31 data center projects cancelled, 9 paused: the stopped projects in the public record, one by one
Of 1,320 tracked data center projects, 31 are listed as cancelled and 9 as paused, 40 projects across 24 states.
By Bear Harper · Published November 22, 2026
Of 1,320 tracked data center projects, 31 are listed as cancelled and 9 as paused, 40 projects across 24 states. Seven of the cancelled projects state a capacity, 4,740 MW in total; three of the paused projects state one, 1,620 MW. The other 30 stopped projects state no capacity in any document the record holds. The record states outcomes, not reasons.
Data Center Fact Check tracks 1,320 data center projects in the United States. Forty of them, 3 percent, carry a cancelled or paused stage in the record: 31 cancelled and 9 paused. This article lists what the record states about each one: the outcome, the place, the capacity where a document states one, and the last public record behind the stage. Where the record holds no reason for a stop, it says so below rather than guessing.
The count, and what sits beside it
The 40 stopped projects sit inside a record that is mostly building. The same staging holds 681 operating projects and 185 under construction, against 124 proposed, 71 approved, 55 announced, 53 expanding, and 42 in permitting. A cancelled announcement is a plan that ended before construction in nearly every case the documents describe, and a pause is not an ending: a paused project's stage moves again when a public record moves it.
The stopped count
31
Projects cancelled
Stage as the public record states it
9
Projects paused
Stage as the public record states it
Most of the stopped projects are recent announcements. Of the 31 cancelled projects, 11 first appear in the public record in 2025 and 7 in 2026. Four date to 2021, three to 2024, and three carry no first public date in the record. Maine holds the most stops of any state: four cancelled projects and one paused, five of the 40.
- Maine: 5
- Indiana: 3
- Wisconsin: 3
- Georgia: 2
- Maryland: 2
- Michigan: 2
- Minnesota: 2
- Montana: 2
- Nebraska: 2
- North Carolina: 2
- Ohio: 2
- Colorado: 1
- Delaware: 1
- Florida: 1
- Massachusetts: 1
- New York: 1
- Oregon: 1
- South Dakota: 1
- Tennessee: 1
- Texas: 1
- Utah: 1
- Virginia: 1
- Washington: 1
- Wyoming: 1
Source: this site's project record; stage and first public date as the public record states them.
Data table
| State | Projects |
|---|---|
| Maine | 5 |
| Indiana | 3 |
| Wisconsin | 3 |
| Georgia | 2 |
| Maryland | 2 |
| Michigan | 2 |
| Minnesota | 2 |
| Montana | 2 |
| Nebraska | 2 |
| North Carolina | 2 |
| Ohio | 2 |
| Colorado | 1 |
| Delaware | 1 |
| Florida | 1 |
| Massachusetts | 1 |
| New York | 1 |
| Oregon | 1 |
| South Dakota | 1 |
| Tennessee | 1 |
| Texas | 1 |
| Utah | 1 |
| Virginia | 1 |
| Washington | 1 |
| Wyoming | 1 |
- Cancelled: 7.00 (2026)
- Paused: 3.00 (2026)
Source: this site's project record; stage and first public date as the public record states them.
Data table
| Outcome | 2019 | 2020 | 2021 | 2023 | 2024 | 2025 | 2026 |
|---|---|---|---|---|---|---|---|
| Cancelled | 1.00 | 1.00 | 4.00 | 1.00 | 3.00 | 11.00 | 7.00 |
| Paused | Not filed | 1.00 | Not filed | Not filed | 3.00 | 1.00 | 3.00 |
The largest stopped projects the record can size
Seven cancelled projects state a capacity. The two largest are 1,250 MW each. Stillwater Technology Park in Lovejoy, Georgia, first public in July 2026 on its state development review filings, is listed as cancelled on those filings. Prometheus Falls Ranch near Casper, Wyoming, first public in June 2026, is listed as cancelled as of October 2026. Project Washington in Delaware City, Delaware, at 1,200 MW, carries the strongest paper trail in the set: its staged sources are a Delaware Coastal Zone Industrial Control Board decision and final order from 2026 and a withdrawn appeal of that decision.
