What the record shows
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
In the territories that publish both numbers, data center power requests run well ahead of signed contracts.
By Bear Harper · Published November 22, 2026
In the territories that publish both numbers, data center power requests run well ahead of signed contracts. Dominion Energy Virginia held about 40 GW of requests in December 2024 against about 9 GW under executed agreements and 3.6 GW actually metered. PPL's pipeline grew from 9 GW of requests in April 2025 testimony to 31.8 GW in August 2026, with 11 GW signed. Requests are expressions of interest. Contracts are the smaller, harder number.
PPL Electric Utilities in Pennsylvania reported the two numbers in the same sentence of its second-quarter 2026 earnings release: a data center pipeline of 31.8 gigawatts in advanced stages of planning, with over 11 gigawatts under signed electric service agreements and more than 6.5 gigawatts under construction. The gap between the first number and the second is the pattern in every territory that publishes both. Data Center Fact Check's record holds 110 load forecast rows from utilities, grid operators, and agencies, and 191 large-load proceedings before regulators. This article lays out the gap, territory by territory, with the publisher and date on every figure.
110
Load forecast rows in the record
Forecasts from utilities, grid operators, and agencies
The funnel, in four territories
Dominion Energy Virginia's figures come from sworn testimony its own witness filed with the Virginia State Corporation Commission. As of December 2024 the company held approximately 40 GW of data center capacity requests, more than twice its 2024 peak demand of 18,408.81 MW. Of that 40 GW, about 9 GW had an executed electric service agreement, about 5 GW more was being built under construction letters, and the industry's metered demand stood at about 3.6 GW. By May 2026, Dominion's own large-load rate class report put 25 GW of new data centers on assigned energization dates through 2031, with a further 45 GW of projects holding no connection date.
AEP Ohio shows what happens when a regulator makes requests cost something. Before Ohio approved AEP Ohio's data center tariff, developers had submitted requests for 30,000 MW. After the tariff took effect, 13,022.7 MW of that interest paid for a study. By February 12, 2026, developers had signed binding contracts under the tariff for 5,642 MW, and AEP Ohio put its total contracted data center load at 17,861 MW, scheduled to come online progressively through 2035.
In northern Illinois, Exelon's third-quarter 2026 filing puts about 14 GW of ComEd load in or awaiting cluster studies. ComEd's own January 2026 release announced the first eight transmission security agreements, covering a forecasted new load greater than 6.5 GW, structured as revenue commitments. Exelon separately counts about 9 GW at ComEd as high-probability load, in an official phase of engineering with deposits paid.
Georgia, counted by the state
Georgia's Public Service Commission publishes the state version of the same funnel. Georgia Power's 2023 integrated resource plan update estimated 6,600 MW of load growth, an estimate the commission approved in April 2024. The 2025 plan raised the projection to approximately 8,500 MW of load growth over six years. In December 2025 the commission certified 9,985 MW of new generation, and the commission's September 2026 fact sheet records that Georgia Power had secured customers for all 9,985 MW by August 2026, four months ahead of schedule.
Above the state level, a Charles River Associates review prepared for PJM in November 2026 puts data center demand in the PJM footprint at 30 GW by 2030 and 82 GW by 2047, concentrated in the Dominion and AEP territories. That is a forecast about forecasts, and it is labeled as one here: a review of utility projections, not a measurement.
The proceedings that turn requests into terms
Requests become obligations in regulatory proceedings, and the record tracks 191 of them, every one flagged as applying to large loads. Seventy-five are decided and 33 are in effect, 108 decided or in effect in total; 80 remain pending. Where terms have been decided, they run 70 to 90 percent minimum billing demand, 10 to 20 year minimum terms, collateral, and exit terms. AEP Ohio's tariff, approved by the Ohio commission in July 2025, sits inside that range: an 85 percent minimum demand charge and terms up to 12 years. Those terms are the benefit side of this record for other customers, stated in the documents themselves: a signed data center pays for most of its contracted capacity whether it uses it or not, and posts collateral against walking away. The cost side is in the same record: certified generation and transmission get built ahead of the load, as in Georgia, and households in these territories have seen a decade of rising prices whose causes this record cannot separate, which is the subject of this site's electric rates page and its data-center-vs-my-utility calculator.
