What it is
The Large Load Stipulation filed October 27, 2025 and approved December 12, 2025 committed Duke Energy Progress to request a generic large load docket by June 1, 2026 (which became Docket No. 2026-138-E). Company testimony in the case (Section III, Large Load Tariffs and Contract Terms) addresses proposed service regulation requirements for customers with contract demand greater than 50 MW. The stipulation’s other substantive terms were not extracted in this sweep.
The facts
- Regulator
- Public Service Commission of South Carolina
- Docket number
- 2025-154-E
- Type
- Rate case
- Utility
- Duke Energy Progress, LLC
- State
- South Carolina
- Filed
- Jun 12, 2025
- Status date
- Dec 12, 2025
- Large-load rules
- Yes, for loads of 50 MW or more
Projects served by Duke Energy Progress, LLC
Related cases and proceedings
- Utility commission · DecidedSchedule L-27-HIL, Large Light and Power High Impact Load
- Utility commission · Pending before the commissionApplication of Duke Energy Progress, LLC for Adjustment of Rates and Charges Applicable to Electric Service in North Carolina and Performance-Based Regulation (Large Load Tariff settlement)
- Utility commission · DecidedDominion Energy South Carolina, Inc. general rate case (Agreement and Stipulation of Settlement Regarding Large Load Issues)
- Utility commission · DecidedDuke Energy Carolinas, LLC general rate case (Large Load Stipulation)
- Utility commission · In effectSchedule L-25-LL, Large Light and Power, Experimental Large Load Service
In the record
- Utility case, Jun 12, 2025. Utility case filed: Duke Energy Progress, LLC general rate case (Large Load Stipulation) Public Service Commission of South Carolina, 2025-154-E
Sources
- 1Filing in Docket No. 2026-78-E citing Order No. 2025-757 (December 12, 2025), Docket No. 2025-154-E
Public Service Commission of South CarolinaTier 1 · Order No. 2025-757 (December 12, 2025) as cited at pp. 11 and 39 of the Docket No. 2026-78-E filing; Wilson direct testimony, September 16, 2025, Section III (contract demand greater than 50 MW) · Open the source
Report an error or send a tip on this page
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "Duke Energy Progress, LLC general rate case (Large Load Stipulation)." Last activity 2025-12-12. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-duke-progress-sc-rate-case-2025