Capacity the stopped projects state
4,740
MW of cancelled capacity stated
Across the cancelled projects that state a capacity; the rest state none
1,620
MW of paused capacity stated
Across the paused projects that state a capacity; the rest state none
The largest paused project that states a capacity is Brightseat Tech Park in Landover, Maryland, at 820 MW. Its record runs from a Prince George's County planning staff report in January 2024 to a paused stage as of July 2026. In Spokane County, Washington, an unnamed project under a 500 MW memorandum of understanding with Avista is listed as paused as of November 2026; the county record behind that row is the county's ZTA 8-14 packet, which proposed pausing acceptance of data center permit applications while the county rewrites its rules. Pauses like that one connect to the wider set of local pauses tracked on this site's moratorium tracker.

What the outcomes rest on
The paper behind a stopped stage varies, and the article names the kind of document for the projects it features. The Prince William Digital Gateway in Prince William County, Virginia, first public in July 2021, is listed as cancelled as of July 2026 on the county's own project page. Sabey's Butte campus in Montana, 250 MW, is listed as cancelled as of May 2026; its record holds the operator's project site, a NorthWestern Energy results release, and trade reporting of the withdrawal, labeled here as reporting. Microsoft published its own account of exploring the Perry Township site in Allen County, Ohio; the record lists that project as cancelled as of October 2024.
One town holds both outcomes. In Becker, Minnesota, Google's campus is listed as cancelled as of December 2022, and Amazon's campus, first public in November 2024, is listed as paused as of June 2025. Both Becker outcomes rest on local and trade reporting in the record, not on a county document, and the record labels them that way.
What the record does not show
The record holds no reason field. For most of the 40 projects, no document the record holds states why the project stopped, and this article does not supply a reason from coverage elsewhere. Thirty of the 40 state no capacity, so the 6,360 MW combined figure for the 10 that do is a floor, not a total. Twenty-five of the 40 have no coordinates in the record, so the map below plots the 15 that do and the table lists all 40. Stage dates in the table are the dates of the last public record behind each stage, which is what the record can prove; a project may have stopped earlier than the document that shows it stopped.
- Paused: 9
- Cancelled: 31
- Amazon Data Services Becker data center campus · Sherburne County, Minnesota (county center, not a site address)
- Amazon Sunbury Campus · Delaware County, Ohio (county center, not a site address)
- Androscoggin Mill Data Center (Sentinel / JGT2) · Franklin County, Maine (county center, not a site address)
- Applied Digital Toronto (proposed) · Deuel County, South Dakota (county center, not a site address)
- ArchGreen Doniphan data center (permit denied) · Hall County, Nebraska (county center, not a site address)
- Balloonist LLC Menomonie data center · Dunn County, Wisconsin (county center, not a site address)
- Big Horn Data Hub (MARA Hardin) · Big Horn County, Montana (county center, not a site address)
- Brightseat Tech Park · Prince George's County, Maryland
- Calvert Technology Center · Calvert County, Maryland
- CleanSpark Limestone (GRIID) · Washington County, Tennessee (county center, not a site address)
- CoreWeave Digital Crossroads Expansion · Lake County, Indiana (county center, not a site address)
- Energy Storage Solutions Kingsboro Megasite Data Center · Edgecombe County, North Carolina (county center, not a site address)
- Energy Storage Solutions Tarboro Data Center · Edgecombe County, North Carolina (county center, not a site address)
