Data center court cases and dockets in Illinois
A docket is a case's public file. These are the lawsuits and the utility commission proceedings (rate cases, large-load rules, agreements) that touch data centers, newest activity first. Each links to its source.
3 dockets
Cases and proceedings
Court caseDismissed
Caruthers et al. v. County of Sangamon, Sangamon County Board, and C1 Sangamon I LLC (CyrusOne conditional use permit)
Circuit Court of Sangamon County, Illinois (Seventh Judicial Circuit) · Docket Case No. 2026MR236 · Sangamon County · Illinois
About: CyrusOne Sangamon County Campus
Utility commissionDecidedLarge loads
Commonwealth Edison Company, changes to new service requests for large demand project applicants or customers and revisions to Rider DE
Illinois Commerce Commission · Docket 25-0677 / 25-0679 (consolidated) · ComEd · Illinois
Utility commissionPending before the commissionLarge loads
Investigation of possible ratepayer protections and cost recovery mechanisms for servicing large demand project applicants or customers of Commonwealth Edison Company
Illinois Commerce Commission · Docket 26-0364 · ComEd · Illinois
Sources on this page
- 1Judge dismisses county's first data center lawsuit
Illinois TimesTier 3 · Draft research, not yet verified · Open the source - 2Judge Dismisses Lawsuit Challenging CyrusOne Data Center Approval
Sangamon ReporterTier 3 · Draft research, not yet verified · Open the source - 3ICC looks to develop consumer protection framework amid increase in large energy demand (press release)
Illinois Commerce CommissionTier 1 · Draft research, not yet verified · Open the source - 4Regulators OK ComEd's plan to increase deposit costs for large-load projects like data centers
Capitol News IllinoisTier 3 · Draft research, not yet verified · Open the source - 5Verified Petition to Intervene of the Citizens Utility Board, ICC Docket No. 26-0364
Illinois Commerce Commission (docket document)Tier 1 · Draft research, not yet verified · Open the source - 6ComEd customers could be on hook for billions in data center-related costs, according to consumer advocates' review of utility's records
Citizens Utility BoardTier 4 · Draft research, not yet verified · Open the source