What it means for locals
A data center is proposed near you: what happens next
A proposal passes through decisions by different bodies, on different documents, over months or years. This page lays out the path in the order it usually travels, names who decides each step, and links to the votes, permits, proceedings, and cases where each step appears in our record. It takes no side: the same steps serve a resident who supports a proposal and a resident who opposes one.
A data center proposal is not approved in one place. It becomes public, then passes through separate decisions: the county or city decides the land use, the state environmental agency issues the permits, the state utility commission sets the terms for power, and the local body votes on any tax agreement. This page walks through each step, names who decides it, and links to the part of our record where that step appears. We are tracking 179 projects at the announced or proposed stage today. Which body decides, and whether a public hearing is required, is set by state law and by the zoning already on the land, so the steps route you to your own state and county pages for the rules that apply where you live.
Find your place
Enter your ZIP code or your county or town name. Your place page lists the projects tracked there by stage, the local rules already adopted, and the officials we track.
The path a proposal travels
Step 1
It becomes public
Who decides: The developer announces the project, or a first filing names it: a land purchase, a permit application, or a request to the utility.
The document: The project enters this record with a first public date and a stage, announced or proposed. We set a project's stage only from a record that states it, never from a rumor or a rendering.
Where to watch it: Every tracked project has a page with its stage, its first public date, and the sources behind both. Your county page lists the projects there by stage, so a new proposal shows up next to what is already built.
Step 2
The land use decision
Who decides: The county board or the city council decides. A planning commission usually hears the case first and votes a recommendation.
The document: A rezoning case, or a special exception (special use) case where the zoning requires one, decided by a recorded vote. Our record holds 67 rezoning votes and 43 zoning amendment votes by named bodies, with each official's vote recorded.
Where to watch it: Whether this step happens at all depends on the zoning already on the land. In some districts in our record a data center is a by-right use and needs no rezoning vote; in others it needs a special exception permit, and counties in the record have moved data centers from by-right to special exception, which adds this vote. Your place page lists the local rules already adopted where you live, including setbacks and noise rules, and the officials we track there.
Step 3
The tax agreement
Who decides: The same county board or city council votes on it in a public session, often alongside or after the land use decision.
The document: A tax agreement: an abatement, a payment in lieu of taxes, or a development agreement, stating its term and its estimated value. We hold 218 agreements, each listed on its place page with its source. In Texas, local agreements are made under Chapters 380 and 312 of state law.
Where to watch it: The place pages list each agreement with its term and value. The tax break per job calculator divides the valued agreements by the jobs they promised, deal by deal.
Step 4
State environmental permits
Who decides: The state environmental agency decides. In Virginia that is the Department of Environmental Quality; each state names its own agency.
The document: Permits for the site's air emissions, stormwater, water use, and wetlands: 237 air permits and 40 for stormwater, water, and wetlands in our record. A project waiting on them carries the stage In permitting on its page: 42 projects carry that stage today.
Where to watch it: Each project's records page lists its permits with the deciding agency, the decision, and the date, each linked to its source.
Step 5
Power: the utility commission proceeding
Who decides: The state utility commission decides the terms on which the utility serves a very large new load.
The document: A docketed proceeding, opened by the utility's filing and decided by commission order. We track 191 proceedings; 108 have been decided or are in effect. The decided terms typically require the customer to pay for the lines and equipment built for it, post collateral, sign a contract of 10 to 20 years, and pay for at least 70 to 90 percent of its contracted demand every month whether it uses it or not.
Where to watch it: Courts and dockets lists each proceeding with its regulator, its docket number, and its status. The commission's own docket, under the number we list, is where its filings are posted.
Step 6
Construction and opening
Who decides: With the approvals in hand, the developer builds. The county issues the building permits and, at the end, a certificate of occupancy.
The document: The project's stage moves to Under construction, then Operating, when a record states it: 185 projects are under construction and 681 are operating in the record today.
Where to watch it: The project page carries the stage and the date it was last checked against a source. A stage never changes on this site until a record states the new one.
Step 7
If the decision is challenged
Who decides: A court. A land use decision can be appealed, and a project can be sued over, by residents, by the developer, or by the county itself.
The document: A case with a court, a docket number, and a status. Our record holds 20 cases, including a land use appeal residents brought against a township board of supervisors over its approvals (Gerber et al. v. Board of Supervisors of Middlesex Township).
Where to watch it: Courts and dockets lists each case with its court, its docket number, and where it stands.
Before the hearing: what to check
A working list, in the order most residents need it. Every item points at a page where this record holds the thing itself: the documents, the rules, the votes. One item cannot be checked here, and it says so. Tick items off as you go.
Search your county or your ZIP code. The project page states the project's stage, the date it first became public, who is building it, and the capacity it announced, each with the source behind it. We are tracking 179 projects at the announced or proposed stage today.
The project's records page lists the documents behind it: the application, the permits, and the filings, each with the body that issued it, the decision, and the date. Our record holds 624 project documents. Read the application first; it is the developer's own statement of what is proposed.
