · DecisionOffice of the Governor, State of Illinois: Announces the Meta DeKalb Data Center fully operational and serving traffic for Meta DeKalb Data CenterPress release of November 29, 2023
  2. · DecisionMeta: Announces the DeKalb data center is online and serving traffic for Meta DeKalb Data CenterMeta data center site post of November 29, 2023
  3. · FilingFiled with Meta for Meta DeKalb Data CenterMeta data center site post of November 29, 2023
  4. · FilingFiled with Office of the Governor, State of Illinois for Meta DeKalb Data CenterPress release of November 29, 2023
  5. · DecisionMeta: Announces the expansion of the DeKalb campus from two buildings to five, more than doubling its square footage for Meta DeKalb Data CenterMeta data center site post of April 27, 2022
  6. · FilingFiled with Meta for Meta DeKalb Data CenterMeta data center site post of April 27, 2022
  7. · DecisionIllinois Department of Commerce and Economic Opportunity: Memorandum of understanding entered with Goldframe LLC in 2021 under the Data Center Investment Program (20 ILCS 605/605-1025), per DCEO's published MOU table for Meta DeKalb Data CenterData Center Investment Program MOU (Goldframe LLC, DeKalb)
  8. · FilingFiled with Illinois Department of Commerce and Economic Opportunity for Meta DeKalb Data CenterData Center Investment Program MOU (Goldframe LLC, DeKalb)
All 26 events for this project

Bills and laws in Illinois

All 28 in Bill Watch

Who's involved

Power and water

Water, as reported by the operator

DeKalb (IL) facility as named in Meta's 2025 Environmental Data Index

  • 2024 · Withdrawal: 105 ML
  • 2023 · Withdrawal: 55 ML
  • 2022 · Withdrawal: 30 ML
  • 2021 · Withdrawal: 0 ML

From the filings

Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.

  • Illinois Department of Commerce and Economic Opportunity, Data Center Investment Program MOU (Goldframe LLC, DeKalb)

    Stated in the filing
    50 new jobs
    Stated in the filing
    $685.8 million
    Stated in the filing
    $800 million
    Stated in the filing
    $50 million
  • City of DeKalb, Ordinance 2020-025

    Stated in the filing
    505.329 acres
    Stated in the filing
    11-01-100-001; 11-01-200-002; 11-01-200-001; 11-02-100-001; 11-02-200-001 DeKalb County parcel index numbers
  • City of DeKalb, Annexation and Development Agreement (Exhibit B to Ordinance 2020-023)

    Stated in the filing
    970,000 square feet (approximately)
    Stated in the filing
    all impact fees related to the Property or the design, development, construction or occupancy of the Project waived
    Stated in the filing
    20 years
  • City of DeKalb, Ordinance 2020-031

    Stated in the filing
    $125,000 per year
    Stated in the filing
    $0 per kWh
  • City of DeKalb, Ordinance 2020-003

    Stated in the filing
    $800 million
    Stated in the filing
    900,000 square feet of new building space
    Stated in the filing
    50 new full-time jobs located on the property
  • Meta, Meta data center site post of April 27, 2022

    Stated in the filing
    5 buildings
    Stated in the filing
    $50,000
  • Meta, Meta data center site post of November 29, 2023

    Stated in the filing
    1,200 skilled trade workers on site at peak (average)
  • Office of the Governor, State of Illinois, Press release of November 29, 2023

    Stated in the filing
    $1 billion stated as more than $1 billion
    Stated in the filing
    200 jobs (stated as over 200)
    Stated in the filing
    1,200 skilled trade jobs created during construction (stated as over 1,200)
    Stated in the filing
    2,300,000 square feet (stated as 2.3 million)

Public records

22 records found so far. 5 kinds of record are still being collected.

