What it is
The tariffs define a class of Large Demand Project Applicants or Customers (LDPACs), in practice data centers, requesting 50 MW or more. The Commission approved ComEd's changes in March 2026, replacing a flat $1 million deposit with a scaled refundable deposit: $1 million for projects of 50 to 200 MW plus $500,000 for each additional 100 MW, with a letter of credit from a U.S. financial institution also required where the deposit would exceed $2 million, protecting the deposit if a project is canceled or abandoned. The new structure does not apply to data centers already on the grid. The order also directed a docketed investigation into stronger ratepayer protections (Docket 26-0364) and a ComEd annual compliance filing. The order records more than 75 large load projects in ComEd's pipeline with combined maximum demand over 28,000 MW, above its all-time system peak.
The facts
- Regulator
- Illinois Commerce Commission
- Docket number
- 25-0677 / 25-0679 (consolidated)
- Type
- Large load tariff
- Utility
- ComEd
- State
- Illinois
- Filed
- Jun 23, 2025
- Status date
- Mar 20, 2026
- Large-load rules
- Yes, for loads of 50 MW or more
Projects served by ComEd
- Chirisa Volo Data Center
- CloudHQ Mount Prospect Campus (Mount Prospect Technology Campus)
- Compass Hoffman Estates Campus (former Sears HQ)
- CoreSite Chicago Campus (CH1, CH2)
- CyrusOne Aurora Campus (CHI1-CHI3)
- Digital Realty ORD10 (350 East Cermak)
- Digital Realty ORD11 (600 South Federal)
- HydraVault Chicago
- Meta DeKalb Data Center
- Microsoft Hoffman Estates Campus
- Microsoft Northlake Data Center (CH1)
- Stream ORDC Campus
Related cases and proceedings
- Court case · DismissedCaruthers et al. v. County of Sangamon, Sangamon County Board, and C1 Sangamon I LLC (CyrusOne conditional use permit)
- Utility commission · Pending before the commissionInvestigation of possible ratepayer protections and cost recovery mechanisms for servicing large demand project applicants or customers of Commonwealth Edison Company
In the record
- Utility case, Jun 23, 2025. Utility case filed: Commonwealth Edison Company, changes to new service requests for large demand project applicants or customers and revisions to Rider DE Illinois Commerce Commission, 25-0677 / 25-0679 (consolidated)
Sources
- 1ICC looks to develop consumer protection framework amid increase in large energy demand (press release)
Illinois Commerce CommissionTier 1 · ICC press release of March 20, 2026 (approval; 50 MW class; deposit protection; 75 applications; investigation directed by April 23, 2026); Capitol News Illinois, March 20, 2026 (deposit scale: $1 million for 50-200 MW plus $500,000 per additional 100 MW; prior flat $1 million) · Open the source - 2Regulators OK ComEd's plan to increase deposit costs for large-load projects like data centers
Capitol News IllinoisTier 3 · ICC press release of March 20, 2026 (approval; 50 MW class; deposit protection; 75 applications; investigation directed by April 23, 2026); Capitol News Illinois, March 20, 2026 (deposit scale: $1 million for 50-200 MW plus $500,000 per additional 100 MW; prior flat $1 million) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Commonwealth Edison Company, changes to new service requests for large demand project applicants or customers and revisions to Rider DE." Last activity 2026-03-20. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-comed-large-load-tariffs-2026