North CarolinaSenate2025-2026 General AssemblyBill
SB 257: Ends the sales tax exemption for electricity used in datacenters
Official title: 2026 Appropriations Act
Draft research, not yet verified: traced to the official record by an AI research agent; an editor has not checked it yet.
Where it stands
In effect as of Jul 7, 2026. The official record says: Ch. SL 2026-41.
- Filed (done)
- In committee (done)
- Passed one chamber (done)
- Passed both chambers (done)
- Signed into law (done)
- In effect (current stage)
What it means for a household (draft rating)
Unclear for households. The appropriations act funds a State Bureau of Investigation data center and sets no tax, rate, or exemption rule for households.
We rate a bill as helping or costing households only when its own text says who pays or who is exempt. Otherwise it is unclear. This is a draft rating and has not been verified yet.
What it does
Effective date
Applies to: Section 44.4 datacenter electricity repeal (North Carolina)
Starts: 2026-07-07.
“This section became effective July 7, 2026, and applies to the first billing period that starts on or after that date and is at least 30 days after that date.”
Legislative Analysis Division summary S257-SMSV-138(sl)-v-3, on Section 44.4
Tax exemption
Applies to: electricity used in datacenters (North Carolina)
Starts: 2026-07-07.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.”
SECTION 44.4, as described in Fiscal Note SFN257v7
Reporting duty
Applies to: purchasers of electricity for use at a datacenter (North Carolina)
“Therefore, the provision requires purchasers of electricity for use at a datacenter to report within 30 days of the end of each quarter to the Secretary the amount of tax paid on electricity.”
Legislative Analysis Division summary S257-SMSV-138(sl)-v-3, on Section 44.4 as amended
Who it touches (21)
Projects this may apply to, from the bill's own place and size rules. Each says who has checked it so far.
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Apple Maiden Data Center
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026 for billing periods starting on or after that date, and this project is an operating data center in North Carolina on record, so every condition the text sets is met by a fact on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026CyrusOne DUR1 / DUR2 (Durham)
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026 for billing periods starting on or after that date, and this project is an operating data center in North Carolina on record, so every condition the text sets is met by a fact on record. Status part: the act's status (Session Law 2026-41, in effect July 7, 2026) makes the repeal operative. Text part: the decision rests on the repeal text quoted here, which reaches electricity used in datacenters.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Digital Realty CLT10 (Uptown Charlotte)
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026 for billing periods starting on or after that date, and this project is an operating data center in North Carolina on record, so every condition the text sets is met by a fact on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Flexential Charlotte - North Data Center
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026 for billing periods starting on or after that date, and this project is an operating data center in North Carolina on record, so every condition the text sets is met by a fact on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Flexential Charlotte - South Data Center
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026 for billing periods starting on or after that date, and this project is an operating data center in North Carolina on record, so every condition the text sets is met by a fact on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Flexential Raleigh Data Center (Morrisville)
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026 for billing periods starting on or after that date, and this project is an operating data center in North Carolina on record, so every condition the text sets is met by a fact on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Google Lenoir Data Center
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026 for billing periods starting on or after that date, and this project is an operating data center in North Carolina on record, so every condition the text sets is met by a fact on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Checked by AI against the bill text, not yet by a person · Nov 29, 2026Meta Forest City Data Center
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026 for billing periods starting on or after that date, and this project is an operating data center in North Carolina on record, so every condition the text sets is met by a fact on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Amazon Richmond County AI Campus
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a announced data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026CyrusOne Lee County
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a proposed data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record. Status part: the act's status (Session Law 2026-41, in effect July 7, 2026) makes the repeal operative. Text part: the decision rests on the repeal text quoted here.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty 725 East Trade Street Expansion
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a announced data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Digital Realty Charlotte Campus (Moores Chapel Road)
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a approved data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Energy Storage Solutions Kingsboro Megasite Data Center
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a cancelled data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Energy Storage Solutions Tarboro Data Center
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a cancelled data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Flexential Salisbury Data Center
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a approved data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026ImpactData Dream Center
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a announced data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft Conover Data Center
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a under_construction data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft Hickory Data Center (Hickory Lincolnton Highway)
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a under_construction data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft Hickory Data Center (Tate Boulevard)
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a announced data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Microsoft Maiden Data Center
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a under_construction data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026PowerHouse Charlotte
Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters, effective July 7, 2026; this project is a announced data center in North Carolina on record, but whether it purchases electricity for use at a datacenter is not on record.
“Section 44.4 repeals the sales and use tax exemption for electricity used in datacenters with all net proceeds intended to be retained by the State.” (SECTION 44.4, as described in Fiscal Note SFN257v7)
Rule checks: Project is in North Carolina. Still to check: dates: not checked, who it covers: not checked
Who acted
- Primary sponsorSen. Brent JacksonSenate
- Primary sponsorSen. Michael V. LeeSenate
- Primary sponsorSen. Ralph HiseSenate
Timeline
Every official action on record, oldest first. An action that moved the bill to a new stage names that stage.
- Conference report adopted (House 88-21, Senate 35-10)Stage: Passed both chambers
- Ch. SL 2026-41Stage: Signed into law
More from North Carolina
- HB 1213 · In committeeRepeals the sales and use tax exemption for data centers
- SB 730 · Passed one chamberSets siting, water, and power contract rules for large data centers
- HB 1189 · In committeePauses data center permits two years and studies their impacts
- HB 1180 · In committeeRequires approved utility tariffs for large load data center service
- HB 1063 · In committeeRegulates large data centers and repeals their sales tax exemptions
Sources
- 1Senate Bill 257 / SL 2026-41 (2025-2026 Session)
North Carolina General AssemblyTier 1 · Open the source - 2Legislative Fiscal Note, Senate Bill 257 (7th Edition), 2026 Appropriations Act
North Carolina General Assembly, Fiscal Research DivisionTier 1 · Open the source - 3Senate Bill 257: 2026 Appropriations Act, Sec. 44.4, Repeal Sales Tax Exemption on Electricity for Datacenters
North Carolina General Assembly, Legislative Analysis DivisionTier 1 · Open the source
Cite this page
Copy this citation when you reuse a figure or a finding from this page.
Data Center Fact Check. "SB 257: Ends the sales tax exemption for electricity used in datacenters." Bill Watch. Updated 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/policy/bills/nc-2025-26-sb-257
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page