Minnesota Power first petitioned in February 2026 to retain its existing framework for serving large power customers. After the Commission's May 2026 decision in Xcel Energy's Docket 25-289, the company withdrew that filing, and the Commission directed it to file an updated proposed tariff by July 15, 2026. Trade coverage of the resubmitted petition describes a new Very Large Power (VLP) customer class and service tariff filed July 15, 2026. The updated petition is pending; its terms were not verified from the petition itself in this pass.
The facts
- Regulator
- Minnesota Public Utilities Commission
- Docket number
- 26-126
- Type
- Large load tariff
- Utility
- Minnesota Power
- State
- Minnesota
- Large-load rules
- Yes
Related cases and proceedings
- Utility commission · DecidedNorthern States Power Company (Xcel Energy) very large customer tariff under Minn. Stat. 216B.1622
- Utility commission · DecidedDakota Electric Association, modified Extension of Service Tariff for extraordinarily large and system-intensive members
- Utility commission · Pending before the commissionDakota Electric Association, proposed Very Large Member Contract Rate Service tariff
- Utility commission · Pending before the commissionOtter Tail Power Company petition for a very large customer class and a data center rate schedule
Sources
- 1Very large electric customers and the PUC process
Minnesota Public Utilities CommissionTier 1 · PUC very large customers page (Minnesota Power directed to file an updated proposed tariff by July 15, 2026; Docket 26-126); CUB Minnesota (February 2026 filing, opposition, withdrawal, expected resubmission) · Open the source - 2Data Centers to Pay Fair Share: PUC enacts protections for Xcel customers
Citizens Utility Board of MinnesotaTier 4 · PUC very large customers page (Minnesota Power directed to file an updated proposed tariff by July 15, 2026; Docket 26-126); CUB Minnesota (February 2026 filing, opposition, withdrawal, expected resubmission) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Minnesota Power petition for a very large customer tariff under Minn. Stat. 216B.1622." Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-minnesota-power-vlp-2026