Data center moratoriums and bans

Cities and counties that have paused or barred new data centers, from their own ordinances, resolutions, and meeting records. 20 tracked. This page is updated as the record changes.

Right now, 15 data center moratoriums are in effect across 15 places, per the local records we track. We track 20 moratoriums in total, including 5 that have ended. Each entry below states what the pause covers, when it was adopted, and the record it comes from. A place with no entry is a place where we have not found a moratorium in the record, not proof that none exists.

In effect now (15)

  • Wells, Maine · In effect · Adopted Nov 3, 2026

    Ordinance to Establish a Retroactive Moratorium on Data Centers

    Special Town Meeting Article 5 (2026-11-03)

    Wells declared a moratorium on the siting construction establishment or operation of any data center and on accepting processing or acting on applications for new or expanded data centers while the town studies permanent rules. The moratorium is retroactive to applications pending on or after June 16 2026.

    Data Center = a facility with an aggregate Data Center Area of 100000 sq ft or more; moratorium runs 180 days from the 2026-06-16 date of applicability (to 2026-12-13) unless extended repealed or modified; final permits issued within 45 days of the effective date may be nullified

  • Memphis, Tennessee · In effect · Adopted Oct 20, 2026

    135-day pause on new data center development with directions for permanent rules

    Ordinance No. 5986 (substitute adopted 2026-10-20)

    Memphis paused new data center development for 135 days and directed its planning division to draft permanent Unified Development Code amendments for data centers within 90 days with council guidelines for the permanent rules; existing facilities are not stopped. The separate 18-month moratorium (Ordinance No. 5982) failed on a 6-6 tie the same night.

    135-day pause running to about 2027-03-04; permanent code amendments due within 90 days; the ordinance text posted before the meeting defined a large data center at 20 MW or more of demand

  • Newton County, Georgia · In effect · Adopted Oct 6, 2026

    Extension of the data center application moratorium to December 16 2026

    Resolution R-100626A

    Newton County extended its moratorium on accepting any application request or submission that proposes developing a data center in the county including rezoning special use and conditional use permits development and building permits and site plans while the county finishes studying a data center ordinance.

    Moratorium bars acceptance of data center applications until 2026-12-16; it ends on the earliest of 2026-12-16 approval of an additional moratorium after a public hearing or Board action terminating it

  • Palm Beach County, Florida · In effect · Adopted Sep 24, 2026

    One-year moratorium on large-scale data center applications in unincorporated Palm Beach County

    Ordinance revising the ULDC (Large-Scale Data Center Moratorium) adopted 2026-09-24

    Palm Beach County adopted an ordinance revising its Unified Land Development Code to add the Large-Scale Data Center use and establish a one-year moratorium: the county will not accept process or approve zoning requests or related comprehensive plan amendments for large-scale data centers in unincorporated areas while permanent rules are drafted.

    Large-Scale Data Center = anticipated peak load of 50 MW or more evaluated across the entire site; moratorium ends 2027-09-24 or earlier if permanent rules are adopted; applications deemed sufficient before the moratorium may continue; facilities under 50 MW may apply with a Florida-licensed engineer certifying the load

  • Spokane County, Washington · In effect · Adopted Aug 18, 2026

    Pause on land use and permit applications for large-load data centers in unincorporated Spokane County

    BoCC resolution (2026) adopting a pause on data center applications

    Spokane County paused the acceptance and processing of land use and permit applications for large-load data centers in the unincorporated county as an interim official control while staff draft a zoning text amendment (ZTA 8-14) defining and regulating the use.

    Large-Load Data Center = a data center with a connected or contracted electrical load of 20 MW or more; pause as adopted ran through 2026-12-15; on 2026-10-20 the Board adopted the pause through 2027-06-01 or until the zoning text amendments are complete whichever comes first

  • Cass County, Nebraska · In effect · Adopted Aug 11, 2026

    Land Use Moratorium / Data Centers (12-month moratorium)

    Resolution 2026-12

    Cass County adopted a 12-month moratorium on data centers. The Board of Commissioners held the public hearing on Resolution 2026-12 (Land Use Moratorium/Data Centers) on August 11, 2026 and then adopted it; the zoning administrator had no recommendation and the Planning Commission had recommended the Board consider a moratorium.

