PowerHouse Charlotte
Charlotte,Mecklenburg County,North CarolinaAnnouncedLast checked Nov 8, 2026
PowerHouse Data CentersDeveloperDuke EnergyElectric utility
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Capacity
- Confirmed: Electric utility
- Still to confirm: First public date
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
PowerHouse Charlotte is an announced data center project in Charlotte, Mecklenburg County, North Carolina. PowerHouse Data Centers is named as developer. It was announced at 300 MW.
PowerHouse Charlotte is an announced data center project in Charlotte, Mecklenburg County, North Carolina. PowerHouse Data Centers is named as developer. It was announced at 300 MW. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Charlotte, Mecklenburg County, North Carolina. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
We have not written the homeowner summary for this project yet. Every record we have is on the Records tab.
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
The land, to scale
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026North Carolina SB 257: Ends the sales tax exemption for electricity used in datacenters
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a announced data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026North Carolina SB 730: Sets siting, water, and power contract rules for large data centers
The act covers data centers with a peak monthly electricity demand of 100 megawatts or greater, including new data centers that must submit a site assessment before local approval; this project has 500 MW on record (grid connection), but the project's peak monthly electricity demand and whether it is a new data center seeking local approval is not on record.
“For purposes of this section, the term "data center" means a facility, campus of facilities, or array of interconnected facilities used by an entity or other business enterprise for the primary purpose of storing, retrieving, managing, and processing digital data, which has a peak monthly electricity demand of 100 megawatts or greater.” (SECTION 1.(a), G.S. 160D-974(d))
Rule checks: Project is in North Carolina; 500 MW on record (grid connection), threshold 100 MW (SECTION 1.(a), G.S. 160D-974(d)). Still to check: who it covers: not checked
Bills and laws in North Carolina
- SB 257 · In effect · Jul 7, 2026Ends the sales tax exemption for electricity used in datacenters
- HB 1213 · In committee · Jun 30, 2026Repeals the sales and use tax exemption for data centers
- SB 730 · Passed one chamber · Jun 8, 2026Sets siting, water, and power contract rules for large data centers
- HB 1189 · In committee · May 5, 2026Pauses data center permits two years and studies their impacts
- HB 1180 · In committee · May 4, 2026Requires approved utility tariffs for large load data center service
- HB 1063 · In committee · Apr 28, 2026Regulates large data centers and repeals their sales tax exemptions
Who's involved
- DeveloperPowerHouse Data Centers
- Electric utilityDuke Energy
Power
Capacity, as announced or filed
- 300 MW · Full campus (secured power)grid connection
- 500 MW · Full campus (potential increase)grid connection
Public records
3 records found so far. 7 kinds of record are still being collected.
See every recordCourt cases and commission dockets
- Utility commission · Pending before the commission · Oct 6, 2026Application of Duke Energy Carolinas, LLC for Adjustment of Rates and Charges Applicable to Electric Service in North Carolina and Performance-Based Regulation (Large Load Tariff settlement)
- Utility commission · Decided · Dec 31, 2025Duke Energy Carolinas, LLC general rate case (Large Load Stipulation)
Questions people ask
- Where is PowerHouse Charlotte?
- PowerHouse Charlotte is a data center project in Charlotte, Mecklenburg County, North Carolina.
- Who is developing PowerHouse Charlotte?
- PowerHouse Data Centers is named as the developer of PowerHouse Charlotte.
- How big is PowerHouse Charlotte?
- PowerHouse Charlotte was announced at 300 MW of capacity. The site covers 122 acres.
- What stage is PowerHouse Charlotte?
- PowerHouse Charlotte is announced.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Data Centers Update: City Council business meeting October 12 2026
City of CharlotteTier 1 · Captured 2026-11-08 · Open the source - 2Filing in Docket No. 2025-172-E citing Order No. 2025-769 (December 31, 2025)
Public Service Commission of South CarolinaTier 1 · Captured 2026-11-08 · Open the source - 3Agreement and Stipulation of Settlement on Large Load Tariff, Dockets E-7 Sub 1329 and E-2 Sub 1380 (filed October 6, 2026)
Duke Energy Carolinas, LLC and Duke Energy Progress, LLC (filing parties)Tier 2 · Captured 2026-11-08 · Open the source - 4Town Lane and PowerHouse Data Centers JV acquires future data center land site in Charlotte, NC
PowerHouse Data Centers and Town LaneTier 4 · Captured 2026-11-08 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page