What it is

Xcel Energy (Public Service Company of Colorado) filed its Large Load Tariff on April 2, 2026 for customers requiring 50 MW or more of peak demand; customers between 20 and 50 MW may also be subject to the terms. Proposed Schedule TL requires the customer to pay all transmission, substation, interconnection, and generation costs its load causes, sign a contract of 15 years or more, make minimum monthly payments, and pay early-termination charges. An optional Schedule CTT, modeled on NV Energy's, would let a customer self-generate at least 20 percent of its annual energy while the utility provides shaping, balancing, and backup. Hearings ran October 21 to 28, 2026 and the Commission's decision was still to be determined when the Commission's case page was read on November 8, 2026.

The facts

Regulator
Colorado Public Utilities Commission
Docket number
26AL-0137E
Type
Large load tariff
Utility
Public Service Co of Colorado
State
Colorado
Filed
Apr 2, 2026
Status date
Apr 2, 2026
Large-load rules
Yes, for loads of 50 MW or more

Projects served by Public Service Co of Colorado

Related cases and proceedings

In the record

  1. Utility case, Apr 2, 2026. Utility case filed: Public Service Company of Colorado (Xcel Energy), Large Load Tariff: proposed Schedule TL (Large Load Service) and optional Schedule CTT (Contract Tariff Template) Colorado Public Utilities Commission, 26AL-0137E

Sources

  1. 1
    Electric Rate Cases (Xcel Large Load Tariff, Proceeding No. 26AL-0137E)
    Colorado Public Utilities Commission
    Tier 1 · Commission Electric Rate Cases page, entry for Proceeding No. 26AL-0137E, as read firsthand by the Q5 WG3 sweep on 2026-11-08 (the source row's notes carry the filing date, the 50 MW test, and the terms). The page returns HTTP 403 to this conversion pass's fetches (two attempts, 2026-11-09), so the row rests on the WG3 reading of the Commission's own page. · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Public Service Company of Colorado (Xcel Energy), Large Load Tariff: proposed Schedule TL (Large Load Service) and optional Schedule CTT (Contract Tariff Template)." Last activity 2026-04-02. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-psco-26al-0137e-large-load-tariff