Skip to content

Project File

Androscoggin Mill Data Center (Sentinel / JGT2)

Jay,Franklin County,MaineCancelledFirst public 2026Filing entity: JGT2 RedevelopmentLast checked Nov 8, 2026

JGT2 RedevelopmentDeveloperSentinel Data CentersOperator

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Electric utility
  • Confirmed: First public date
  • Still to confirm: Capacity
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Androscoggin Mill Data Center (Sentinel / JGT2) is a cancelled data center project in Jay, Franklin County, Maine. Sentinel Data Centers is named as operator. It was first public in 2026. No site capacity figure is published for this project.

Androscoggin Mill Data Center (Sentinel / JGT2) is a cancelled data center project in Jay, Franklin County, Maine. Sentinel Data Centers is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Jay, Franklin County, Maine. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Franklin County, Maine.See every project on the map

Timeline

  1. · New projectFirst public record of Androscoggin Mill Data Center (Sentinel / JGT2)Cancelled

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Maine LD 713: Excludes data centers from two state business tax incentives

    The act covers property in a data center, or in the portion of a facility that is a data center, that begins operations on or after August 1, 2026, including expansions, which is excluded from the business equipment tax exemption; this project has no capacity figure on record, but the date this project began operations or will begin operations is not on record.

    “Any property located in a data center or in the portion of a facility that constitutes a data center that begins operations on or after August 1, 2026, including any property located in a data center or in the portion of a facility that constitutes a data center that is part of an expansion or project after August 1, 2026.” (PL 2025, c. 768, Sec. 1 (36 MRSA Sec. 691, sub-Sec. 1, para. A, subpara. (10)))

    Rule checks: Project is in Maine. Still to check: dates: not checked, who it covers: not checked

Bills and laws in Maine

Open Bill Watch

Who's involved

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Androscoggin Mill Data Center (Sentinel / JGT2)?
    Androscoggin Mill Data Center (Sentinel / JGT2) is a data center project in Jay, Franklin County, Maine.
    Who operates Androscoggin Mill Data Center (Sentinel / JGT2)?
    Sentinel Data Centers is named as the operator of Androscoggin Mill Data Center (Sentinel / JGT2).
    What stage is Androscoggin Mill Data Center (Sentinel / JGT2)?
    Androscoggin Mill Data Center (Sentinel / JGT2) is cancelled. It was first public in 2026.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Sentinel DC backs off paper mill data center project in Maine
      Data Center Dynamics
      Tier 3 · Captured 2026-11-08 · Open the source
    2. 2
      Maine: Shutdown 2.0 - Mill Redevelopment Project Stymied by Data Center Resistance
      Site Selection Magazine
      Tier 3 · Captured 2026-11-08 · Open the source
    3. 3
      EIA Form 861, Service Territory file, 2025 (final)
      U.S. Energy Information Administration
      Tier 1 · Captured 2026-11-11 · Open the source · Archived copy

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page