Data centers in Chicago, Illinois

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 13 data center projects in Chicago, Illinois as of November 2026: 11 operating, 1 approved and 1 under construction, totaling about 180 MW announced where a figure is published.

Chicago has 13 tracked data centers. Their announced capacity totals about 180 MW where a figure is published. Of those, 11 operating, 1 approved and 1 under construction. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.

HydraVault Chicago video · 2 min 13 sec

Full project file: HydraVault Chicago

13Data center projects we track

Data center projects in Chicago

Who serves this place

  • Not collected yet.

More places in Cook County

Chicago is part of Cook County.

Nearby places

Tax breaks and payments

  • 2021 · QTS Chicago Mega Data Center

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for QTS Chicago Mega Data Center
  • 2020 · CoreSite Chicago Campus (CH1, CH2)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for CoreSite Chicago Campus (CH1, CH2)
  • 2023 · Serverfarm CH1 (840 South Canal)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Serverfarm CH1 (840 South Canal)
  • 2023 · Metro Edge IMD1 (Illinois Medical District)

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for Metro Edge IMD1 (Illinois Medical District)
  • 2025 · HydraVault Chicago

    Sales and use tax exemptions and credits (20 ILCS 605/605-1025)

    State sales and use tax exemptions on qualifying data center equipment under the Data Center Investment Program (20 ILCS 605/605-1025); exemption certificates run in five-year renewable increments up to 20 years. DCEO estimates the benefit at 6.25 percent of the investment commitment (report footnote, MOU table).

    All tax records for HydraVault Chicago

Court cases and commission dockets in Illinois (3)

Bills and laws in Illinois

All 28 in Bill Watch

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Questions people ask

How many data centers are in Chicago?
Data Center Fact Check tracks 13 data center projects in Chicago as of November 2026. Of those, 11 operating, 1 approved and 1 under construction.
What is the biggest data center in Chicago?
By announced capacity, the biggest data center in Chicago is QTS Chicago Mega Data Center, announced at 125 MW. It is operating.
How much power do data centers in Chicago use?
The 13 projects tracked in Chicago have announced about 180 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.

Sources

  1. 1
    Data Center Investment Program 2025 Annual Report
    Illinois Department of Commerce and Economic Opportunity
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Chicago." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-il-chicago

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page