- Google Becker data center · Sherburne County, Minnesota (county center, not a site address)
- Howell Township data center proposal (Randee LLC) · Livingston County, Michigan (county center, not a site address)
- Microsoft Caledonia data center · Racine County, Wisconsin (county center, not a site address)
- Microsoft Perry Township data center site · Allen County, Ohio (county center, not a site address)
- MillCompute Bates Mill Data Center · Androscoggin County, Maine
- Nautilus Millinocket · Penobscot County, Maine (county center, not a site address)
- Northeast Brighton data center campus (withdrawn application) · Adams County, Colorado (county center, not a site address)
- Northern Data Stanton County cloud hub (not built) · Stanton County, Nebraska (county center, not a site address)
- Prince William Digital Gateway · Prince William County, Virginia (county center, not a site address)
- Project Bus · Carroll County, Georgia (county center, not a site address)
- Project Tango (Central Park Commerce Center) · Palm Beach County, Florida
- Project Washington · New Castle County, Delaware
- Prometheus Falls Ranch (Casper) · Natrona County, Wyoming (county center, not a site address)
- Proposed data center at the former Hynix plant (Eugene) · Lane County, Oregon
- QTS DeForest / Vienna data center campus · Dane County, Wisconsin (county center, not a site address)
- QTS Jeremiah A Data Center Campus · Porter County, Indiana (county center, not a site address)
- QTS Jeremiah B Data Center Campus · Porter County, Indiana (county center, not a site address)
- Red Butte Energy & Data Center Campus · Iron County, Utah (county center, not a site address)
- RELLIS Campus Data and Research Center · Brazos County, Texas (county center, not a site address)
- Riverview Innovation and Technology Campus Data Center · Erie County, New York
- Sabey Butte Data Center Campus · Silver Bow County, Montana (county center, not a site address)
- Sanford Woods Industrial and Technical Campus · York County, Maine (county center, not a site address)
- Stillwater Technology Park · Clayton County, Georgia
- Thor Equities Augusta Township data center campus · Washtenaw County, Michigan (county center, not a site address)
- Unnamed Data Center Project (Avista 500 MW MOU) · Spokane County, Washington (county center, not a site address)
- Westfield Servistar Data Center Campus · Hampden County, Massachusetts (county center, not a site address)
- Wiscasset Maine Yankee Site Data Center Proposal · Lincoln County, Maine (county center, not a site address)
The 15 stopped projects that carry coordinates in the record, plotted by stage. A point sits at the project's site position where the record holds one, and at its county's center point otherwise. The other 25 stopped projects appear in the table only.
The 40 projects

| Project | Place | Stage | Capacity stated | First public | Last record |
|---|---|---|---|---|---|
| Project Washington | Delaware City, Delaware | Cancelled | 1,200 MW | 2025 | Jul 2026 |
| Stillwater Technology Park | Lovejoy, Georgia | Cancelled | 1,250 MW | 2026 | Jul 2026 |
| Prometheus Falls Ranch | Casper, Wyoming | Cancelled | 1,250 MW | 2026 | Oct 2026 |
| Sabey Butte Data Center Campus | Butte-Silver Bow, Montana | Cancelled | 250 MW | 2024 | May 2026 |
| Energy Storage Solutions Tarboro | Tarboro, North Carolina | Cancelled | 300 MW | Not stated | Aug 2026 |
| Applied Digital Toronto | Toronto, South Dakota | Cancelled | 430 MW | Not stated | Oct 2026 |
| Nautilus Millinocket | Millinocket, Maine | Cancelled | 60 MW | 2021 | Apr 2025 |
| Northeast Brighton campus | Brighton, Colorado | Cancelled | Not stated | 2026 | Oct 2026 |
| Project Tango | Palm Beach County, Florida | Cancelled | Not stated | 2025 | Jul 2026 |
| Project Bus | Temple, Georgia | Cancelled | Not stated | 2026 | Jan 2026 |
| CoreWeave Digital Crossroads Expansion | Hammond, Indiana | Cancelled | Not stated | 2025 | Jun 2026 |
