Data Center Fact Check tracks 23 data center projects in New York as of November 2026: 18 operating, 2 in permitting and 1 proposed, totaling about 2,464 MW announced where a figure is published.
New York has 23 tracked data centers. Their announced capacity totals about 2,464 MW where a figure is published. Of those, 18 operating, 2 in permitting and 1 proposed. Every figure comes from the public record linked on this page.
Data center projects in New York
- Coinmint Massena
OperatingMassena
- CoreSite NY1
OperatingNew York
- CyrusOne Wappingers Falls
OperatingWappingers Falls3 MW announced
- DataBank LGA1 (New York City)
OperatingNew York
- DataBank LGA2 (New York City)
OperatingNew York
- DataBank LGA3 (New York City)
OperatingNew York
- DataBank LGA4 (New York City)
OperatingNew York
- Digi Power X North Tonawanda
OperatingNorth Tonawanda60 MW announced
- Digital Realty 32 Avenue of the Americas
OperatingNew York10 MW announced
- Digital Realty JFK10 (New York)
OperatingNew York
- Digital Realty JFK12 (New York)
OperatingNew York
- Digital Realty JFK13 (New York)
OperatingNew York
- Equinix NY13 (New York metro)
OperatingElmsford
- Equinix NY9 (New York metro)
OperatingNew York
- Greenidge Dresden Power and Data Center
OperatingDresden
- NYDIG Massena East Data Center Campus
In permittingMassena635 MW announced
- Riverview Innovation and Technology Campus Data Center
PausedTonawanda300 MW announced
- Sabey Data Centers SDC Manhattan (New York)
OperatingNew York18 MW announced
- Sabey SDC Manhattan
OperatingNew York18 MW announced
- Stream Data Centers Project Double Reed at STAMP
In permittingAlabama500 MW announced
- TeraWulf Lake Hawkeye
ProposedLansing320 MW announced
- TeraWulf Lake Mariner Data Center
ExpandingBarker600 MW announced
- Yahoo Lockport Data Center
OperatingLockport
Who serves this place
- Not collected yet.
Counties and cities in New York
Counties
- Dutchess County1 data center project tracked
- Erie County1 data center project tracked
- Genesee County1 data center project tracked
- New York County12 data center projects tracked
- Niagara County3 data center projects tracked
- St. Lawrence County2 data center projects tracked
- Tompkins County1 data center project tracked
- Westchester County1 data center project tracked
- Yates County1 data center project tracked
Cities and towns
- New York12 data center projects tracked
- Massena2 data center projects tracked
- Alabama1 data center project tracked
- Barker1 data center project tracked
- Dresden1 data center project tracked
- Elmsford1 data center project tracked
- Lansing1 data center project tracked
- Lockport1 data center project tracked
- North Tonawanda1 data center project tracked
- Tonawanda1 data center project tracked
- Wappingers Falls1 data center project tracked
Tax breaks and payments
Sales and use tax exemption (N.Y. Tax Law Sec. 1115(a)(37) and Sec. 1115(y))
An operator of an Internet data center in New York does not pay state or local sales and use tax on machinery, equipment, and other tangible personal property bought for use in the center, including computer system hardware, pre-written software, storage racks and cages, climate-control property, power generators and conditioners, raised flooring, and data center building systems, fire control, and security property. Services to install, maintain, service, and repair the exempt property, and protective and detective services, are also exempt. The operator claims the exemption with Form ST-121.5; there is no certification, investment threshold, or jobs threshold in the program.
Bills and laws in New York
- EO 62 · In effect · Jul 14, 2026Pauses state permits for large data centers pending new standards
- A11560 · Passed both chambers · Jun 4, 2026Would pause large data center permits and set rate classes
- A9086 · In committee · Jun 1, 2026Regulates data center energy use and requires disclosure reports
- S9182 · In committee · May 22, 2026Bars power allocations and caps state aid for data centers
- S9144A · In committee · May 12, 2026Would pause data center permits until state rules are finished
- S9288 · In committee · Feb 25, 2026Repeals sales tax exemptions for data center equipment
Newswire for New York
What the record shows · November 22, 2026
31 data center projects cancelled, 9 paused: the stopped projects in the public record, one by one
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
Officials we track for New York
The lawmakers and local officials whose recorded jurisdiction is New York, with the bills and votes we have on record for each.
- Alex BoresAssemblymember · 73
- Amy PaulinAssemblymember · 88
- Anil Beephan, Jr.Assemblymember · 105
- Anna R. KellesAssemblymember · 125
- April N.M. BaskinState Senator · 63
- Brian CunninghamAssemblymember · 43
- Brian KavanaghState Senator · 27
- Cordell CleareState Senator · 30
- Dana LevenbergAssemblymember · 95
- Deborah J. GlickAssemblymember · 66
- Diana C. MorenoAssemblymember · 36
- Didi BarrettAssemblymember · 106
- Donna A. LupardoAssemblymember · 123
- Emérita TorresAssemblymember · 85
- Emily GallagherAssemblymember · 50
- Gabriella A. RomeroAssemblymember · 109
- Grace LeeAssemblymember · 65
- Gustavo RiveraState Senator · 33
- Harry B. BronsonAssemblymember · 138
- Jabari BrisportState Senator · 25
- James Sanders Jr.State Senator · 10
- Jen LunsfordAssemblymember · 135
- Jeremy J. ZellnerState Senator · 61
- Jonathan G. JacobsonAssemblymember · 104
- Jonathan RiveraAssemblymember · 149
- Jose M. SerranoState Senator · 29
- Joseph P. Addabbo Jr.State Senator · 15
- Julia SalazarState Senator · 18
- Karen McMahonAssemblymember · 146
- Kathy HochulGovernor
- Kristen GonzalezState Senator · 59
- Lea WebbState Senator · 52
- Leroy ComrieState Senator · 14
- Linda B. RosenthalAssemblymember · 67
- Liz KruegerState Senator · 28
- Marcela MitaynesAssemblymember · 51
- Maritza DavilaAssemblymember · 53
- MaryJane ShimskyAssemblymember · 92
- Micah C. LasherAssemblymember · 69
- Michael S. CashmanAssemblymember · 115
- Michelle HincheyState Senator · 41
- Nathalia FernandezState Senator · 34
- Nikki LucasAssemblymember · 60
- Patricia FahyState Senator · 46
- Patrick J. CarrollAssemblymember · 96
- Paula Elaine KayAssemblymember · 100
- Phara Souffrant ForrestAssemblymember · 57
- Rachel MayState Senator · 48
- Rebecca KassayAssemblymember · 4
- Robert JacksonState Senator · 31
Questions people ask
- How many data centers are in New York?
- Data Center Fact Check tracks 23 data center projects in New York as of November 2026. Of those, 18 operating, 2 in permitting and 1 proposed.
- What is the biggest data center in New York?
- By announced capacity, the biggest data center in New York is NYDIG Massena East Data Center Campus, announced at 635 MW. It is in permitting.
- How much power do data centers in New York use?
- The 23 projects tracked in New York have announced about 2,464 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Tax Bulletin ST-405, Internet Data Centers
New York State Department of Taxation and FinanceTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "New York." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ny
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page