Yahoo Lockport Data Center
Lockport,Niagara County,New YorkOperatingFiling entity: Yahoo! Inc.Last checked Nov 14, 2026
NYPAElectric utilityYahooOperator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
4 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Still to confirm: Electric utility
- Still to confirm: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Yahoo Lockport Data Center is an operating data center project in Lockport, Niagara County, New York. Yahoo is named as operator. No site capacity figure is published for this project.
Yahoo Lockport Data Center is an operating data center project in Lockport, Niagara County, New York. Yahoo is named as operator. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Lockport, Niagara County, New York. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Bills and laws in New York
- EO 62 · In effect · Jul 14, 2026Pauses state permits for large data centers pending new standards
- A11560 · Passed both chambers · Jun 4, 2026Would pause large data center permits and set rate classes
- A9086 · In committee · Jun 1, 2026Regulates data center energy use and requires disclosure reports
- S9182 · In committee · May 22, 2026Bars power allocations and caps state aid for data centers
- S9144A · In committee · May 12, 2026Would pause data center permits until state rules are finished
- S9288 · In committee · Feb 25, 2026Repeals sales tax exemptions for data center equipment
Who's involved
Power
Capacity, as announced or filed
- 15 MW · Phase I NYPA hydropower allocationMay 2015 · grid connection
- 7.2 MW · Expansion NYPA hydropower allocationMay 2015 · grid connection
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is Yahoo Lockport Data Center?
- Yahoo Lockport Data Center is a data center project in Lockport, Niagara County, New York.
- Who operates Yahoo Lockport Data Center?
- Yahoo is named as the operator of Yahoo Lockport Data Center.
- What stage is Yahoo Lockport Data Center?
- Yahoo Lockport Data Center is operating.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Cuomo unveils grand opening of Yahoo's new state-of-the-art ctr. in Lockport; 115 new jobs and $170m in capital investment
New York Real Estate JournalTier 3 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page