Data center court cases and dockets in Colorado

A docket is a case's public file. These are the lawsuits and the utility commission proceedings (rate cases, large-load rules, agreements) that touch data centers, newest activity first. Each links to its source.

See this week's Docket Drop

3 dockets

Cases and proceedings

  1. Utility commissionPending before the commissionLarge loads

    Public Service Company of Colorado (Xcel Energy), Large Load Tariff: proposed Schedule TL (Large Load Service) and optional Schedule CTT (Contract Tariff Template)

    Colorado Public Utilities Commission · Docket 26AL-0137E · Public Service Co of Colorado · Colorado

  2. Utility commissionDecidedLarge loads

    Public Service Company of Colorado 2024 Just Transition Solicitation (Electric Resource Plan), Phase 1

    Colorado Public Utilities Commission · Docket 24A-0442E · Public Service Co of Colorado · Colorado

  3. Utility commissionDecidedLarge loads

    Public Service Company of Colorado application for approval of a non-standard economic development rate (EDR) contract with QTS Aurora Infrastructure, LLC, and for a determination on a certificate of public convenience and necessity (CPCN) for customer-funded transmission facilities

    Colorado Public Utilities Commission · Docket 23A-0330E · Public Service Co of Colorado · Colorado

Sources on this page

  1. 1
    Electric Rate Cases (Xcel Large Load Tariff, Proceeding No. 26AL-0137E)
    Colorado Public Utilities Commission
    Tier 1 · Draft research, not yet verified · Open the source
  2. 2
    2025 JTS Written Order summary, Proceeding No. 24A-0442E
    Colorado Public Utilities Commission
    Tier 1 · Draft research, not yet verified · Open the source
  3. 3
    Decision No. C24-0378, Proceeding No. 23A-0330E (QTS non-standard EDR contract)
    Colorado Public Utilities Commission
    Tier 1 · Draft research, not yet verified · Open the source