Utility commission
Schedule L-27-HIL, Large Light and Power High Impact Load
Where it stands: Decided as of Oct 30, 2026
Draft research, not yet verified. Open a source to check any detail.
What it is
Permanent successor to the experimental L-25-LL. Required for computational loads with aggregate monthly maximum demand over 20 MW, mobile computational loads (including cryptocurrency mining) over 1 MW, and other loads over 20 MW with high load factors not meeting economic development criteria. Contract term not less than 15 years; base demand charge $23.23 per kW plus a coincident peak charge of $6.16 per kW adjusted per customer to the actual incremental cost of service; minimum billing 90 percent for both non coincident peak and coincident peak for the contract term; service agreements include financial guarantees so high impact customers pay the incremental cost of serving them.
The facts
- Regulator
- Board of the South Carolina Public Service Authority
- Type
- Large load tariff
- Utility
- South Carolina Public Service Authority
- State
- South Carolina
- Filed
- Oct 30, 2026
- Status date
- Oct 30, 2026
- Large-load rules
- Yes, for loads of 20 MW or more
Related cases and proceedings
- Utility commission · DecidedDominion Energy South Carolina, Inc. general rate case (Agreement and Stipulation of Settlement Regarding Large Load Issues)
- Utility commission · DecidedDuke Energy Carolinas, LLC general rate case (Large Load Stipulation)
- Utility commission · DecidedDuke Energy Progress, LLC general rate case (Large Load Stipulation)
- Utility commission · In effectSchedule L-25-LL, Large Light and Power, Experimental Large Load Service
In the record
- Utility case, Oct 30, 2026. Utility case filed: Schedule L-27-HIL, Large Light and Power High Impact Load Board of the South Carolina Public Service Authority
Sources
- 1Management Rate Recommendation Presentation to the Board (May 1, 2026): High Impact Load Schedule L-27-HIL comparison
South Carolina Public Service AuthorityTier 1 · Management Rate Recommendation Presentation, May 1, 2026, comparison table (thresholds, 15 year term, $23.23 and $6.16 charges, 90 percent minimum billing); newsroom release (Board approval October 30, 2026; permanent rate replaces the experimental rate; effective February 1, 2027) · Open the source - 2Santee Cooper Board approves new rates for 2027 and 2028 (newsroom release)
South Carolina Public Service AuthorityTier 4 · Management Rate Recommendation Presentation, May 1, 2026, comparison table (thresholds, 15 year term, $23.23 and $6.16 charges, 90 percent minimum billing); newsroom release (Board approval October 30, 2026; permanent rate replaces the experimental rate; effective February 1, 2027) · Open the source
Report an error or send a tip on this page