New YorkExecutive Office of the Governor2026Executive order
EO 62: Pauses state permits for large data centers pending new standards
Official title: Establishing a Temporary Moratorium on Data Centers in New York While the State Develops Higher Standards for Data Center Development and Benefits Blueprint to Support Localities
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
In effect as of Jul 14, 2026. The official record says: in effect.
- Issued (executive or agency action) (done)
- In effect (current stage)
- Ended or expired (not reached)
What it means for a household (draft rating)
Unclear for households. The order holds data center permit applications at the environmental agency until a statewide environmental study is filed.
"Until DPS submits its report of the final Generic Environmental Impact Statement and associated findings statement, the Department of Environmental Conservation (DEC), consistent with its obligations under SEQRA, is directed to hold in abeyance all applications for any discretionary permit, approval, license, or similar form of permission for the construction or expansion of a data center"Data Center Permitting Moratorium section
We rate a bill as helping or costing households only when its own text says who pays or who is exempt. Otherwise it is unclear. This is a draft rating and has not been verified yet.
What it does
Pause or moratorium
Applies to: DEC discretionary permit applications for data center construction or expansion not determined complete before July 14, 2026 (New York)
Starts: 2026-07-14.
“Until DPS submits its report of the final Generic Environmental Impact Statement and associated findings statement, the Department of Environmental Conservation (DEC), consistent with its obligations under SEQRA, is directed to hold in abeyance all applications for any discretionary permit, approval, license, or similar form of permission for the construction or expansion of a data center that (1) are or may hereafter be pending before DEC and (2) have not been determined to be complete by DEC before the date of this Executive Order.”
Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)"
Definition · threshold 50 MW
Applies to: facilities that count as data centers under the order (New York)
Starts: 2026-07-14.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more…”
Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition)
Study or report
Applies to: data centers statewide, through the Department of Public Service (New York)
Starts: 2026-07-14.
“DPS is further directed to initiate a formal public process, including public comment and a public hearing, to create a Generic Environmental Impact Statement in accordance with the requirements of the State Environmental Quality Review Act at Article 8 of the Environmental Conservation Law and the regulations promulgated thereunder (collectively, SEQRA), to assess the potential environmental impacts of the construction and operation of data centers in the State, including energy demand, water use and quality, air quality, disproportionate impacts on disadvantaged communities, and noise levels.”
Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)"
Who it touches (18)
Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Coinmint Massena
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has no capacity figure on record, but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CoreSite NY1
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has no capacity figure on record, but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank LGA1 (New York City)
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has no capacity figure on record, but the project's energy consumption and its permit application status before the Department of Environmental Conservation and its completeness date is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank LGA2 (New York City)
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has no capacity figure on record, but the project's energy consumption and its permit application status before the Department of Environmental Conservation and its completeness date is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank LGA3 (New York City)
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has no capacity figure on record, but the project's energy consumption and its permit application status before the Department of Environmental Conservation and its completeness date is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026DataBank LGA4 (New York City)
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has no capacity figure on record, but the project's energy consumption and its permit application status before the Department of Environmental Conservation and its completeness date is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digi Power X North Tonawanda
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has 60 MW on record (generator capacity), but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York; 60 MW on record (announced), threshold 50 MW (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition)). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty JFK10 (New York)
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has no capacity figure on record, but the project's energy consumption and its permit application status before the Department of Environmental Conservation and its completeness date is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty JFK12 (New York)
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has no capacity figure on record, but the project's energy consumption and its permit application status before the Department of Environmental Conservation and its completeness date is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty JFK13 (New York)
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has no capacity figure on record, but the project's energy consumption and its permit application status before the Department of Environmental Conservation and its completeness date is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix NY13 (New York metro)
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has no capacity figure on record, but the project's energy consumption and its permit application status before the Department of Environmental Conservation and its completeness date is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Equinix NY9 (New York metro)
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has no capacity figure on record, but the project's energy consumption and its permit application status before the Department of Environmental Conservation and its completeness date is not on record. Status part: the bill's status (in effect) makes its text operative, and no part of this decision rests on status beyond that. Text part: the decision rests on the bill's text quoted here, which sets the conditions named above.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York. Still to check: size: unknown, dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Greenidge Dresden Power and Data Center
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has 60 MW on record (grid connection), but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York; 60 MW on record (grid connection), threshold 50 MW (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition)). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026NYDIG Massena East Data Center Campus
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has 635 MW announced on record, but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York; 635 MW on record (announced), threshold 50 MW (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition)). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Riverview Innovation and Technology Campus Data Center
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has 300 MW announced on record, but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York; 300 MW on record (announced), threshold 50 MW (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition)). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Stream Data Centers Project Double Reed at STAMP
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has 600 MW on record (grid connection), but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York; 600 MW on record (grid connection), threshold 50 MW (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition)). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026TeraWulf Lake Hawkeye
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has 320 MW announced on record, but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York; 320 MW on record (announced), threshold 50 MW (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition)). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026TeraWulf Lake Mariner Data Center
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has 600 MW on record (IT load), but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York; 600 MW on record (it load), threshold 50 MW (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition)). Still to check: dates: not checked, who it covers: not checked
Other projects we track in New York (5), not affected
- CyrusOne Wappingers FallsOperating
- Digital Realty 32 Avenue of the AmericasOperating
- Sabey Data Centers SDC Manhattan (New York)Operating
- Sabey SDC ManhattanOperating
- Yahoo Lockport Data CenterOperating
Who acted
- SponsorKathy Hochul
Timeline
Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.
- Executive Order 62 issued by Governor Kathy Hochul, establishing a temporary moratorium on data center permits; in effect July 14, 2026Stage: In effect
More from New York
- A11560 · Passed both chambersWould pause large data center permits and set rate classes
- A9086 · In committeeRegulates data center energy use and requires disclosure reports
- S9182 · In committeeBars power allocations and caps state aid for data centers
- S9144A · In committeeWould pause data center permits until state rules are finished
- S9288 · In committeeRepeals sales tax exemptions for data center equipment
Sources
- 1Executive Order No. 62: Establishing a Temporary Moratorium on Data Centers in New York While the State Develops Higher Standards for Data Center Development and Benefits Blueprint to Support Localities
Office of the Governor of New York (governor.ny.gov)Tier 1 · Open the source - 2Executive Order No. 62: Establishing a Temporary Moratorium on Data Centers in New York (full text)
Governor of New York (governor.ny.gov)Tier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.