Skip to content

Project File

Greenidge Dresden Power and Data Center

Dresden,Yates County,New YorkOperatingFiling entity: Greenidge Generation Holdings Inc.Last checked Nov 8, 2026

Vulcan Infrastructure and PowerDeveloper and operatorNYSEGElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Still to confirm: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Greenidge Dresden Power and Data Center is an operating data center project in Dresden, Yates County, New York. Vulcan Infrastructure and Power is named as operator. No site capacity figure is published for this project.

Greenidge Dresden Power and Data Center is an operating data center project in Dresden, Yates County, New York. Vulcan Infrastructure and Power is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Dresden, Yates County, New York. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Yates County, New York.See every project on the map

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026New York EO 62: Pauses state permits for large data centers pending new standards

    The act covers data centers that consume or can consume 50 megawatts of energy or more, whose applications for Department of Environmental Conservation permits for construction or expansion were not determined complete before July 14, 2026; this project has 60 MW on record (grid connection), but the project's permit application status before the Department of Environmental Conservation and its completeness date is not on record.

    “oftentimes on a continuous twenty-four-hour cycle, and (3) consume or can consume 50 megawatts of energy or more” (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition))

    Rule checks: Project is in New York; 60 MW on record (grid connection), threshold 50 MW (Executive Order No. 62, section "Data Center Permitting Moratorium and Generic Environmental Impact Statement (GEIS)" (definition)). Still to check: dates: not checked, who it covers: not checked

Bills and laws in New York

Open Bill Watch

Who's involved

Power

Capacity, as announced or filed

  • 60 MW · AI/HPC conversion, proposed grid supplyMay 2026 · grid connection

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Greenidge Dresden Power and Data Center?
    Greenidge Dresden Power and Data Center is a data center project in Dresden, Yates County, New York.
    Who operates Greenidge Dresden Power and Data Center?
    Vulcan Infrastructure and Power is named as the operator of Greenidge Dresden Power and Data Center.
    What stage is Greenidge Dresden Power and Data Center?
    Greenidge Dresden Power and Data Center is operating.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Greenidge Generation Reports First Quarter 2026 Results and Advances AI/HPC Infrastructure Expansion
      Greenidge Generation Holdings Inc.
      Tier 4 · Captured 2026-11-08 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page