Meta Newton Data Center (Stanton Springs)
Social Circle,Newton County,GeorgiaOperatingFirst public 2018Last checked Nov 9, 2026
MetaDeveloper and operatorWalton EMCElectric utilityJoint Development Authority (Stanton Springs)Public partner
Details confirmed
Every detail on this page comes from an original record. Anything we have not confirmed is left blank, and this bar shows where this project's record stands.
5 of 6 details confirmed
- Confirmed: County
- Confirmed: City or address
- Confirmed: Stage
- Confirmed: Electric utility
- Confirmed: First public date
- Still to confirm: Capacity
What happens next: No upcoming date is on record.
Record order shows the sections in file order. Highlights first makes the first key number large and moves the timeline up under it. Both show the same sections; nothing is hidden.
Draft research: these facts were traced to their sources by an AI research agent and have not passed verification yet.
Meta Newton Data Center (Stanton Springs) is an operating data center project in Social Circle, Newton County, Georgia. Meta is named as operator. It was first public in 2018. No site capacity figure is published for this project.
Meta Newton Data Center (Stanton Springs) is an operating data center project in Social Circle, Newton County, Georgia. Meta is named as operator. No site capacity figure is published for this project. 5 of the six core facts we track for every project are confirmed on this page.
Where this project sits
This project sits in Social Circle, Newton County, Georgia. Each place page carries the projects tracked there, who provides its power and water, and its local rules.
For homeowners
What this project means if you live nearby
Each fact says which way it runs: comes to the community (such as tax paid), comes from the community (such as water or a tax break), or goes both ways. The labels show direction, not whether it is good or bad. How we work
- Property tax
The authority holds title to the campus, so it pays no property tax; Meta pays per building instead.
Goes both ways - Tax breaks
Two bond deals, each $42 billion authorized in 2018 and 2021, hold the campus tax-exempt through the authority.
Goes both ways - Money for schools and services
Newton County share of the campus payments is 37.5 percent, split with three neighboring counties.
Comes to the community - Electricity bill
The average Walton EMC home paid $174.78 a month in 2025, up from $141.12 in 2016, not adjusted for inflation.
Not known yet - Water
Meta says it pays the full cost of water and sewer service from the county water authority.
Comes from the community - Jobs
Job counts for this campus are not in our records yet.
Not known yet - Next door: height, setbacks, noise
Newton County paused new data center approvals for 30 days in February 2026; the pause has expired.
Local rule - Your say
County commissioners voted the 2026 pause in public; the authority board holding the campus title also meets publicly.
How to take part
Latest from the newswire
What the record shows · November 28, 2026
What the record shows · November 22, 2026
SpaceX's SEC filing counts 220,000 processors at xAI Colossus 2, switched on in 91 days and 64 days
What the record shows · November 22, 2026
PPL's data center pipeline reached 31.8 gigawatts. Signed contracts cover over 11.
Timeline
- · Court caseCourt case filed: Morris et al. v. Meta Platforms, Inc. et al. (Stanton Springs wells)Superior Court of Gwinnett County, Georgia
- · Tax dealTax agreement approved: Bond resolution, inducement, and payment in lieu of taxes agreement (joint development authority) for Baymare LLCThe JDA issued $42 billion in bonds in 2021, holds fee simple title, and Baymare held the lease; payments in lieu of taxes run under the same per-building schedule as the 2018 project. The JDA's FY2023-24 budget amendment shows Baymare P...
- · New projectFirst public record of Meta Newton Data Center (Stanton Springs)Operating
- · Tax dealTax agreement approved: Bond lease and payment in lieu of taxes agreement (joint development authority) for Morning Hornet LLCThe JDA issued $42 billion in bonds in 2018, holds title to the property (which makes it tax-exempt), and the company pays rent equal to the bond draws plus payments in lieu of taxes of $1 million per building per year, triggered by cert...
Laws and bills that may apply here
Found by each bill's own place and size rules. Each one says who has checked it so far.
