Investigation of possible ratepayer protections and cost recovery mechanisms for servicing large demand project applicants or customers of Commonwealth Edison Company
Where it stands: Pending before the commission
Draft research, not yet verified. Open a source to check any detail.
What it is
Investigation opened on the Commission's own motion under its March 2026 order in Dockets 25-0677/25-0679, which directed initiation by April 23, 2026 and completion within eight months. Advocate testimony filed in the docket (consultant James Fine, for the Citizens Utility Board and allied groups, October 2026) analyzed 30 ComEd large load projects already interconnected or requesting service from 2021 through 2031 and put their transmission and distribution connection cost above $3 billion against about $721 million in deposits and advance commitments, under 25 percent; ComEd disputes that analysis and points to transmission security agreements and letters of credit.
The facts
- Regulator
- Illinois Commerce Commission
- Docket number
- 26-0364
- Type
- Other
- Utility
- ComEd
- State
- Illinois
- Large-load rules
- Yes
Projects served by ComEd
- Chirisa Volo Data Center
- CloudHQ Mount Prospect Campus (Mount Prospect Technology Campus)
- Compass Hoffman Estates Campus (former Sears HQ)
- CoreSite Chicago Campus (CH1, CH2)
- CyrusOne Aurora Campus (CHI1-CHI3)
- Digital Realty ORD10 (350 East Cermak)
- Digital Realty ORD11 (600 South Federal)
- HydraVault Chicago
- Meta DeKalb Data Center
- Microsoft Hoffman Estates Campus
- Microsoft Northlake Data Center (CH1)
- Stream ORDC Campus
Related cases and proceedings
- Court case · DismissedCaruthers et al. v. County of Sangamon, Sangamon County Board, and C1 Sangamon I LLC (CyrusOne conditional use permit)
- Utility commission · DecidedCommonwealth Edison Company, changes to new service requests for large demand project applicants or customers and revisions to Rider DE
Sources
- 1Verified Petition to Intervene of the Citizens Utility Board, ICC Docket No. 26-0364
Illinois Commerce Commission (docket document)Tier 1 · Docket caption in the verified petition to intervene filed in Docket 26-0364 (docketed April 29, 2026, on the Commission's docket system); ICC press release of March 20, 2026 (investigation directed); CUB release of October 22, 2026 (Fine testimony figures) · Open the source - 2ICC looks to develop consumer protection framework amid increase in large energy demand (press release)
Illinois Commerce CommissionTier 1 · Docket caption in the verified petition to intervene filed in Docket 26-0364 (docketed April 29, 2026, on the Commission's docket system); ICC press release of March 20, 2026 (investigation directed); CUB release of October 22, 2026 (Fine testimony figures) · Open the source - 3ComEd customers could be on hook for billions in data center-related costs, according to consumer advocates' review of utility's records
Citizens Utility BoardTier 4 · Docket caption in the verified petition to intervene filed in Docket 26-0364 (docketed April 29, 2026, on the Commission's docket system); ICC press release of March 20, 2026 (investigation directed); CUB release of October 22, 2026 (Fine testimony figures) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Investigation of possible ratepayer protections and cost recovery mechanisms for servicing large demand project applicants or customers of Commonwealth Edison Company." Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-comed-protection-investigation-2026