Project File
Sanford Woods Industrial and Technical Campus
Sanford,York County,MainePausedFirst public 2026Filing entity: New England Energy CompanyLast checked Nov 8, 2026
New England Energy CompanyDeveloper
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: First public date
- Still to confirm: Capacity
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Sanford Woods Industrial and Technical Campus is a paused data center project in Sanford, York County, Maine. New England Energy Company is named as developer. It was first public in 2026. No site capacity figure is published for this project.
Sanford Woods Industrial and Technical Campus is a paused data center project in Sanford, York County, Maine. New England Energy Company is named as developer. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Sanford, York County, Maine. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Timeline
- · New projectFirst public record of Sanford Woods Industrial and Technical CampusPaused
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Maine LD 713: Excludes data centers from two state business tax incentives
The act covers property in a data center, or in the portion of a facility that is a data center, that begins operations on or after August 1, 2026, including expansions, which is excluded from the business equipment tax exemption; this project has no capacity figure on record, but the date this project began operations or will begin operations is not on record.
“Any property located in a data center or in the portion of a facility that constitutes a data center that begins operations on or after August 1, 2026, including any property located in a data center or in the portion of a facility that constitutes a data center that is part of an expansion or project after August 1, 2026.” (PL 2025, c. 768, Sec. 1 (36 MRSA Sec. 691, sub-Sec. 1, para. A, subpara. (10)))
Rule checks: Project is in Maine. Still to check: dates: not checked, who it covers: not checked
Bills and laws in Maine
- LD 307 · Vetoed · Apr 29, 2026Would have paused large data center permits until November 2027
- LD 713 · Signed into law · Apr 23, 2026Excludes data centers from two state business tax incentives
Who's involved
- DeveloperNew England Energy Company
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Sanford Woods Industrial and Technical Campus?
- Sanford Woods Industrial and Technical Campus is a data center project in Sanford, York County, Maine.
- Who is developing Sanford Woods Industrial and Technical Campus?
- New England Energy Company is named as the developer of Sanford Woods Industrial and Technical Campus.
- How big is Sanford Woods Industrial and Technical Campus?
- The site covers 1,060 acres.
- What stage is Sanford Woods Industrial and Technical Campus?
- Sanford Woods Industrial and Technical Campus is paused. It was first public in 2026.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Sanford AI data center proposal faces pushback, possible moratorium
Seacoastonline (York County Coast Star)Tier 3 · Captured 2026-11-08 · Open the source - 2Maine committee backs bill that would halt Sanford AI data center project
Seacoastonline (York County Coast Star)Tier 3 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page