Skip to content

South DakotaHouse of Representatives101st Legislative Session (2026)Bill

HB 1038: PUC may bill data centers for contract review costs

Official title: An Act to allow the Public Utilities Commission to assess actual costs to data centers that are customers of public utilities.

Official text

Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.

Where it stands

Signed into law as of Mar 24, 2026. The official record says: Signed into law.

  1. Filed (done)
  2. In committee (done)
  3. Passed one chamber (done)
  4. Passed both chambers (done)
  5. Signed into law (current stage)
  6. In effect (not reached)

What it does

  • Fee · threshold 10 MW

    Applies to: data center customers of public utilities (peak demand of 10 MW or more) (South Dakota)

    Starts: 2026-07-01.

    “The commission may assess a customer of a public utility the actual costs associated with processing a request for approval of a contract with deviations, or other electric service agreement with a public utility, related to the provision of electric service to a customer that is a data center with a peak demand of ten megawatts or greater.”

    Section 1, new section in chapter 49-34A, ch. 185

Who it touches (2)

Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Applied Digital Toronto (proposed)

    The act covers customers of a public utility that are data centers with a peak demand of ten megawatts or greater, when the commission processes a request for approval of a contract with deviations or another electric service agreement; this project has 430 MW announced on record, but the project's peak demand and whether it has requested approval of a contract with deviations or another electric service agreement is not on record.

    “The commission may assess a customer of a public utility the actual costs associated with processing a request for approval of a contract with deviations, or other electric service agreement with a public utility, related to the provision of electric service to a customer that is a data center with a peak demand of ten megawatts or greater.” (Section 1, new section in chapter 49-34A, ch. 185)

    Rule checks: Project is in South Dakota; 430 MW on record (announced), threshold 10 MW (Section 1, new section in chapter 49-34A, ch. 185). Still to check: dates: not checked, who it covers: not checked

  • Possible match, AI could not decide; waiting for a person · Nov 29, 2026Gemini Capital Sioux Falls Data Center (proposed)

    The act covers customers of a public utility that are data centers with a peak demand of ten megawatts or greater, when the commission processes a request for approval of a contract with deviations or another electric service agreement; this project has 500 MW announced on record, but the project's peak demand and whether it has requested approval of a contract with deviations or another electric service agreement is not on record.

    “The commission may assess a customer of a public utility the actual costs associated with processing a request for approval of a contract with deviations, or other electric service agreement with a public utility, related to the provision of electric service to a customer that is a data center with a peak demand of ten megawatts or greater.” (Section 1, new section in chapter 49-34A, ch. 185)

    Rule checks: Project is in South Dakota; 500 MW on record (announced), threshold 10 MW (Section 1, new section in chapter 49-34A, ch. 185). Still to check: dates: not checked, who it covers: not checked

Who acted

  • RequesterPublic Utilities Commission of the State of South Dakota
  • SponsorThe Chair of the Committee on Commerce and EnergyHouse

Timeline

Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.

  1. Signed by Governor Larry Rhoden (2026 Session Laws, ch. 185)Stage: Signed into law

More from South Dakota

Sources

  1. 1
    Chapter 185 (House Bill 1038), 2026 Session Laws
    South Dakota Legislature (Legislative Research Council)
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "HB 1038: PUC may bill data centers for contract review costs." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/sd-101-hb-1038

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page