Data centers in Elk Grove Village, Illinois
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 13 data center projects in Elk Grove Village, Illinois as of November 2026: 7 operating, 3 under construction and 1 announced, totaling about 312 MW announced where a figure is published.
Elk Grove Village has 13 tracked data centers. Their announced capacity totals about 312 MW where a figure is published. Of those, 7 operating, 3 under construction and 1 announced. Every figure comes from the public record linked on this page.
Prime ORD Chicago Campus video · 2 min 26 sec
Data center projects in Elk Grove Village
- Aligned Elk Grove Village Campus (ORD-03)
ProposedElk Grove Village96 MW announced
- Centersquare ORD2 (Elk Grove Village)
OperatingElk Grove Village
- Digital Realty Elk Grove Village Campus (CH1/CH2/CH3)
OperatingElk Grove Village
- EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)
OperatingElk Grove Village
- Equinix Elk Grove Village Campus (CH3, CH5)
ExpandingElk Grove Village
- Microsoft Elk Grove Village Campus
Under constructionElk Grove Village
- Prime ORD Chicago Campus
Under constructionElk Grove Village180 MW announced
- STACK CHI01 (Elk Grove Village)
OperatingElk Grove Village
- STACK CHI02
AnnouncedElk Grove Village36 MW announced
- Stream Chicago I (Elk Grove Village)
OperatingElk Grove Village
- Stream Chicago II (Elk Grove Village)
OperatingElk Grove Village
- Stream ORDC Campus
Under constructionElk Grove Village
- T5@Chicago (Chicago I and II)
OperatingElk Grove Village
Who serves this place
- Not collected yet.
More places in Cook County
Elk Grove Village is part of Cook County.
Nearby places
- Chicago13 data center projects tracked
- Northlake4 data center projects tracked
- Hoffman Estates3 data center projects tracked
- Des Plaines1 data center project tracked
- Franklin Park1 data center project tracked
- Mount Prospect1 data center project tracked
Tax breaks and payments
2020 · STACK CHI01 (Elk Grove Village)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for STACK CHI01 (Elk Grove Village)2020 · T5@Chicago (Chicago I and II)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for T5@Chicago (Chicago I and II)2021 · Digital Realty Elk Grove Village Campus (CH1/CH2/CH3)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Digital Realty Elk Grove Village Campus (CH1/CH2/CH3)2020 · Microsoft Elk Grove Village Campus
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Microsoft Elk Grove Village Campus2022
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
2023 · EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)2021
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
2023 · Prime ORD Chicago Campus
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Prime ORD Chicago Campus2023 · Aligned Elk Grove Village Campus (ORD-03)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Aligned Elk Grove Village Campus (ORD-03)2024 · Equinix Elk Grove Village Campus (CH3, CH5)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Equinix Elk Grove Village Campus (CH3, CH5)2025 · Centersquare ORD2 (Elk Grove Village)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for Centersquare ORD2 (Elk Grove Village)2025 · EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
All tax records for EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)2025
Sales and use tax exemptions and credits (20 ILCS 605/605-1025)
State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).
Court cases and commission dockets in Illinois (3)
Bills and laws in Illinois
- HB 5826 · Filed · Oct 19, 2026Requires hourly energy accounting and clean certificates for covered data centers
- SB 4004 · In committee · May 22, 2026Would create the Data Center Water Transparency and Aquifer Protection Act
- SB 3120 · In committee · May 22, 2026Would tie the state data center incentive to a water stewardship strategy
- SB 3030 · In committee · May 22, 2026Would require cryptocurrency mining facilities to use noise-reduction techniques
- SB 2181 · In committee · May 22, 2026Would require annual energy and water reporting by Illinois data centers
- SB 4016 · In committee · May 22, 2026Would set environmental, water and energy rules for hyperscale data centers
- SB 3761 · In committee · May 22, 2026Requires data center disclosures and creates a clean energy self-direct program
- SB 3830 · In committee · May 22, 2026Would establish the data center self-direct program and related data center provisions
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Elk Grove Village?
- Data Center Fact Check tracks 13 data center projects in Elk Grove Village as of November 2026. Of those, 7 operating, 3 under construction and 1 announced.
- What is the biggest data center in Elk Grove Village?
- By announced capacity, the biggest data center in Elk Grove Village is Prime ORD Chicago Campus, announced at 180 MW. It is under construction.
- How much power do data centers in Elk Grove Village use?
- The 13 projects tracked in Elk Grove Village have announced about 312 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Data Center Investment Program 2025 Annual Report
Illinois Department of Commerce and Economic OpportunityTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Elk Grove Village." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-il-elk-grove-village