Project File
Digi Power X North Tonawanda
North Tonawanda,Niagara County,New YorkOperatingFiling entity: Digi Power X Inc.Last checked Nov 8, 2026
Digi Power XOperator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Still to confirm: Electric utility
- Still to confirm: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Digi Power X North Tonawanda is an operating data center project in North Tonawanda, Niagara County, New York. Digi Power X is named as operator. It was announced at 60 MW.
Digi Power X North Tonawanda is an operating data center project in North Tonawanda, Niagara County, New York. Digi Power X is named as operator. It was announced at 60 MW. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in North Tonawanda, Niagara County, New York. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026New York EO 62: Pauses state permits for large data centers pending new standards
The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has 60 MW on record (generator capacity), but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.
“oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))
Rule checks: Project is in New York; 60 MW on record (announced), threshold 50 MW (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition)). Still to check: dates: not checked, who it covers: not checked
Bills and laws in New York
- EO 62 · In effect · Jul 14, 2026Pauses state permits for large data centers pending new standards
- A11560 · Passed both chambers · Jun 4, 2026Would pause large data center permits and set rate classes
- A9086 · In committee · Jun 1, 2026Regulates data center energy use and requires disclosure reports
- S9182 · In committee · May 22, 2026Bars power allocations and caps state aid for data centers
- S9144A · In committee · May 12, 2026Would pause data center permits until state rules are finished
- S9288 · In committee · Feb 25, 2026Repeals sales tax exemptions for data center equipment
Who's involved
- OperatorDigi Power X
Power
Capacity, as announced or filed
- 60 MW · On-site power plant (as acquired)Jan 2023 · generator_capacity
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Digi Power X North Tonawanda?
- Digi Power X North Tonawanda is a data center project in North Tonawanda, Niagara County, New York.
- Who operates Digi Power X North Tonawanda?
- Digi Power X is named as the operator of Digi Power X North Tonawanda.
- How big is Digi Power X North Tonawanda?
- Digi Power X North Tonawanda was announced at 60 MW of capacity.
- What stage is Digi Power X North Tonawanda?
- Digi Power X North Tonawanda is operating.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1City's data center moratorium in New York impacts Digi Power X's hopes to convert cryptomine to AI data center
Data Center DynamicsTier 3 · Captured 2026-11-08 · Open the source - 2Digihost Provides Update on Power Plant Acquisition
Digihost Technology Inc.Tier 4 · Captured 2026-11-08 · Open the source - 3U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page