ColoradoHouse of Representatives2026 Regular SessionBill
HB 26-1030: Creates a data center authority and 20-year sales tax exemption
Official title: Data Center & Utility Modernization
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Died or failed as of May 7, 2026. The official record says: Postponed indefinitely in House Energy & Environment.
- Filed (done)
- In committee (done)
- Passed one chamber (not reached)
- Passed both chambers (not reached)
- Signed into law (not reached)
- In effect (not reached)
- Died or failed (current stage)
What it does
Definition · threshold 100 MW
Applies to: customers of PUC-regulated utilities (Colorado)
“"EMERGING LARGE-LOAD CUSTOMER" MEANS A CUSTOMER OF A UTILITY WITH PROJECTED LOAD REQUIREMENTS OF AT LEAST ONE HUNDRED MEGAWATTS, EITHER INDIVIDUALLY OR IN THE AGGREGATE THROUGH COLOCATED CUSTOMERS.”
Introduced text, section 3, new C.R.S. 40-2-140(1)
Tax exemption
Applies to: certified data centers (Colorado)
Starts: 2027-01-01.
“BEGINNING JANUARY 1, 2027, ALL SALES AND USE OF QUALIFIED DATA CENTER INFRASTRUCTURE AND SYSTEMS THAT WILL BE PURCHASED AND USED IN CONNECTION WITH A CERTIFIED DATA CENTER FOR WHICH A DATA CENTER OPERATOR HAS A STATE SALES AND USE TAX EXEMPTION CERTIFICATE IS EXEMPT FROM TAXATION UNDER PARTS 1 AND 2 OF THIS ARTICLE 26.”
Introduced text, section 5, new C.R.S. 39-26-735(3)
Tax exemption
Applies to: certified data center operators (Colorado)
“FOR TWENTY YEARS FROM THE DATE THAT THE DATA CENTER RECEIVED CERTIFICATION [the operator is eligible], conditioned on maintaining the employment and compensation commitment and submitting annual compliance reports.”
Introduced text, section 1, new C.R.S. 24-48.5-808(1)(b)
Reporting duty
Applies to: certified data center operators (Colorado)
“INCLUDE IN THE REPORT THE TOTAL AMOUNT OF THE STATE SALES AND USE TAX EXEMPTION CLAIMED EACH YEAR [annual compliance report to the authority].”
Introduced text, section 1, new C.R.S. 24-48.5-808(3)
Tax exemption
Applies to: certified data center operators (Colorado)
“A DATA CENTER OPERATOR OF A CERTIFIED DATA CENTER IS ELIGIBLE FOR A ONE HUNDRED PERCENT STATE SALES AND USE TAX EXEMPTION ON QUALIFIED PURCHASES PURSUANT TO SECTION 39-26-735.”
Introduced text, section 1, new C.R.S. 24-48.5-808(1)(a)
Who it touches
No project we track is matched to this bill or order: its rules do not reach them, or a check found it does not apply.
Other projects we track in Colorado (34), not affected
- 365 Data Centers Aurora (CO1)Operating
- Aerotropolis Logistics Center data center (Aurora application)Proposed
- BluSky AI Walsenburg data centerAnnounced
- Centersquare DEN2Operating
- Cielo Hudson data center campusProposed
- CoreSite DE3 (Race Street campus)Under construction
- CoreSite Denver data centers (DE1, DE2)Operating
- DataBank DEN1 (Denver)Operating
- DataBank DEN1 (Englewood)Operating
- DataBank DEN2 (Centennial)Operating
- DataBank DEN3 (Downtown Denver)Operating
- DataBank DEN4 (Denver)Operating
- DataBank DEN4 (Westminster)Operating
- DataBank DEN5 (Centennial II)Operating
- DataBank DEN5 (Denver)Operating
- EdgeConneX Denver CampusExpanding
- Equinix Denver data centers (DE1, DE2)Operating
- Flexential Aurora data centerOperating
- Flexential Centennial data centerOperating
- Flexential Denver-Parker data centerUnder construction
- Flexential Englewood data centerOperating
- Fontus Data Centre ProjectAnnounced
- Global AI data center (Weld County)Approved
- H5 Data Centers Denver campusOperating
- Iron Mountain Data Centers Iron Mountain Denver (Denver)Operating
- Iron Mountain DEN-1 (Denver)Operating
- Northeast Brighton data center campus (withdrawn application)Cancelled
- Novva Data Centers Colorado SpringsOperating
- NTT Global Data Centers AuroraAnnounced
- OneNeck Denver Data CenterOperating
- QTS Aurora-Denver data center campus (Denver 1)Under construction
- QTS Colorado Springs data centerOperating
- Raeden Project Taurus (Colorado Springs)Approved
- Vantage Trident data center campusIn permitting
Who acted
- Primary sponsorDuranHouse
- Primary sponsorValdezHouse
- SponsorMullicaSenate
Timeline
Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.
- · HouseIntroduced In House - Assigned to Energy & EnvironmentStage: In committee
- · HouseHouse Committee on Energy & Environment Postpone IndefinitelyStage: Died or failed
More from Colorado
- SB 26-102 · Died or failedSets renewable power and grid cost rules for large data centers
- SB 25-280 · Died or failedCreates tax exemptions and grid planning for certified data centers
- SB 24-085 · Died or failedSales and use tax rebate for data center (digital asset) purchases
- SB 23-207 · Died or failedSales and use tax refund for data center purchases
Sources
- 1HB26-1030 Data Center & Utility Modernization - Bill page
Colorado General AssemblyTier 1 · Open the source - 2House Bill 26-1030, introduced text (LLS No. 26-0134.03)
Colorado General AssemblyTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "HB 26-1030: Creates a data center authority and 20-year sales tax exemption." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/co-2026-hb-1030
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page