Skip to content

village Card

Data centers in Elk Grove Village, Illinois

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 13 data center projects in Elk Grove Village, Illinois as of November 2026: 7 operating, 3 under construction and 1 announced, totaling about 312 MW announced where a figure is published.

Elk Grove Village has 13 tracked data centers. Their announced capacity totals about 312 MW where a figure is published. Of those, 7 operating, 3 under construction and 1 announced. Every figure comes from the public record linked on this page.

Prime ORD Chicago Campus video · 2 min 26 sec

Full project file: Prime ORD Chicago Campus

13Data center projects we track

Data center projects in Elk Grove Village

Who serves this place

  • Not collected yet.

More places in Cook County

Elk Grove Village is part of Cook County.

Nearby places

Tax breaks and payments

  • 2020 · STACK CHI01 (Elk Grove Village)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for STACK CHI01 (Elk Grove Village)
  • 2020 · T5@Chicago (Chicago I and II)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for T5@Chicago (Chicago I and II)
  • 2021 · Digital Realty Elk Grove Village Campus (CH1/CH2/CH3)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Digital Realty Elk Grove Village Campus (CH1/CH2/CH3)
  • 2020 · Microsoft Elk Grove Village Campus

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Microsoft Elk Grove Village Campus
  • 2022

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

  • 2023 · EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)
  • 2021

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

  • 2023 · Prime ORD Chicago Campus

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Prime ORD Chicago Campus
  • 2023 · Aligned Elk Grove Village Campus (ORD-03)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Aligned Elk Grove Village Campus (ORD-03)
  • 2024 · Equinix Elk Grove Village Campus (CH3, CH5)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Equinix Elk Grove Village Campus (CH3, CH5)
  • 2025 · Centersquare ORD2 (Elk Grove Village)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Centersquare ORD2 (Elk Grove Village)
  • 2025 · EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for EdgeConneX Chicago Campus (CHI01/CHI02/CHI03)
  • 2025

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

Court cases and commission dockets in Illinois (3)

Bills and laws in Illinois

All 28 in Bill Watch

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Questions people ask

How many data centers are in Elk Grove Village?
Data Center Fact Check tracks 13 data center projects in Elk Grove Village as of November 2026. Of those, 7 operating, 3 under construction and 1 announced.
What is the biggest data center in Elk Grove Village?
By announced capacity, the biggest data center in Elk Grove Village is Prime ORD Chicago Campus, announced at 180 MW. It is under construction.
How much power do data centers in Elk Grove Village use?
The 13 projects tracked in Elk Grove Village have announced about 312 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.

Sources

  1. 1
    Data Center Investment Program 2025 Annual Report
    Illinois Department of Commerce and Economic Opportunity
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Elk Grove Village." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-il-elk-grove-village

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page