| QTS Jeremiah A | Porter County, Indiana | Cancelled | Not stated | 2025 | Sep 2025 |
| QTS Jeremiah B | Porter County, Indiana | Cancelled | Not stated | 2025 | Sep 2025 |
| Westfield Servistar Campus | Westfield, Massachusetts | Cancelled | Not stated | 2021 | Oct 2026 |
| Calvert Technology Center | Lusby, Maryland | Cancelled | Not stated | 2026 | Aug 2026 |
| MillCompute Bates Mill | Lewiston, Maine | Cancelled | Not stated | 2025 | Dec 2025 |
| Androscoggin Mill (Sentinel) | Jay, Maine | Cancelled | Not stated | 2026 | Jun 2026 |
| Wiscasset Maine Yankee Site | Wiscasset, Maine | Cancelled | Not stated | 2025 | Nov 2025 |
| Howell Township proposal | Livingston County, Michigan | Cancelled | Not stated | 2025 | Dec 2025 |
| Thor Equities Augusta Township | Washtenaw County, Michigan | Cancelled | Not stated | 2025 | Aug 2026 |
| Google Becker | Becker, Minnesota | Cancelled | Not stated | 2019 | Dec 2022 |
| Big Horn Data Hub (MARA) | Hardin, Montana | Cancelled | Not stated | 2020 | Apr 2022 |
| Energy Storage Solutions Kingsboro | Edgecombe County, North Carolina | Cancelled | Not stated | Not stated | Jul 2026 |
| ArchGreen Doniphan | Hall County, Nebraska | Cancelled | Not stated | 2023 | Oct 2023 |
| Northern Data Stanton County | Stanton County, Nebraska | Cancelled | Not stated | 2021 | 2021 |
| Microsoft Perry Township | Allen County, Ohio | Cancelled | Not stated | 2024 | Oct 2024 |
| Former Hynix plant proposal | Eugene, Oregon | Cancelled | Not stated | 2026 | Sep 2026 |
| CleanSpark Limestone (GRIID) | Washington County, Tennessee | Cancelled | Not stated | 2024 | 2026 |
| Prince William Digital Gateway | Prince William County, Virginia | Cancelled | Not stated | 2021 | Jul 2026 |
| Microsoft Caledonia | Caledonia, Wisconsin | Cancelled | Not stated | 2025 | 2025 |
| QTS DeForest / Vienna | DeForest, Wisconsin | Cancelled | Not stated | 2025 | Feb 2026 |
| Brightseat Tech Park | Landover, Maryland | Paused | 820 MW | 2024 | Jul 2026 |
| Unnamed project (Avista MOU) | Spokane County, Washington | Paused | 500 MW | 2026 | Nov 2026 |
| Riverview Innovation and Technology Campus | Tonawanda, New York | Paused | 300 MW | Not stated | 2026 |
| Sanford Woods Campus | Sanford, Maine | Paused | Not stated | 2026 | Aug 2026 |
| Amazon Becker | Becker, Minnesota | Paused | Not stated | 2024 | Jun 2025 |
| Amazon Sunbury Campus | Sunbury, Ohio | Paused | Not stated | 2024 | Apr 2026 |
| RELLIS Campus Data and Research Center | Brazos County, Texas | Paused | Not stated | 2020 | Not stated |
| Red Butte Energy and Data Center Campus | Iron County, Utah | Paused | Not stated | 2026 | May 2026 |
| Balloonist LLC Menomonie | Menomonie, Wisconsin | Paused | Not stated | 2025 | Jan 2026 |
Sources
- Staged record: projects.csv (stage counts across 1,320 projects; all 40 cancelled and paused rows with their source keys and locators) · Data Center Fact Check · Checked November 22, 2026
- Decision and Final Order, CZICB Appeal No. 2026-01 (Starwood Digital Ventures) · Delaware Coastal Zone Industrial Control Board · 2026 · Decision and Final Order, CZICB Appeal No. 2026-01 (Starwood Digital Ventures)
- PW Digital Gateway · Prince William County · Updated August 5, 2026
- Draft Resolution (ZTA 8-14 packet): pause on acceptance of land use and permit applications for data centers · Spokane County Board of County Commissioners · August 18, 2026 · Draft resolution, ZTA 8-14 packet
- Preliminary Plan of Subdivision 4-23024, Brightseat Tech Park, Technical Staff Report · Maryland-National Capital Park and Planning Commission, Prince George's County Planning Department · March 7, 2024 · Preliminary Plan of Subdivision 4-23024, Brightseat Tech Park
- Exploring the potential to expand our presence in Ohio · Microsoft · August 12, 2024 · Microsoft's account of exploring the Perry Township site, Allen County, Ohio