Project File
QTS Aurora-Denver data center campus (Denver 1)
Aurora,Arapahoe County,ColoradoUnder constructionFirst public 2021Last checked Nov 8, 2026
QTSDeveloper and operator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: First public date
- Still to confirm: Electric utility
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
QTS Aurora-Denver data center campus (Denver 1) is a under-construction data center project in Aurora, Arapahoe County, Colorado. QTS is named as operator. It was first public in 2021. It was announced at 160 MW.
QTS Aurora-Denver data center campus (Denver 1) is an under-construction data center project in Aurora, Arapahoe County, Colorado. QTS is named as operator. It was announced at 160 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Aurora, Arapahoe County, Colorado. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

The land, to scale
Timeline
- · New projectFirst public record of QTS Aurora-Denver data center campus (Denver 1)Under construction
Bills and laws in Colorado
- SB 26-102 · Died or failed · May 11, 2026Sets renewable power and grid cost rules for large data centers
- HB 26-1030 · Died or failed · May 7, 2026Creates a data center authority and 20-year sales tax exemption
- SB 25-280 · Died or failed · May 8, 2025Creates tax exemptions and grid planning for certified data centers
- SB 24-085 · Died or failed · Apr 30, 2024Sales and use tax rebate for data center (digital asset) purchases
- SB 23-207 · Died or failed · Apr 11, 2023Sales and use tax refund for data center purchases
Who's involved
- Developer and operatorQTS
Power
Capacity, as announced or filed
- 160 MW · it_load
Public records
0 records found so far. 9 kinds of record are still being collected.
Questions people ask
- Where is QTS Aurora-Denver data center campus (Denver 1)?
- QTS Aurora-Denver data center campus (Denver 1) is a data center project in Aurora, Arapahoe County, Colorado.
- Who operates QTS Aurora-Denver data center campus (Denver 1)?
- QTS is named as the operator of QTS Aurora-Denver data center campus (Denver 1).
- How big is QTS Aurora-Denver data center campus (Denver 1)?
- QTS Aurora-Denver data center campus (Denver 1) was announced at 160 MW of capacity. The site covers 65 acres.
- What stage is QTS Aurora-Denver data center campus (Denver 1)?
- QTS Aurora-Denver data center campus (Denver 1) is under construction. It was first public in 2021.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Data Center Campus Denver 1 (Aurora-Denver)
QTS Data CentersTier 4 · Captured 2026-11-08 · Open the source - 2Colorado data center locations (Denver and Colorado Springs)
QTS Data CentersTier 4 · Captured 2026-11-08 · Open the source - 3U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page