Otter Tail Power Company petition for a very large customer class and a data center rate schedule

Where it stands: Pending before the commission

Draft research, not yet verified. Open a source to check any detail.

What it is

Petition for a new class for very large customers generally and a rate schedule for data center loads, under Minn. Stat. 216B.1622. A public comment period was expected when the Commission's summary was read. The petition's own terms were not opened in this pass.

The facts

Regulator
Minnesota Public Utilities Commission
Docket number
26-211
Type
Large load tariff
Utility
Otter Tail Power Company
State
Minnesota
Large-load rules
Yes

Projects served by Otter Tail Power Company

Related cases and proceedings

Sources

  1. 1
    Very large electric customers and the PUC process
    Minnesota Public Utilities Commission
    Tier 1 · PUC very large customers page (Otter Tail Power filed a petition for a new class for very large customers generally and a rate schedule for data center loads; Docket 26-211) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Otter Tail Power Company petition for a very large customer class and a data center rate schedule." Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-otter-tail-vlc-2026