The proceedings record
191
Large-load proceedings tracked
Every one flagged as applying to large loads
75
Proceedings decided
Decided by the regulator
33
Proceedings in effect
Decided and now in force
What the record does not show
A forecast is not an outcome, and this record does not total one. Each publisher defines its pipeline stages differently, so adding the request figures across territories would double count projects that ask more than one utility for the same campus, a practice the Dominion testimony describes indirectly by noting requests at more than twice the system's peak. The record also cannot say how much of any territory's household price change a data center caused; the 11 tracked residential price series all rose from 2016 to 2025, and fuel, storm recovery, and general grid investment sit in the same rates. The full counts behind this article are on the numbers page.
The chart data
- Dominion Energy Virginia, requested: 40,000 (2024)
- Dominion Energy Virginia, signed or contracted: 9,000 (2024)
- PPL Electric, Pennsylvania, requested: 31,800 (2026)
- PPL Electric, Pennsylvania, signed or contracted: 11,000 (2026)
- AEP Ohio, requested: 30,000 (2025)
- AEP Ohio, signed or contracted: 17,861 (2026)
- ComEd, northern Illinois, requested: 14,000 (2026)
- ComEd, northern Illinois, signed or contracted: 6,500 (2026)
- Georgia (statewide), requested: 8,500 (2025)
- Georgia (statewide), signed or contracted: 9,985 (2026)
Source: this site's record (load_forecasts), from the utilities' own testimony, filings, and releases, 2024 to 2026.
Data table
| Territory | Requested | Signed or contracted |
|---|---|---|
| Dominion Energy Virginia | 40000 | 9000 |
| PPL Electric, Pennsylvania | 31800 | 11000 |
| AEP Ohio | 30000 | 17861 |
| ComEd, northern Illinois | 14000 | 6500 |
| Georgia (statewide) | 8500 | 9985 |
| Territory | Asked | Signed or contracted | Also stated | Publisher and date |
|---|---|---|---|---|
| Dominion Energy Virginia | 40,000 MW requested | 9,000 MW under executed agreements | 3,600 MW metered; 5,000 MW under construction letters | SCC testimony, as of Dec 2024 |
| Dominion Energy Virginia | 45,000 MW without connection dates | 25,000 MW with energization dates to 2031 | Dominion GS-5 report, May 2026 | |
| PPL Electric, Pennsylvania | 31,800 MW pipeline | 11,000 MW under signed agreements | 6,500 MW under construction | PPL Q2 2026 earnings release, Aug 2026 |
| AEP Ohio | 30,000 MW expressed interest | 17,861 MW total contracted | 13,022.7 MW paid for studies; 5,642 MW signed under the tariff | AEP Ohio update to PUCO, Feb 2026 |
| ComEd, northern Illinois | 14,000 MW in cluster studies | 6,500 MW under the first eight agreements | 9,000 MW high-probability load | Exelon Q3 2026 filing; ComEd release, Jan 2026 |
| Georgia (statewide) | 8,500 MW projected load growth | 9,985 MW of certified generation fully contracted | Earlier estimate: 6,600 MW | Georgia Power 2025 IRP; Georgia PSC fact sheet, Sep 2026 |
Sources
- Staged record: load_forecasts.csv (110 rows) and utility_proceedings.csv (191 rows) · Data Center Fact Check · Checked November 22, 2026 · All counts and forecast rows in this article
- Direct testimony of Stan Blackwell, Dominion Energy Virginia, SCC Case No. PUR-2025-00058 · Virginia State Corporation Commission · September 3, 2025 · Case No. PUR-2025-00058; testimony figures as of December 2024
- GS-5 Large-Load Rate Class Report · Dominion Energy Virginia · May 2026
- PPL Corporation Delivers Solid Second-Quarter 2026 Earnings; Reaffirms Guidance and Long-Term Growth Outlook · PPL Corporation (via PR Newswire) · August 7, 2026
- AEP Ohio Updates PUCO on Data Center Load: Figures Show Tariff is Working · AEP Ohio · February 2026
- Exelon Reports Third Quarter 2026 Results (Form 8-K, Exhibits 99.1 and 99.2) · Exelon Corporation (SEC filing) · October 30, 2026 · Form 8-K, Exhibit 99.1
- ComEd Announces New Agreements Signed to Ensure Large Load Customers Pay their Fair Share to Connect with and Use the Grid · ComEd (Business Wire) · January 6, 2026
- Data Center Fact Sheet (September 2026) · Georgia Public Service Commission · September 2026
- Charles River Associates Review of Data Center Forecast (PJM Load Analysis Subcommittee, November 2, 2026) · PJM Interconnection · November 2, 2026