    12-month moratorium adopted 2026-08-11; motion carried 5-0

  • Jeffersonville, Indiana · In effect · Adopted Aug 3, 2026

    One year moratorium on new data center development

    Ordinance Establishing a Temporary Moratorium on New Data Centers (ordinance number not published in the sources read)

    The moratorium halts new data center development in the city for one year while the Plan Commission drafts permanent zoning rules for the Unified Development Ordinance. The administration proposed six months and the council extended it to a full year. It does not affect the Meta data center under construction at the River Ridge Commerce Center, because the River Ridge Development Authority holds zoning authority over that land under a long standing interlocal agreement, and the city's own 2026 zoning update handout confirms data center zoning is being handled in a separate later ordinance because of the moratorium.

    Duration 1 year (2026-08-03 to 2027-08-03); council vote 8-0; administration proposal was 6 months

  • Lakeland, Florida · In effect · Adopted Aug 3, 2026

    Temporary moratorium on data centers and large load customers

    Ordinance No. 6148 (proposed ordinance 26-018)

    Lakeland imposed a 12-month moratorium on accepting processing reviewing or approving applications for development permits development orders comprehensive plan amendments or other approvals related to a data center or a large load customer while staff drafts comprehensive plan and land development code amendments and a large-load policy.

    Moratorium runs 12 months from the effective date (immediate on passage 2026-08-03) unless terminated earlier by ordinance; Large Load Customer = anticipated peak demand of 50 MW or more at a single location; reaches unincorporated areas served by Lakeland electric water or wastewater utilities; exceptions include businesses storing their own data

  • DeSoto County, Florida · In effect · Adopted Jul 28, 2026

    Temporary one-year moratorium on data center facility approvals in unincorporated DeSoto County

    Ordinance 2026 (number blank in the county packet copy)

    DeSoto County established a one-year moratorium under which the county will not accept process review approve issue or grant any development approval for the construction expansion or operation of a data center facility in the unincorporated county. Development under the March 2026 DCIP rezoning (Ordinance 2026-004 application RZNE-0077-2025) and the pending DCIP rezoning applications are exempt.

    Moratorium runs one (1) year from the effective date; no MW or size threshold in the ordinance's Data Center Facility definition; exemptions: RZNE-0077-2025 development and pending applications RZNE-0086-2026 and RZNE-0087-2026

  • Hillsboro, Oregon · In effect · Adopted Jul 27, 2026

    120-day moratorium on new or expanded data center and battery storage applications as a primary use

    Resolution No. 2932

    Hillsboro adopted a temporary moratorium under ORS 197.505 to 197.540: no person may submit, and the city may not accept, process, or approve, a new land use application for a new data center or battery energy storage system as a primary use, or an expansion of an existing one as a primary use, while the city studies the uses and writes Community Development Code amendments. The resolution defines a data center as a facility for the storage, management, processing, and/or transmission of digital data housing computer and network equipment, with no megawatt or square-foot threshold.

    Effective immediately on adoption 2026-07-27 for 120 calendar days (to 2026-11-24), unless earlier extended or repealed; Council must review the need to extend or repeal not more than 120 days after the effective date (Resolution Sections 3 and 5)

  • York County, South Carolina · In effect · Adopted Jul 13, 2026

    Nine-month moratorium on data center approvals in unincorporated York County

    Ordinance establishing a temporary moratorium on data centers (2026; number not printed on the county page)

    York County Council passed a nine-month moratorium on new data centers in the unincorporated county: the county will not consider accept or approve special exceptions or conditional use approvals site plans or other land use or development approvals for data centers while it studies their impact on critical resources nearby properties and infrastructure. Projects with vested rights are exempt.

