Utility commission
Public Service Company of Colorado 2024 Just Transition Solicitation (Electric Resource Plan), Phase 1
Where it stands: Decided as of Nov 6, 2025
Draft research, not yet verified. Open a source to check any detail.
What it is
Public Service's 2024 Just Transition Solicitation is its Electric Resource Plan for resource acquisitions from 2029 to 2033, including replacement of Pueblo Unit 3, which retires by January 1, 2031. The Phase I Decision (Decision No. C25-0747, issued November 6, 2025) approved the solicitation with modifications, on a plan that could result in acquisition of over 6,000 MW of new generation, and established a more flexible acquisition process to respond to new loads in a timely way while protecting existing ratepayers if large customer loads do not materialize but generation has been built to serve them. Phase II, covering portfolio selection and contracting, continues in the same proceeding. All figures are plan-level resource and load figures for the utility system, never the capacity of any single project.
The facts
- Regulator
- Colorado Public Utilities Commission
- Docket number
- 24A-0442E
- Type
- Other
- Utility
- Public Service Co of Colorado
- State
- Colorado
- Filed
- Oct 15, 2024
- Status date
- Nov 6, 2025
- Large-load rules
- Yes
Projects served by Public Service Co of Colorado
Related cases and proceedings
- Utility commission · Pending before the commissionPublic Service Company of Colorado (Xcel Energy), Large Load Tariff: proposed Schedule TL (Large Load Service) and optional Schedule CTT (Contract Tariff Template)
- Utility commission · DecidedPublic Service Company of Colorado application for approval of a non-standard economic development rate (EDR) contract with QTS Aurora Infrastructure, LLC, and for a determination on a certificate of public convenience and necessity (CPCN) for customer-funded transmission facilities
In the record
- Utility case, Oct 15, 2024. Utility case filed: Public Service Company of Colorado 2024 Just Transition Solicitation (Electric Resource Plan), Phase 1 Colorado Public Utilities Commission, 24A-0442E
Sources
- 12025 JTS Written Order summary, Proceeding No. 24A-0442E
Colorado Public Utilities CommissionTier 1 · Commission's 2025 JTS Written Order summary (Proceeding No. 24A-0442E; Written Decision issued Nov. 6, 2025) and the Commission's press release on completion of Phase 1 deliberations · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Public Service Company of Colorado 2024 Just Transition Solicitation (Electric Resource Plan), Phase 1." Last activity 2025-11-06. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-psco-24a-0442e-jts