Schedule L-25-LL, Large Light and Power, Experimental Large Load Service

Where it stands: In effect as of Apr 25, 2025

Draft research, not yet verified. Open a source to check any detail.

What it is

Mandatory for Schedule L customers operating a Large Load: a data facility with aggregate monthly maximum demand over 50,000 kW, a mobile large load (including cryptocurrency mining) over 1,000 kW, or another facility over 50,000 kW with a high load factor not meeting economic development criteria. Contract demand may be adjusted during the first 36 months for buildup; no reduction is effective before 15 years of service, then staged reductions of 20 to 100 percent over successive 12 month periods. Minimum firm billing demand factor: 100 percent in months 1 to 60, 95 percent in months 61 to 120, 90 percent after; minimum coincident peak billing factor 50, 65, then 80 percent. The initial service agreement term is not less than 180 months; before execution and construction the customer pays all delivery point and transmission expenses in full and provides collateral equal to the value of the initial 180 months of minimum bills, at least 12 months of minimum bills in cash. Experimental: the schedule ends no later than April 24, 2029, and class size is capped at 12 percent of the large industrial class (customers of 100 MW or more excluded from the cap).

The facts

Regulator
Board of the South Carolina Public Service Authority
Type
Large load tariff
Utility
South Carolina Public Service Authority
State
South Carolina
Filed
Apr 25, 2025
Status date
Apr 25, 2025
Large-load rules
Yes, for loads of 50 MW or more

Related cases and proceedings

In the record

  1. Utility case, Apr 25, 2025. Utility case filed: Schedule L-25-LL, Large Light and Power, Experimental Large Load Service Board of the South Carolina Public Service Authority

Sources

  1. 1
    Schedule L-25-LL, Large Light and Power, Experimental Large Load Service (adopted April 25, 2025)
    South Carolina Public Service Authority
    Tier 1 · Schedule L-25-LL: Section 1(A) (mandatory service, three categories), Section 3 (charges), Section 4(C) (buildup and reductions), Section 4(H)(2)-(3) (billing factors), Section 6(B) (180 month term, upfront expenses, collateral), Section 7(D) (experimental end date and class cap); tariff footer (adopted April 25, 2025; effective for bills on and after April 25, 2025) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Schedule L-25-LL, Large Light and Power, Experimental Large Load Service." Last activity 2025-04-25. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-santee-cooper-l-25-ll-2025