Data centers in Adams County, Colorado
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 5 data center projects in Adams County, Colorado as of November 2026: 1 announced, 1 proposed and 1 in permitting, totaling about 342 MW announced where a figure is published.
Adams County has 5 tracked data centers. Their announced capacity totals about 342 MW where a figure is published. Of those, 1 announced, 1 proposed and 1 in permitting. Every figure comes from the public record linked on this page.
Data center projects in Adams County
- 365 Data Centers Aurora (CO1)
OperatingAurora8 MW announced
- Aerotropolis Logistics Center data center (Aurora application)
ProposedAurora
- Northeast Brighton data center campus (withdrawn application)
CancelledBrighton
- NTT Global Data Centers Aurora
AnnouncedAurora
- Vantage Trident data center campus
In permittingAurora334 MW announced
Who serves this place
- Not collected yet.
A data center is proposed in Adams County
2 projects here are at the announced or proposed stage. Before the hearing, the resident checklist walks through what to check: the proposal's documents, the local rules where you live, the tax agreement, and the recorded votes.
Places in and around Adams County
Adams County is part of Colorado.
Cities and towns
- Aurora6 data center projects tracked
- Brighton1 data center project tracked
- Westminster1 data center project tracked
Nearby places
- Denver County8 data center projects tracked
- Arapahoe County6 data center projects tracked
- Douglas County6 data center projects tracked
- El Paso County3 data center projects tracked
- Weld County2 data center projects tracked
- Huerfano County1 data center project tracked
- Jefferson County1 data center project tracked
Court cases and commission dockets in Colorado (3)
Bills and laws in Colorado
- SB 26-102 · Died or failed · May 11, 2026Sets renewable power and grid cost rules for large data centers
- HB 26-1030 · Died or failed · May 7, 2026Creates a data center authority and 20-year sales tax exemption
- SB 25-280 · Died or failed · May 8, 2025Creates tax exemptions and grid planning for certified data centers
- SB 24-085 · Died or failed · Apr 30, 2024Sales and use tax rebate for data center (digital asset) purchases
- SB 23-207 · Died or failed · Apr 11, 2023Sales and use tax refund for data center purchases
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Adams County?
- Data Center Fact Check tracks 5 data center projects in Adams County as of November 2026. Of those, 1 announced, 1 proposed and 1 in permitting.
- What is the biggest data center in Adams County?
- By announced capacity, the biggest data center in Adams County is Vantage Trident data center campus, announced at 334 MW. It is in permitting.
- How much power do data centers in Adams County use?
- The 5 projects tracked in Adams County have announced about 342 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Adams County." Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-co-adams
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page