See every record

Questions people ask

Where is Meta DeKalb Data Center?
Meta DeKalb Data Center is a data center project in DeKalb, DeKalb County, Illinois.
Who operates Meta DeKalb Data Center?
Meta is named as the operator of Meta DeKalb Data Center.
How big is Meta DeKalb Data Center?
The site covers 505.33 acres.
What stage is Meta DeKalb Data Center?
Meta DeKalb Data Center is operating. It was first public in 2020.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Data Center Investment Program 2025 Annual Report
    Illinois Department of Commerce and Economic Opportunity
    Tier 1 · Captured 2026-11-09 · Open the source
  2. 2
    Data Center Investment Program 2021 Annual Report
    Illinois Department of Commerce and Economic Opportunity
    Tier 1 · Captured 2026-11-09 · Open the source
  3. 3
    Ordinance 2020-025 Approving the Annexation of Certain Property to the City of DeKalb, Illinois for the Ventus Tech Services, LLC
    City of DeKalb, Illinois
    Tier 1 · Captured 2026-11-09 · Open the source
  4. 4
    Minutes of the Regular City Council Meeting of April 27, 2020
    City of DeKalb, Illinois (Office of the City Clerk)
    Tier 1 · Captured 2026-11-09 · Open the source
  5. 5
    Ordinance 2020-023 Approving an Annexation and Development Agreement with Ventus Tech Services, LLC (Project Ventus)
    City of DeKalb, Illinois
    Tier 1 · Captured 2026-11-09 · Open the source
  6. 6
    Ordinance 2020-031 Authorizing an Effective Electrical Utility Tax Rate for Electricity Used or Consumed by Ventus Tech Services, LLC (Project Ventus) in the City of DeKalb, Illinois
    City of DeKalb, Illinois
    Tier 1 · Captured 2026-11-09 · Open the source
  7. 7
    Ordinance 2020-026 (Ventus rezoning to PD-I, planned development plans and plat, UDO text amendment)
    City of DeKalb, Illinois
    Tier 1 · Captured 2026-11-09 · Open the source
  8. 8
    Ordinance 2020-003 Amending the Property Tax Abatement Qualifying Criteria and Definitions in the DeKalb County Enterprise Zone
    City of DeKalb, Illinois
    Tier 1 · Captured 2026-11-09 · Open the source
  9. 9
    Good news from DeKalb!
    Meta
    Tier 4 · Captured 2026-11-09 · Open the source
  10. 10
    DeKalb, we are online!
    Meta
    Tier 4 · Captured 2026-11-09 · Open the source
  11. 11
    Governor Pritzker Announces Meta DeKalb Data Center Now Fully Operational
    Office of the Governor, State of Illinois
    Tier 1 · Captured 2026-11-09 · Open the source
  12. 12
    ICC looks to develop consumer protection framework amid increase in large energy demand (press release)
    Illinois Commerce Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  13. 13
    Regulators OK ComEd's plan to increase deposit costs for large-load projects like data centers
    Capitol News Illinois
    Tier 3 · Captured 2026-11-08 · Open the source
  14. 14
    Verified Petition to Intervene of the Citizens Utility Board, ICC Docket No. 26-0364
    Illinois Commerce Commission (docket document)
    Tier 1 · Captured 2026-11-08 · Open the source
  15. 15
    ComEd customers could be on hook for billions in data center-related costs, according to consumer advocates' review of utility's records
    Citizens Utility Board
    Tier 4 · Captured 2026-11-08 · Open the source
  16. 16
    DCEO: Facebook Announces $800 Million Investment in Illinois Community for New Data Center (Illinois DCEO release, 2020-06-30, republished)
    Illinois Department of Commerce and Economic Opportunity
    Tier 1 · Captured 2026-11-08 · Open the source
  17. 17
    City of DeKalb Economic Development Projects update, July 2021 (Facebook Data Center, 505 acres)
    City of DeKalb
    Tier 1 · Captured 2026-11-08 · Open the source
  18. 18
    Gov. Pritzker celebrates opening of Meta's DeKalb Data Center (governor's office release, November 2023, republished)
    Office of the Governor of Illinois
    Tier 1 · Captured 2026-11-08 · Open the source
  19. 19
    United States - Meta Data Centers (fleet list incl. Fort Worth)
    Meta
    Tier 4 · Captured 2026-11-08 · Open the source
  20. 20
    Meta 2025 Environmental Data Index
    Meta Platforms, Inc.
    Tier 4 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page