Whether a hearing and a vote happen at all depends on the zoning already on the land: a by-right use needs no rezoning vote, and a special exception adds both. Your place page lists the rules adopted where you live, including setbacks and noise rules. Our record holds 83 local rules for the places we track.
For the projects covered in depth, the record holds statements on the questions residents raise: water, power, jobs, property tax, tax breaks, the neighborhood, and how residents took part. The record holds 339 of these statements across 44 projects. They sit on the place page under If you live nearby, and on each project page, each with its source.
If the local body has voted a tax agreement, the place page lists it with its term, its stated value, and the commitments written into it, including the jobs promised. We hold 218 agreements. The calculator divides each valued agreement by the jobs it promised, deal by deal.
When a body in our record has voted on a tracked decision, the vote is recorded with each official's name and how they voted. Our record holds 738 recorded votes, 67 of them on rezonings and 43 on zoning amendments. The officials we track for your place are listed on your place page.
The utility commission proceeding sets the terms on which the utility serves the project, including who pays for the lines and equipment built for it. We track 191 proceedings. The dockets page names the regulator and the docket number for each one, so the commission's own filings are one search away.
A county, city, or town can pause new applications while it rewrites its rules, and a pause changes what a proposal filed today can do. Our record holds 20 moratoriums, 15 of them in effect today. The tracker lists each pause with its status and its dates.
We do not track hearing dates or comment deadlines; they are not fields in this record yet, so no date on this site can tell you when the hearing is. The date, the agenda, and the way to submit a comment are published by your county or town ahead of the hearing, and the utility commission's docket carries its own dates. Check them before you go, and check again on the day: dates move.
Where you can be heard
Speak at the hearing
Rezoning and special exception cases are heard before the vote: the planning commission hears the case and recommends, and the governing body hears it again before deciding. We do not track hearing dates or comment deadlines yet; the date appears in the county's published agenda. The vote itself, once it happens, is recorded on the place page with each official's name and how they voted.
Work on the rule itself
The zoning that decides whether a vote is needed can itself be changed by the same bodies, and a county or town can pause applications while it rewrites its rules. Our record holds 20 moratoriums, 15 of them in effect and 43 zoning amendment votes. The moratoriums tracker lists each pause with its status and dates.
Follow the power docket
The utility commission proceeding runs on filings at the commission under its docket number. The dockets page tracks each proceeding's status and names its regulator and docket number, so the commission's own docket is one search away.
What this page cannot tell you
- Whether a rumored project is real. We list a project when a public record names the site, the operator, or a filing. A place with no project listed is a place we have not found one in the record, not proof that none is planned.
- Hearing dates and comment deadlines. We do not track them yet. The county's published agenda and the commission's docket carry them.
- Legal advice. This page explains the process the record shows. It does not advise anyone on a case, a filing, or a deadline.
- What the decision will be. The record shows who decides, and what those bodies decided in the cases we hold. It does not predict a vote.
Questions people ask
- A data center is proposed in my town. What happens next?
- It passes through separate decisions, not one approval. The developer's announcement or first filing makes it public. The county board or city council then decides the land use, usually after a planning commission hearing. The state environmental agency issues the air, stormwater, water, and wetland permits. The state utility commission sets the terms for power in a docketed proceeding. The local body votes on any tax agreement. Which of these steps a given proposal needs, and in what order, is set by state law and the zoning already on the land.
- Who decides whether a data center gets built near me?
- No single body decides the whole project. The county board or city council decides the land use and any tax agreement. The state environmental agency decides the permits. The state utility commission decides the terms for serving the load. A court decides any appeal or lawsuit that follows. Your place page names the local officials we track where you live.
- Does every data center proposal get a public hearing and a vote?
- No. A hearing and a vote are required when the proposal needs a rezoning or a special exception. Where the zoning already allows a data center by right, no rezoning vote is needed. Our local rules show both: places where a data center is a by-right use, and places that have moved it to a special exception, which adds the hearing and the vote. Your place page lists the rules adopted where you live.
- What should I check before a hearing on a data center proposal?
- Work through the checklist on this page. Find the proposal in the record and read its documents. Check the zoning on the land, because it decides whether a hearing and a vote happen at all. Read what the record says about living nearby, the tax agreement if one has been voted, the recorded votes on the project so far, and the power proceeding's docket number. One thing is not in this record: the hearing date and the comment deadline. Your county's published agenda carries both.
- Can my county or town pause data center proposals?
- Yes. A county board, a city council, or a town board can adopt a moratorium that pauses new applications while it rewrites its rules, and can amend the zoning itself. Our record holds 20 moratoriums adopted by local bodies; 15 are in effect today. The moratoriums and bans tracker lists each one with its status and its dates.
- How do I find out what is proposed in my county?
- Enter your ZIP code in the search and the site takes you to your county page, which lists the tracked projects there by stage, including the ones at the announced and proposed stages. Each project page states its stage and the date it first became public, with the source for both. A county with nothing listed is a county where we have not found a project in the public record.
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "A data center is proposed near you: what happens next." Checked 2026-11-24. Accessed 2026-11-29. https://datacenterfactcheck.org/benefits/proposed-near-me