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia HB 1063: Requires utility contracts shielding other customers from data center costs
The act covers data centers with a peak annual electricity demand of 100 megawatts or greater, under agreements with an electric utility entered into on or after the effective date of the act; this project has no capacity figure on record, but the project's peak annual electricity demand and the date of its electric service agreement is not on record.
“As used in this part, the term 'data center' means a facility, campus of facilities, or array of interconnected facilities used by an entity or other business enterprise to operate, manage, or maintain a computer, group of computers, or other organized assembly of hardware and software for the primary purpose of processing, storing, retrieving, or transmitting data and that have a peak annual electricity demand of 100 megawatts or greater.” (Section 1, new Code Section 46-3-80)
Rule checks: Project is in Georgia. Still to check: size: unknown, who it covers: not checked
- Possible match, AI could not decide; waiting for a person · Nov 29, 2026Georgia SB 410: Ends new data center tax breaks, sets large load contract terms
The act covers large load customers with an expected total peak demand of 100 megawatts or greater at premises on one tract or contiguous tracts of land, under contracts entered into on or after the effective date of the act; this project has no capacity figure on record, but the project's expected total peak demand and the date of its electric service contract is not on record.
“As used in this Code section, the term 'large load customer' means customers with an expected total peak demand of 100 megawatts or greater at one or more premises located on one tract or contiguous tracts of land.” (Part I, Section 1-2, new Code Section 46-2-25.4(a))
Rule checks: Project is in Georgia. Still to check: size: unknown, who it covers: not checked
Bills and laws in Georgia
- SB 410 · Passed one chamber · Mar 6, 2026Ends new data center tax breaks, sets large load contract terms
- SB 34 · Died or failed · Feb 26, 2026Bars shifting data center power costs onto other utility customers
- HB 1387 · Died or failed · Feb 20, 2026Funds homestead exemption from property taxes collected on data centers
- SB 530 · Died or failed · Feb 19, 2026Deposits data center tax collections into a property tax relief fund
- HB 1323 · Died or failed · Feb 18, 2026Requires new data centers to operate as hybrid power facilities
- HB 1063 · Passed one chamber · Feb 17, 2026Requires utility contracts shielding other customers from data center costs
Who's involved
- Developer and operatorMeta
- Electric utilityWalton EMC
- Public partnerJoint Development Authority (Stanton Springs)
Power and water
Electricity used, as reported by the operator
Facility electricity consumption as reported by the operator (whole site; the table does not split IT load from facility load)
| Year | Electricity used |
|---|---|
| 2024 | 1,184,380 MWh |
| 2023 | 968,565 MWh |
| 2022 | 636,266 MWh |
| 2021 | 215,279 MWh |
Water, as reported by the operator
Stanton Springs (GA) facility as named in Meta's 2025 Environmental Data Index (the Newton County campus)
- 2024 · Withdrawal: 146 ML
- 2023 · Withdrawal: 61 ML
- 2022 · Withdrawal: 77 ML
- 2021 · Withdrawal: 105 ML
From the filings
Numbers stated in permits, agreements, and decisions, as printed. Each links to the filing.
Newton County (as reported by the Joint Development Authority), Final certificates of occupancy, three buildings, Morning Hornet campus
- Buildings
- 3 buildings with final certificates of occupancy, Morning Hornet campus
Newton County (as reported by the Joint Development Authority), Certificates of occupancy, three buildings, Baymare campus
- Buildings
- 3 buildings with certificates of occupancy, Baymare campus
Public records
22 records found so far. 3 kinds of record are still being collected.
- Land and zoning rules11
- Building and site permits2
- Tax breaks and payments2
- Votes and minutes5
- Courts and disputes1
- Company filings1
Court cases and commission dockets
- Court case · Pending · Aug 31, 2026Morris et al. v. Meta Platforms, Inc. et al. (Stanton Springs wells)
Questions people ask
- Where is Meta Newton Data Center (Stanton Springs)?
- Meta Newton Data Center (Stanton Springs) is a data center project in Social Circle, Newton County, Georgia.
- Who operates Meta Newton Data Center (Stanton Springs)?