    Nine (9) months from adoption (to about 2027-04-13); extension possible by further resolution of County Council; QTS's nine buildings under development hold vested rights and are exempt

  • Spokane, Washington · In effect · Adopted Jun 22, 2026

    One-year citywide moratorium on new computer data centers

    Ordinance C36887

    Spokane imposed an immediate one-year citywide moratorium on the acceptance processing review and approval of building permit applications for new computer data centers while the city develops a regulatory framework. An adopted amendment clarifies how the moratorium applies to facilities that combine a data center with other business activities such as manufacturing.

    One-year moratorium effective immediately on passage; applies citywide to building permit applications for new computer data centers; public hearing held 2026-07-22

  • Seattle, Washington · In effect · Adopted Jun 9, 2026

    Data center moratorium and definition (Seattle Municipal Code Sec. 23.84A.008)

    Ordinance 127447 (Council Bill 121214)

    One-year moratorium on filing accepting processing or approving applications to establish or expand a data center or change a use to a data center anywhere in Seattle. The ordinance also adds a data center definition to the municipal code and approves a work plan for permanent regulations.

    Data center defined as a facility with capacity in excess of 20 MVA; moratorium runs 365 days from the effective date; expansion of a facility operating on the effective date by no more than an additional 20 MVA is exempt

  • Nassau County, Florida · In effect · Adopted Jun 8, 2026

    Temporary moratorium on data center facility applications in unincorporated Nassau County

    Ordinance No. 2026-044

    Nassau County imposed a temporary moratorium on the acceptance review processing or approval of applications for data center facilities in the unincorporated county while it studies amendments to its comprehensive plan land development code and code of ordinances. A Fact-Finding Committee on Data Center Development was created the same season under Resolution No. 2026-102.

    Moratorium runs twelve (12) months from the effective date (filing with the Florida Secretary of State) or until an ordinance amending the regulations takes effect; covers rezoning applications conditional use permits development permits site plan approvals and building permits for data centers data processing facilities data mining and cryptocurrency mining operations

  • Reno, Nevada · In effect · Adopted Jun 1, 2026

    Moratorium on data center conditional use permit applications through August 31 2027

    Final moratorium resolution on data center development (resolution number not stated on the city page read)

    The Reno City Council approved a final moratorium resolution on data center development on June 1, 2026. While it runs, the city will not accept applications for conditional use permits for data centers; all new data centers in Reno require a conditional use permit. The moratorium supports a Title 18 text amendment process on data center regulations initiated April 22, 2026, with the Truckee Meadows Regional Planning Agency leading public engagement.

    Moratorium in effect through 2027-08-31, or until adequate regulations are adopted, whichever comes first (city page)

Ended (5)

These pauses ran their stated course. They stay listed so the full record is visible.

  • Charlotte, North Carolina · Expired · Adopted Jun 8, 2026

    150-day moratorium on new data center applications

    Data Centers Moratorium (adopted 2026-06-08)

    Charlotte adopted a 150-day moratorium on new data center development applications while it studied infrastructure capacity noise and environmental impacts and drafted development rules; the city UDO covers the use as a telecommunications and data storage facility. Staff later proposed extending the pause.

    150 days from 2026-06-08 through 2026-11-05; an extension to 2027-10-18 was proposed in October 2026 with a public hearing set on 2026-09-28

  • Newton County, Georgia · Expired · Adopted Apr 7, 2026

    Limited moratorium on acceptance of data center applications

    Resolution R-040726b

    The resolution continues the county's moratorium chain (the February 17, 2026 emergency moratorium ran to March 18, and a March 3 revision extended it to April 8) by barring acceptance of data center applications until October 7, 2026, while the county drafts data center standards. Resolution R-100626A later extended the moratorium to December 16, 2026.

