Data centers in Newton County, Georgia

Last checked Nov 12, 2026

Draft research: figures were traced to their sources by an AI research agent and have not passed verification yet.

Data Center Fact Check tracks 2 data center projects in Newton County, Georgia as of November 2026: 1 proposed and 1 operating.

Newton County has 2 tracked data centers. Of those, 1 proposed and 1 operating. Electricity here comes from Central Georgia Electric Membership Corporation. The projects here are Gregory Road Data Center and Meta Newton Data Center (Stanton Springs). Every figure comes from the public record linked on this page.

2Data center projects we track
8.567Real property tax rate, mills (USD per 1000 USD of assessed value), 2026

Data center projects in Newton County

Who serves this place

  • ElectricityCentral Georgia Electric Membership Corporation
  • ElectricityCity of Covington Utilities
  • ElectricityGeorgia Power Company
  • ElectricitySnapping Shoals Electric Membership Corporation
  • ElectricityWalton Electric Membership Corporation
  • WaterCity of Social Circle
  • WaterNewton County Water and Sewerage Authority
  • Grid regionSouthern Company balancing area

A data center is proposed in Newton County

1 project here is at the announced or proposed stage. Before the hearing, the resident checklist walks through what to check: the proposal's documents, the local rules where you live, the tax agreement, and the recorded votes.

Open the resident checklist

Places in and around Newton County

Newton County is part of Georgia.

Cities and towns

Nearby places

For homeowners

What the projects here mean if you live nearby

Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work

  1. Property tax

  2. Tax breaks

  3. Money for schools and services

  4. Electricity bill

  5. Water

  6. Jobs

  7. Next door: height, setbacks, noise

  8. Your say

Taxes and budget over time

As published by the county, not adjusted for inflation. Projections are labeled.

Total property tax revenue

Total property tax revenue by year
FY 2024$41.4 million
FY 2023$40.1 million
FY 2022$38.8 million
FY 2021$37.8 million
FY 2020$36.4 million
FY 2019$33.2 million

Real property tax rate

Real property tax rate by year
20268.567 mills (USD per 1000 USD of assessed value)
20258.567 mills (USD per 1000 USD of assessed value)
FY 20248.439 mills (USD per 1000 USD of assessed value)
FY 20239.454 mills (USD per 1000 USD of assessed value)
FY 202211.145 mills (USD per 1000 USD of assessed value)
FY 202112.916 mills (USD per 1000 USD of assessed value)

Total assessed value

Total assessed value by year
FY 2024$5.3 billion
FY 2023$4.22 billion
FY 2022$3.47 billion
FY 2021$3.03 billion
FY 2020$2.83 billion
FY 2019$2.37 billion

General fund budget

General fund budget by year
FY 2026$108.6 million
FY 2025$99.5 million

Tax breaks and payments

  • 2018 · Meta Newton Data Center (Stanton Springs)

    Bond lease and payment in lieu of taxes agreement (Joint Development Authority)

    The JDA issued $42 billion in bonds in 2018, holds title to the property (which makes it tax-exempt), and the company pays rent equal to the bond draws plus payments in lieu of taxes of $1 million per building per year, triggered by certificates of occupancy by December 31. Payments received: $2 million (2022), $2 million (2023), $3 million (2024), $5 million (2025), $8 million (2026); $10 million per year at buildout. Stanton Springs South shares: Newton 37.5 percent, Walton 37.5 percent, Morgan 15 percent, Jasper 10 percent.

    All tax records for Meta Newton Data Center (Stanton Springs)
  • 2021 · Meta Newton Data Center (Stanton Springs)

    Bond resolution, inducement, and payment in lieu of taxes agreement (Joint Development Authority)

    The JDA issued $42 billion in bonds in 2021, holds fee simple title, and Baymare held the lease; payments in lieu of taxes run under the same per-building schedule as the 2018 project. The JDA's FY2023-24 budget amendment shows Baymare Project PILOT payments of $0.

    All tax records for Meta Newton Data Center (Stanton Springs)

Local rules for data centers

  • In effect · Moratorium · Adopted Oct 6, 2026

    Extension of the data center application moratorium to December 16 2026

    Newton County extended its moratorium on accepting any application request or submission that proposes developing a data center in the county including rezoning special use and conditional use permits development and building permits and site plans while the county finishes studying a data center ordinance.

  • Expired · Moratorium · Adopted Apr 7, 2026

    Limited moratorium on acceptance of data center applications

    The resolution continues the county's moratorium chain (the February 17, 2026 emergency moratorium ran to March 18, and a March 3 revision extended it to April 8) by barring acceptance of data center applications until October 7, 2026, while the county drafts data center standards. Resolution R-100626A later extended the moratorium to December 16, 2026.

  • Expired · Moratorium · Adopted Feb 17, 2026

    Emergency moratorium on acceptance of data center applications

    The resolution bars the county, until March 18, 2026, from accepting applications, requests, or submissions that propose data center development in whole or in part, including rezoning, special use and conditional use permits, development permits, site plans, and building permits. Its stated purpose is to give the county time to study and draft an ordinance on data center development. By its own terms it ended on the earliest of March 18, 2026, Board approval of an additional moratorium after a public hearing, or Board action ending it; no extension was found in the sources read.

