Project File
CoreSite Denver data centers (DE1, DE2)
Denver,Denver County,ColoradoOperatingFirst public 2012Filing entity: CoreSiteLast checked Nov 8, 2026
CoreSiteOperator
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
CoreSite Denver data centers (DE1, DE2) is an operating data center project in Denver, Denver County, Colorado. CoreSite is named as operator. It was first public in 2012. No site capacity figure is published for this project.
CoreSite Denver data centers (DE1, DE2) is an operating data center project in Denver, Denver County, Colorado. CoreSite is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Denver, Denver County, Colorado. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Timeline
- · New projectFirst public record of CoreSite Denver data centers (DE1, DE2)Operating
Bills and laws in Colorado
- SB 26-102 · Died or failed · May 11, 2026Sets renewable power and grid cost rules for large data centers
- HB 26-1030 · Died or failed · May 7, 2026Creates a data center authority and 20-year sales tax exemption
- SB 25-280 · Died or failed · May 8, 2025Creates tax exemptions and grid planning for certified data centers
- SB 24-085 · Died or failed · Apr 30, 2024Sales and use tax rebate for data center (digital asset) purchases
- SB 23-207 · Died or failed · Apr 11, 2023Sales and use tax refund for data center purchases
Who's involved
- OperatorCoreSite
Public records
3 records found so far. 8 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Pending before the commission · Apr 2, 2026Public Service Company of Colorado (Xcel Energy), Large Load Tariff: proposed Schedule TL (Large Load Service) and optional Schedule CTT (Contract Tariff Template)
- Utility commission · Decided · Nov 6, 2025Public Service Company of Colorado 2024 Just Transition Solicitation (Electric Resource Plan), Phase 1
- Utility commission · Decided · May 15, 2024Public Service Company of Colorado application for approval of a non-standard economic development rate (EDR) contract with QTS Aurora Infrastructure, LLC, and for a determination on a certificate of public convenience and necessity (CPCN) for customer-funded transmission facilities
Questions people ask
- Where is CoreSite Denver data centers (DE1, DE2)?
- CoreSite Denver data centers (DE1, DE2) is a data center project in Denver, Denver County, Colorado.
- Who operates CoreSite Denver data centers (DE1, DE2)?
- CoreSite is named as the operator of CoreSite Denver data centers (DE1, DE2).
- What stage is CoreSite Denver data centers (DE1, DE2)?
- CoreSite Denver data centers (DE1, DE2) is operating. It was first public in 2012.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Electric Rate Cases (Xcel Large Load Tariff, Proceeding No. 26AL-0137E)
Colorado Public Utilities CommissionTier 1 · Captured 2026-11-08 · Open the source - 2Decision No. C24-0378, Proceeding No. 23A-0330E (QTS non-standard EDR contract)
Colorado Public Utilities CommissionTier 1 · Captured 2026-11-10 · Open the source - 32025 JTS Written Order summary, Proceeding No. 24A-0442E
Colorado Public Utilities CommissionTier 1 · Captured 2026-11-10 · Open the source - 4
- 5U.S. Census Geocoder (batch geographies endpoint)
U.S. Census BureauTier 1 · Captured 2026-11-11 · Open the source - 6EIA Form 861, Service Territory file, 2025 (final)
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-11 · Open the source · Archived copy
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page