Riverview Innovation and Technology Campus Data Center

Tonawanda,Erie County,New YorkPausedFiling entity: Riverview Innovation and Technology CampusLast checked Nov 8, 2026

RITCDeveloperNational GridElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Still to confirm: Electric utility
  • Still to confirm: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Riverview Innovation and Technology Campus Data Center is a paused data center project in Tonawanda, Erie County, New York. RITC is named as developer. It was announced at 300 MW.

Riverview Innovation and Technology Campus Data Center is a paused data center project in Tonawanda, Erie County, New York. RITC is named as developer. It was announced at 300 MW. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Tonawanda, Erie County, New York. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

300 MWAnnounced capacity
0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Newswire for Riverview Innovation and Technology Campus Data Center

  1. What the record shows · November 22, 2026

    31 data center projects cancelled, 9 paused: the stopped projects in the public record, one by one

  2. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  3. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

Aerial view of Riverview Innovation and Technology Campus Data Center (RITC) in Tonawanda, Erie County, New York, captured 2019
Aerial image, USDA National Agriculture Imagery Program, via the USGS National Map, Public domain (USDA NAIP), captured 2019Aerial images can be older than the campus. This one shows what was on the ground when it was taken.Source: USDA National Agriculture Imagery Program, via the USGS National MapLicense: Public domain (USDA NAIP)
Site-level positionPin placed from the position we have on file, inside Erie County, New York.See every project on the map

The land, to scale

One football field
140 acres, about 106 football fields. Drawn as a square for scale; the real shape is not known.

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026New York EO 62: Pauses state permits for large data centers pending new standards

    The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has 300 MW announced on record, but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.

    “oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))

    Rule checks: Project is in New York; 300 MW on record (announced), threshold 50 MW (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition)). Still to check: dates: not checked, who it covers: not checked

Bills and laws in New York

Open Bill Watch

Who's involved

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Riverview Innovation and Technology Campus Data Center?
    Riverview Innovation and Technology Campus Data Center is a data center project in Tonawanda, Erie County, New York.
    Who is developing Riverview Innovation and Technology Campus Data Center?
    RITC is named as the developer of Riverview Innovation and Technology Campus Data Center.
    How big is Riverview Innovation and Technology Campus Data Center?
    Riverview Innovation and Technology Campus Data Center was announced at 300 MW of capacity. The site covers 140 acres.
    What stage is Riverview Innovation and Technology Campus Data Center?
    Riverview Innovation and Technology Campus Data Center is paused.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Former coke plant near Buffalo eyed for 300MW data center
      Data Center Dynamics
      Tier 3 · Captured 2026-11-08 · Open the source
    2. 2
      RITC and Data Centers in Erie & Niagara Counties
      Clean Air Coalition of Western New York
      Tier 3 · Captured 2026-11-08 · Open the source
    3. 3
      U.S. Census Geocoder (batch geographies endpoint)
      U.S. Census Bureau
      Tier 1 · Captured 2026-11-11 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page