Duke Energy Carolinas, LLC general rate case (Large Load Stipulation)

Where it stands: Decided as of Dec 31, 2025

Draft research, not yet verified. Open a source to check any detail.

What it is

The Large Load Stipulation approved December 31, 2025 committed Duke Energy Carolinas, together with Duke Energy Progress, to request a generic large load docket by June 1, 2026 (Docket No. 2026-138-E). The large load discussion in Order No. 2025-769 runs at pages 125 to 129. The stipulation’s other substantive terms were not extracted in this sweep.

The facts

Regulator
Public Service Commission of South Carolina
Docket number
2025-172-E
Type
Rate case
Utility
Duke Energy Carolinas, LLC
State
South Carolina
Filed
Jan 1, 2025
Status date
Dec 31, 2025
Large-load rules
Yes, for loads of 50 MW or more

Projects served by Duke Energy Carolinas, LLC

Related cases and proceedings

In the record

  1. Utility case, 2025. Utility case filed: Duke Energy Carolinas, LLC general rate case (Large Load Stipulation) Public Service Commission of South Carolina, 2025-172-E

Sources

  1. 1
    Filing in Docket No. 2025-172-E citing Order No. 2025-769 (December 31, 2025)
    Public Service Commission of South Carolina
    Tier 1 · Order No. 2025-769 (December 31, 2025) as cited at p. 28 of the Docket No. 2025-172-E filing; large load discussion at order pp. 125-129 per a later filing · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Duke Energy Carolinas, LLC general rate case (Large Load Stipulation)." Last activity 2025-12-31. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-duke-carolinas-sc-rate-case-2025