  • In effect · Other · Adopted Jan 20, 2026

    Added data center approval criteria: site area, fencing, setbacks, buffers, utilities, noise, and safety

    This ordinance rewrote the city standards for permitting and approving a data center. Its title lists the subjects covered: minimum site area, fencing and security requirements, setbacks, buffers, infrastructure and utility requirements, noise standards, emergency response and public safety standards, and penalties and enforcement. The numeric values inside Section 3.4.6 could not be extracted in this pass because the Municode section page was blocked, so no numbers are claimed here.

  • Expired · Moratorium · Adopted Sep 16, 2025

    90 day moratorium on submission of new data center projects

    The city paused submissions of new data center projects for 90 days so officials could consider the proposals in front of them and study the issue. The pause ran out in mid December 2025, and the city adopted detailed data center criteria the following month (Ordinance No. 2026-2).

Court cases and commission dockets in Georgia (8)

Bills and laws in Georgia

All 14 in Bill Watch

Latest from the newswire

  1. What the record shows · November 28, 2026

    Loudoun County data centers: the complete record

  2. What the record shows · November 22, 2026

    SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days

  3. What the record shows · November 22, 2026

    PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.

Officials we track for Newton County

The lawmakers and local officials whose recorded jurisdiction is Newton County, with the bills and votes we have on record for each.

Questions people ask

How many data centers are in Newton County?
Data Center Fact Check tracks 2 data center projects in Newton County as of November 2026. Of those, 1 proposed and 1 operating.

Sources

  1. 1
    Drinking Water State Revolving Fund, State Fiscal Year 2025 Annual Report
    Georgia Environmental Finance Authority
    Tier 1 · Open the source
  2. 2
    Stanton Springs Data Center info sheet
    Meta
    Tier 4 · Open the source
  3. 3
    Newton County, GA: Electricity Rates, Providers and More
    FindEnergy
    Tier 3 · Open the source
  4. 4
    Electric
    Georgia Public Service Commission
    Tier 1 · Open the source
  5. 5
    Who We Are
    Snapping Shoals EMC
    Tier 1 · Open the source
  6. 6
    Service Area
    Walton EMC
    Tier 1 · Open the source
  7. 7
    Board of Commissioners minutes, August 4, 2026
    Newton County, Georgia
  8. 8
    FY 2024 Annual Comprehensive Financial Report
    Newton County, Georgia
    Tier 1 · Open the source
  9. 9
    Board of Commissioners minutes, August 5, 2025
    Newton County, Georgia
    Tier 1 · Open the source
  10. 10
    FY 2026 Budget Book (Adopted)
    Newton County, Georgia
    Tier 1 · Open the source
  11. 11
    JDA Meeting Packet, December 19, 2023
    Joint Development Authority of Jasper, Morgan, Newton, and Walton Counties
    Tier 1 · Open the source
  12. 12
    JDA Quarterly Report, Q1 2024
    Joint Development Authority of Jasper, Morgan, Newton, and Walton Counties
    Tier 1 · Open the source
  13. 13
    JDA Meeting Packet, May 27, 2025
    Joint Development Authority of Jasper, Morgan, Newton, and Walton Counties
    Tier 1 · Open the source
  14. 14
    JDA Meeting Packet, February 27, 2024
    Joint Development Authority of Jasper, Morgan, Newton, and Walton Counties
    Tier 1 · Open the source
  15. 15
    EIA Form 861 2025, Sales to Ultimate Customers file
    U.S. Energy Information Administration
    Tier 1 · Open the source
  16. 16
    EIA Form 861 2016, Sales to Ultimate Customers file
    U.S. Energy Information Administration
    Tier 1 · Open the source
  17. 17
    FYE 2025 Budget and Financial Plan
    Newton County Water and Sewerage Authority
    Tier 1 · Open the source
  18. 18
    Meta 2025 Environmental Data Index
    Meta Platforms, Inc.
    Tier 4 · Open the source
  19. 19
    Data center proposal in Social Circle, Georgia, fails to receive recommendation from Planning Commission
    Data Center Dynamics
    Tier 3 · Open the source
  20. 20
    Board of Commissioners Regular Meeting Minutes, February 17, 2026
    Newton County, Georgia
    Tier 1 · Open the source
  21. 21
    Newton County Unified Development Ordinance, Chapter 1 Zoning Ordinance
    Newton County, Georgia
    Tier 1 · Open the source
  22. 22
    Code of Ordinances, City of Social Circle (adopted ordinances listing)
    City of Social Circle, Georgia (Municode Library)
    Tier 1 · Open the source
  23. 23
    Board of Commissioners regular meeting minutes 2026-10-06 (full text of Resolution R-100626A)
    Newton County Board of Commissioners
    Tier 1 · Open the source
  24. 24
    Newton County Board of Commissioners regular meeting minutes, April 7, 2026
    Newton County Board of Commissioners
    Tier 1 · Open the source
  25. 25
    Board of Commissioners regular meeting minutes 2026-10-20 (UDO update ordinance O-102026 deferred)
    Newton County Board of Commissioners
    Tier 1 · Open the source
  26. 26
    JDA Quarterly Report, Q2 2026
    Joint Development Authority of Jasper, Morgan, Newton and Walton Counties
    Tier 1 · Open the source

Cite this page

Copy this citation when you reuse a figure or a finding from this page.

Data Center Fact Check. "Newton County." Last checked 2026-11-12. Accessed 2026-11-29. https://datacenterfactcheck.org/places/us-ga-newton

No corrections have been published for this page. Corrections log · Report an error or send a tip on this page