Skip to content

Project File

Applied Digital Toronto (proposed)

Toronto,Deuel County,South DakotaCancelledLast checked Nov 13, 2026

Applied DigitalDeveloperOtter Tail PowerElectric utility

Saved in this browser; see it under My feed. Email alerts are not available yet.

Details confirmed

Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.

5 of 6 details confirmed

  • Confirmed: County
  • Confirmed: City or address
  • Confirmed: Stage
  • Confirmed: Capacity
  • Confirmed: Electric utility
  • Still to confirm: First public date
Know the record? Send it to us

What happens next: No upcoming date is on record.

Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.

Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.

Applied Digital Toronto (proposed) is a cancelled data center project in Toronto, Deuel County, South Dakota. Applied Digital is named as developer. It was announced at 430 MW.

Applied Digital Toronto (proposed) is a cancelled data center project in Toronto, Deuel County, South Dakota. Applied Digital is named as developer. It was announced at 430 MW. 5 of the six core facts we track for every project are confirmed on this page.

Where this project sits

This project sits in Toronto, Deuel County, South Dakota. Each place page carries the projects tracked there, who provides its power and water, and its local rules.

430 MWAnnounced capacity
1Public records we have found

For homeowners

What this project means if you live nearby

We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

County outline onlyExact site not confirmed yet. The outline shows Deuel County, South Dakota.See every project on the map

Laws and bills that may apply here

Found by each bill's own place and size rules. Each one says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026South Dakota HB 1038: PUC may bill data centers for contract review costs

    The act covers customers of a public utility that are data centers with a peak demand of ten megawatts or greater, when the commission processes a request for approval of a contract with deviations or another electric service agreement; this project has 430 MW announced on record, but the project's peak demand and whether it has requested approval of a contract with deviations or another electric service agreement is not on record.

    “The commission may assess a customer of a public utility the actual costs associated with processing a request for approval of a contract with deviations, or other electric service agreement with a public utility, related to the provision of electric service to a customer that is a data center with a peak demand of ten megawatts or greater.” (Section 1, new section in chapter 49-34A, ch. 185)

    Rule checks: Project is in South Dakota; 430 MW on record (announced), threshold 10 MW (Section 1, new section in chapter 49-34A, ch. 185). Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026South Dakota SB 135: Data center bill of rights: power costs, water, local control

    The act requires electricity providers to set separate service terms for a data center, defined by a peak demand of ten megawatts or greater, requiring reimbursement of all costs fairly attributed to the data center; this project has 430 MW announced on record, but the project's peak demand is not on record, since its on-record figure is announced capacity rather than peak demand.

    “A provider of electricity shall establish and maintain separate terms and conditions for electric service applicable to a data center. The terms and conditions must require that the data center reimburse any provider of electricity for all costs fairly attributed to the data center for service demand and utility consumption, including costs incurred to serve the data center if the data center departs the system or materially reduces its load.” (Section 3, ch. 190)

    Rule checks: Project is in South Dakota; 430 MW on record (announced), threshold 10 MW (Section 2, ch. 190). Still to check: dates: not checked, who it covers: not checked

Bills and laws in South Dakota

Open Bill Watch

Who's involved

Public records

1 records found so far. 8 kinds of record are still being collected.

See every record

Court cases and commission dockets

Questions people ask

Where is Applied Digital Toronto (proposed)?
Applied Digital Toronto (proposed) is a data center project in Toronto, Deuel County, South Dakota.
Who is developing Applied Digital Toronto (proposed)?
Applied Digital is named as the developer of Applied Digital Toronto (proposed).
How big is Applied Digital Toronto (proposed)?
Applied Digital Toronto (proposed) was announced at 430 MW of capacity.
What stage is Applied Digital Toronto (proposed)?
Applied Digital Toronto (proposed) is cancelled.

Sources

Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.

  1. 1
    Very large electric customers and the PUC process
    Minnesota Public Utilities Commission
    Tier 1 · Captured 2026-11-08 · Open the source
  2. 2
    North Dakota’s AI Data Center Boom Accelerates as South Dakota’s 430 MW Project Stalls
    Bitcoin Versus
    Tier 3 · Captured 2026-11-08 · Open the source

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page