Application of Duke Energy Carolinas, LLC for Adjustment of Rates and Charges Applicable to Electric Service in North Carolina and Performance-Based Regulation (Large Load Tariff settlement)

Where it stands: Pending before the commission as of Oct 6, 2026

Draft research, not yet verified. Open a source to check any detail.

What it is

The October 6, 2026 settlement Exhibit 1 is a Large Load Tariff for agreements executed on or after June 1, 2026: a Large Load Customer has total contract demand of 50 MW or more with an expected 12 month rolling average load factor of 80 percent or more, or 150 MW or more at any load factor. Billing demand under Schedule HLF is not less than 75 percent of contract demand; dedicated facilities are funded by a customer CIAC advance, and transmission network upgrades are secured by a letter of credit that steps down after the customer sustains 75 percent of contract demand for three consecutive months. Minimum initial term: the greater of 10 years or 5 years plus the ramp period (under 100 MW), or the greater of 15 years or 10 years plus the ramp (100 MW or more); reduction and termination notice runs 24 to 48 months by size; early termination liquidated damages combine the notification period charges, the net present value of remaining extra facilities charges, and 25 percent of remaining minimum billing demand charges, secured by cash, letter of credit, or parent guarantee. Each agreement must include interruptibility (95 percent of contract load up to 50 hours per year, or 50 percent up to 100 hours) for the ramp plus one year. The tariff leaf is stated effective for service on and after January 1, 2027 if the Commission approves.

The facts

Regulator
North Carolina Utilities Commission
Docket number
E-7, Sub 1329
Type
Rate case
Utility
Duke Energy Carolinas, LLC
State
North Carolina
Filed
Nov 20, 2025
Status date
Oct 6, 2026
Large-load rules
Yes, for loads of 50 MW or more

Projects served by Duke Energy Carolinas, LLC

Related cases and proceedings

In the record

  1. Utility case, Nov 20, 2025. Utility case filed: Application of Duke Energy Carolinas, LLC for Adjustment of Rates and Charges Applicable to Electric Service in North Carolina and Performance-Based Regulation (Large Load Tariff settlement) North Carolina Utilities Commission, E-7, Sub 1329

Sources

  1. 1
    Agreement and Stipulation of Settlement on Large Load Tariff, Dockets E-7 Sub 1329 and E-2 Sub 1380 (filed October 6, 2026)
    Duke Energy Carolinas, LLC and Duke Energy Progress, LLC (filing parties)
    Tier 2 · Settlement Exhibit 1, Large Load Tariff, Duke Energy Carolinas NC Original Leaf, pp. 1-3 of the exhibit (definition, CIAC, letter of credit, term, Schedule HLF 75 percent floor, notice periods, liquidated damages, security, reliability provision); Settlement Section II.B.2 (E-100 Sub 208 report commitment) · Open the source

Report an error or send a tip on this page

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Application of Duke Energy Carolinas, LLC for Adjustment of Rates and Charges Applicable to Electric Service in North Carolina and Performance-Based Regulation (Large Load Tariff settlement)." Last activity 2026-10-06. Accessed 2026-11-29. https://datacenterfactcheck.org/dockets/utility/proc-duke-carolinas-nc-large-load-settlement-2026