Data centers in Charlotte, North Carolina
Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.
Data Center Fact Check tracks 6 data center projects in Charlotte, North Carolina as of November 2026: 3 operating, 2 announced and 1 approved, totaling about 718 MW announced where a figure is published.
Charlotte has 6 tracked data centers. Their announced capacity totals about 718 MW where a figure is published. Of those, 3 operating, 2 announced and 1 approved. Every project we track here is listed below, with the public records behind it. Every figure comes from the public record linked on this page.
Data center projects in Charlotte
- Digital Realty 725 East Trade Street Expansion
AnnouncedCharlotte12 MW announced
- Digital Realty Charlotte Campus (Moores Chapel Road)
ApprovedCharlotte400 MW announced
- Digital Realty CLT10 (Uptown Charlotte)
OperatingCharlotte
- Flexential Charlotte - North Data Center
OperatingCharlotte3 MW announced
- Flexential Charlotte - South Data Center
OperatingCharlotte2 MW announced
- PowerHouse Charlotte
AnnouncedCharlotte300 MW announced
Who serves this place
- Not collected yet.
Local rules for data centers
Expired · Moratorium · Adopted Jun 8, 2026
150-day moratorium on new data center applications
Charlotte adopted a 150-day moratorium on new data center development applications while it studied infrastructure capacity noise and environmental impacts and drafted development rules; the city UDO covers the use as a telecommunications and data storage facility. Staff later proposed extending the pause.
Court cases and commission dockets in North Carolina (2)
Bills and laws in North Carolina
- SB 257 · In effect · Jul 7, 2026Ends the sales tax exemption for electricity used in datacenters
- HB 1213 · In committee · Jun 30, 2026Repeals the sales and use tax exemption for data centers
- SB 730 · Passed one chamber · Jun 8, 2026Sets siting, water, and power contract rules for large data centers
- HB 1189 · In committee · May 5, 2026Pauses data center permits two years and studies their impacts
- HB 1180 · In committee · May 4, 2026Requires approved utility tariffs for large load data center service
- HB 1063 · In committee · Apr 28, 2026Regulates large data centers and repeals their sales tax exemptions
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Questions people ask
- How many data centers are in Charlotte?
- Data Center Fact Check tracks 6 data center projects in Charlotte as of November 2026. Of those, 3 operating, 2 announced and 1 approved.
- What is the biggest data center in Charlotte?
- By announced capacity, the biggest data center in Charlotte is Digital Realty Charlotte Campus (Moores Chapel Road), announced at 400 MW. It is approved.
- How much power do data centers in Charlotte use?
- The 6 projects tracked in Charlotte have announced about 718 MW of capacity in total, where a figure is published. That is announced capacity, not measured electricity use.
Sources
- 1Data Centers Update: City Council business meeting October 12 2026
City of CharlotteTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.