Northeast Brighton data center campus (withdrawn application)

Brighton,Adams County,ColoradoCancelledFirst public 2026Filing entity: DewberryLast checked Nov 8, 2026

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

4 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: First public date
  • Still to confirm: Capacity
  • Still to confirm: Electric utility
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Northeast Brighton data center campus (withdrawn application) is a cancelled data center project in Brighton, Adams County, Colorado. It was first public in 2026. No site capacity figure is published for this project.

Northeast Brighton data center campus (withdrawn application) is a cancelled data center project in Brighton, Adams County, Colorado. No site capacity figure is published for this project. 4 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Brighton, Adams County, Colorado. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

0Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Adams County, Colorado.See every project on the map

Timeline

  1. · New projectFirst public record of Northeast Brighton data center campus (withdrawn application)Cancelled

Bills and laws in Colorado

Open Bill Watch

Public records

0 records found so far. 9 kinds of record are still being collected.

    See every record

    Questions people ask

    Where is Northeast Brighton data center campus (withdrawn application)?
    Northeast Brighton data center campus (withdrawn application) is a data center project in Brighton, Adams County, Colorado.
    What stage is Northeast Brighton data center campus (withdrawn application)?
    Northeast Brighton data center campus (withdrawn application) is cancelled. It was first public in 2026.

    Sources

    Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

    1. 1
      Brighton approves data center moratorium
      Colorado Public Radio
      Tier 3 · Captured 2026-11-08 · Open the source

    No corrections have been published for this page. Corrections log · Report an error or send a tip on this page