Utility commission
Dominion Energy South Carolina, Inc. general rate case (Agreement and Stipulation of Settlement Regarding Large Load Issues)
Where it stands: Decided as of Jun 11, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Under the Large Load Stipulation filed May 8, 2026 and approved June 11, 2026, Dominion Energy South Carolina joined the generic large load docket (No. 2026-138-E) for new large load additions of 50 MW or greater; the stipulation’s other substantive terms were not fully extracted. Separately in this case, the May 2026 revenue requirement stipulation deferred recovery of amounts associated with the Mallard data center (Ridgeville) and Scout Motors rather than recovering them in this case; regulatory staff testimony put Mallard-related plant at $45,396,078.26 and noted the company’s position that Mallard interconnection and network upgrade costs are not in current rates. Company testimony in its 2026 IRP docket describes current practice for large loads: contracts of ten years or more with minimum contract demand payments covering transmission facilities above standard rates, and termination fees recovering unrecovered transmission costs.
The facts
- Regulator
- Public Service Commission of South Carolina
- Docket number
- 2025-325-E
- Type
- Rate case
- Utility
- Dominion Energy South Carolina, Inc
- State
- South Carolina
- Filed
- Jan 2, 2026
- Status date
- Jun 11, 2026
- Large-load rules
- Yes, for loads of 50 MW or more
Related cases and proceedings
- Utility commission · DecidedSchedule L-27-HIL, Large Light and Power High Impact Load
- Utility commission · DecidedDuke Energy Carolinas, LLC general rate case (Large Load Stipulation)
- Utility commission · DecidedDuke Energy Progress, LLC general rate case (Large Load Stipulation)
- Utility commission · In effectSchedule L-25-LL, Large Light and Power, Experimental Large Load Service
In the record
- Utility case, Jan 2, 2026. Utility case filed: Dominion Energy South Carolina, Inc. general rate case (Agreement and Stipulation of Settlement Regarding Large Load Issues) Public Service Commission of South Carolina, 2025-325-E
Sources
- 1Agreement and Stipulation of Settlement Regarding Large Load Issues, Docket No. 2025-325-E (filed May 8, 2026)
Public Service Commission of South CarolinaTier 1 · Large Load Stipulation (filed May 8, 2026); Company Petition to Intervene in Docket No. 2026-138-E, paras. 6-8 (stipulation filed May 8, 2026; approved by written directive June 11, 2026); joint proposed order paras. 37-39 (generic docket purpose, 50 MW or greater) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Dominion Energy South Carolina, Inc. general rate case (Agreement and Stipulation of Settlement Regarding Large Load Issues)." Last activity 2026-06-11. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-dominion-sc-rate-case-2026