Data centers in Sangamon County, Illinois

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 2 data center projects in Sangamon County, Illinois as of November 2026: 1 proposed and 1 approved, totaling about 636 MW announced where a figure is published.

Sangamon County has 2 tracked data centers. Their announced capacity totals about 636 MW where a figure is published. Of those, 1 proposed and 1 approved. The projects here are CyrusOne Sangamon County and CyrusOne Sangamon County Campus. Every figure comes from the public record linked on this page.

2Data center projects we track

Data center projects in Sangamon County

Who serves this place

  • Not collected yet.

A data center is proposed in Sangamon County

1 project here is at the announced or proposed stage. Before the hearing, the resident checklist walks through what to check: the proposal's documents, the local rules where you live, the tax agreement, and the recorded votes.

Open the resident checklist

Places in and around Sangamon County

Sangamon County is part of Illinois.

Nearby places

Court cases and commission dockets in Illinois (3)

Bills and laws in Illinois

All 28 in Bill Watch

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Questions people ask

How many data centers are in Sangamon County?
Data Center Fact Check tracks 2 data center projects in Sangamon County as of November 2026. Of those, 1 proposed and 1 approved.
What is the biggest data center in Sangamon County?
By announced capacity, the biggest data center in Sangamon County is CyrusOne Sangamon County Campus, announced at 636 MW. It is approved.
How much power do data centers in Sangamon County use?
The 2 projects tracked in Sangamon County have announced about 636 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.

Sources

    Cite this page

    Copy this citation when you reuse a figure or a finding from this page.

    Data Center Fact Check. "Sangamon County." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-il-sangamon

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page