    Moratorium ran to 2026-10-07 under this resolution

  • Newton County, Georgia · Expired · Adopted Feb 17, 2026

    Emergency moratorium on acceptance of data center applications

    Resolution #R021726

    The resolution bars the county, until March 18, 2026, from accepting applications, requests, or submissions that propose data center development in whole or in part, including rezoning, special use and conditional use permits, development permits, site plans, and building permits. Its stated purpose is to give the county time to study and draft an ordinance on data center development. By its own terms it ended on the earliest of March 18, 2026, Board approval of an additional moratorium after a public hearing, or Board action ending it; no extension was found in the sources read.

    Moratorium ran from 2026-02-17 to 2026-03-18 (about 30 days)

  • Social Circle, Georgia · Expired · Adopted Sep 16, 2025

    90 day moratorium on submission of new data center projects

    City of Social Circle data center moratorium (ordinance or resolution number not stated in the sources read)

    The city paused submissions of new data center projects for 90 days so officials could consider the proposals in front of them and study the issue. The pause ran out in mid December 2025, and the city adopted detailed data center criteria the following month (Ordinance No. 2026-2).

    Duration 90 days

  • Douglas County, Georgia · Expired · Adopted Mar 20, 2025

    Moratorium on data center applications over 50000 square feet

    Board of Commissioners moratorium resolution (2025)

    Douglas County paused land use map amendments rezonings special use permits variances and public hearings for data center campuses over 50000 square feet while it studied the use; the Board extended the pause once and then replaced it with adopted zoning text amendments in September 2025.

    Facilities or campuses over 50000 square feet including accessory structures; initial term 90 days; extended 90 days on 2025-06-17 by a 5-0 vote

Moratoriums are local rules. State and federal bills about data centers are tracked separately on Bill Watch, and each place page lists the local rules that apply there. Our articles explain what a pause means for the people who live under one.

  1. What the record shows · November 22, 2026

    31 data center projects cancelled, 9 paused: the stopped projects in the public record, one by one

    Of 1,320 tracked data center projects, 31 are listed as cancelled and 9 as paused, 40 projects across 24 states.

Questions people ask

Which places have banned or paused data centers?
Per the local records we track, these places have a data center moratorium or pause in effect now: Cass County, Nebraska, DeSoto County, Florida, Hillsboro, Oregon, Jeffersonville, Indiana, Lakeland, Florida, Memphis, Tennessee, Nassau County, Florida, Newton County, Georgia, Palm Beach County, Florida, Reno, Nevada, Seattle, Washington, Spokane County, Washington, Spokane, Washington, Wells, Maine, and York County, South Carolina. Each one is a temporary pause on new applications or approvals, adopted by the city or county named. The list counts only moratoriums we have found in the public record, so it is a lower bound.
How many data center moratoriums are in effect right now?
We track 15 data center moratoriums in effect now, across 15 places, out of 20 moratoriums tracked in total. The count comes from the local ordinances, resolutions, and meeting records listed on this page, each with its source. It is a lower bound: it covers the moratoriums we have found, not every one that exists.
How long do data center moratoriums last?
The lengths vary by place, and each ordinance states its own. In effect now, the record includes Jeffersonville (one year), Memphis (135-day), Spokane (one-year), and Palm Beach County (one-year). Some run a set number of days or months from adoption; others run until the place adopts permanent rules. Each entry on this page states the length its own record gives.
What does a data center moratorium do?
It pauses new data center development in the place that adopted it, for the period the ordinance states. In the records we track, the pause usually bars the city or county from accepting new applications or granting new approvals while it writes or updates its permanent rules. It does not close data centers that are already operating. What exactly is paused, and what is exempt, is stated in each entry below from its own record.
Have any data center moratoriums ended?
Yes. 5 of the moratoriums we track have ended: Charlotte, North Carolina, Douglas County, Georgia, Newton County, Georgia, and Social Circle, Georgia. An ended moratorium stays on this page so the full record is visible, marked as expired. Several places adopted permanent zoning rules after a pause ended.

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Data center moratoriums and bans." Updated 2026-11-29. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/moratoriums