South DakotaSenate101st Legislative Session (2026)Bill
SB 135: Data center bill of rights: power costs, water, local control
Official title: An Act to protect residents from increased utility costs and utility shortages caused by data centers and clarify authority to regulate data centers.
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
Signed into law as of Mar 24, 2026. The official record says: Signed into law.
- Filed (done)
- In committee (done)
- Passed one chamber (done)
- Passed both chambers (done)
- Signed into law (current stage)
- In effect (not reached)
What it does
Who pays for grid costs · threshold 10 MW
Applies to: data centers with peak demand of 10 MW or more (South Dakota)
Starts: 2026-07-01.
“A provider of electricity shall establish and maintain separate terms and conditions for electric service applicable to a data center. The terms and conditions must require that the data center reimburse any provider of electricity for all costs fairly attributed to the data center for service demand and utility consumption, including costs incurred to serve the data center if the data center departs the system or materially reduces its load.”
Section 3, ch. 190
Definition · threshold 10 MW
Applies to: data centers (South Dakota)
Starts: 2026-07-01.
“For purposes of this chapter, "data center" means a centralized repository for the dissemination, management, processing, and storage of electronic data and information, with a peak demand of ten megawatts or greater.”
Section 2, ch. 190
Preemption
Applies to: state preemption of local data center ordinances (South Dakota)
Starts: 2026-07-01.
“The state may not preempt or otherwise limit the authority of the governing body of a county, municipality, or other political subdivision to adopt ordinances and resolutions limiting, prohibiting, or otherwise regulating the construction, development, or operation of data centers.”
Section 4, ch. 190
Reporting duty
Applies to: data center operators (South Dakota)
Starts: 2026-07-01.
“The operator of a data center that is authorized to operate in this state pursuant to this chapter, shall, at the time and in the manner prescribed by the Board of Water Management, submit to the board a semi-annual report regarding the data center's water use.”
Section 6, ch. 190
Who it touches (2)
Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Applied Digital Toronto (proposed)
The act requires electricity providers to set separate service terms for a data center, defined by a peak demand of ten megawatts or greater, requiring reimbursement of all costs fairly attributed to the data center; this project has 430 MW announced on record, but the project's peak demand is not on record, since its on-record figure is announced capacity rather than peak demand.
“A provider of electricity shall establish and maintain separate terms and conditions for electric service applicable to a data center. The terms and conditions must require that the data center reimburse any provider of electricity for all costs fairly attributed to the data center for service demand and utility consumption, including costs incurred to serve the data center if the data center departs the system or materially reduces its load.” (Section 3, ch. 190)
Rule checks: Project is in South Dakota; 430 MW on record (announced), threshold 10 MW (Section 2, ch. 190). Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Gemini Capital Sioux Falls Data Center (proposed)
The act requires electricity providers to set separate service terms for a data center, defined by a peak demand of ten megawatts or greater, requiring reimbursement of all costs fairly attributed to the data center; this project has 500 MW announced on record, but the project's peak demand is not on record, since its on-record figure is announced capacity rather than peak demand.
“A provider of electricity shall establish and maintain separate terms and conditions for electric service applicable to a data center. The terms and conditions must require that the data center reimburse any provider of electricity for all costs fairly attributed to the data center for service demand and utility consumption, including costs incurred to serve the data center if the data center departs the system or materially reduces its load.” (Section 3, ch. 190)
Rule checks: Project is in South Dakota; 500 MW on record (announced), threshold 10 MW (Section 2, ch. 190). Still to check: dates: not checked, who it covers: not checked
Who acted
- Primary sponsorKarrSenate
Timeline
Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.
- Signed by Governor Larry Rhoden (2026 Session Laws, ch. 190)Stage: Signed into law
More from South Dakota
- HB 1005 · Died or failedFifty year sales tax exemption for data center equipment
- HB 1038 · Signed into lawPUC may bill data centers for contract review costs
- SB 239 · Died or failedSales tax relief for large projects including data centers
- HB 1301 · Died or failedMoratorium and cost limits for large data centers
- SB 232 · Died or failedOne year moratorium on hyperscale data centers
Sources
- 1Chapter 190 (Senate Bill 135), 2026 Session Laws
South Dakota Legislature (Legislative Research Council)Tier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "SB 135: Data center bill of rights: power costs, water, local control." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/sd-101-sb-135
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page