- Meta is named as the operator of Meta Newton Data Center (Stanton Springs).
- What stage is Meta Newton Data Center (Stanton Springs)?
- Meta Newton Data Center (Stanton Springs) is operating. It was first public in 2018.
Sources
Tier 1 is a primary record: the original record, such as a filing, permit, dataset, or official document. Tier 2 is expert analysis by a named expert or institution. Tier 3 is credible reporting by a news outlet. Tier 4 is a statement by a party with an interest in the outcome.
- 1Business Search
Georgia Secretary of State, Corporations DivisionTier 1 · Captured 2026-11-08 · Open the source - 2JDA Quarterly Report, Q1 2024
Joint Development Authority of Jasper, Morgan, Newton, and Walton CountiesTier 1 · Captured 2026-11-07 · Open the source - 3JDA Quarterly Report, Q4 2025
Joint Development Authority of Jasper, Morgan, Newton and Walton CountiesTier 1 · Captured 2026-11-09 · Open the source - 4Morris et al. v. Meta Platforms, Inc. et al., complaint (Civil Action File No. 26-A-07974-11)
Superior Court of Gwinnett County, Georgia (filed complaint, hosted by ALM)Tier 1 · Captured 2026-11-07 · Open the source - 5JDA Meeting Packet, December 19, 2023
Joint Development Authority of Jasper, Morgan, Newton, and Walton CountiesTier 1 · Captured 2026-11-07 · Open the source - 6JDA Meeting Packet, May 27, 2025
Joint Development Authority of Jasper, Morgan, Newton, and Walton CountiesTier 1 · Captured 2026-11-07 · Open the source - 7JDA Quarterly Report, Q2 2026
Joint Development Authority of Jasper, Morgan, Newton and Walton CountiesTier 1 · Captured 2026-11-09 · Open the source - 8JDA Meeting Packet, February 27, 2024
Joint Development Authority of Jasper, Morgan, Newton, and Walton CountiesTier 1 · Captured 2026-11-07 · Open the source - 9Newton County Unified Development Ordinance, Chapter 1 Zoning Ordinance
Newton County, GeorgiaTier 1 · Captured 2026-11-07 · Open the source - 10Code of Ordinances, City of Social Circle (adopted ordinances listing)
City of Social Circle, Georgia (Municode Library)Tier 1 · Captured 2026-11-07 · Open the source - 11Data center proposal in Social Circle, Georgia, fails to receive recommendation from Planning Commission
Data Center DynamicsTier 3 · Captured 2026-11-07 · Open the source - 12Board of Commissioners Regular Meeting Minutes, February 17, 2026
Newton County, GeorgiaTier 1 · Captured 2026-11-07 · Open the source - 13Board of Commissioners regular meeting minutes 2026-10-06 (full text of Resolution R-100626A)
Newton County Board of CommissionersTier 1 · Captured 2026-11-08 · Open the source - 14Board of Commissioners regular meeting minutes 2026-10-20 (UDO update ordinance O-102026 deferred)
Newton County Board of CommissionersTier 1 · Captured 2026-11-08 · Open the source - 15Newton County Board of Commissioners regular meeting minutes, April 7, 2026
Newton County Board of CommissionersTier 1 · Captured 2026-11-09 · Open the source - 16Deal: Facebook to invest $750 million in Stanton Springs data center
Office of the Governor of Georgia (archived at the Digital Library of Georgia)Tier 1 · Captured 2026-11-07 · Open the source - 17Meta 2025 Environmental Data Index
Meta Platforms, Inc.Tier 4 · Captured 2026-11-08 · Open the source - 18EIA Form 861 2025, Sales to Ultimate Customers file
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-07 · Open the source - 19EIA Form 861 2016, Sales to Ultimate Customers file
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-07 · Open the source - 20
- 21FYE 2025 Budget and Financial Plan
Newton County Water and Sewerage AuthorityTier 1 · Captured 2026-11-08 · Open the source - 22Form EIA-861 detailed data files 2023 (Service Territory and Utility Data)
U.S. Energy Information AdministrationTier 1 · Captured 2026-11-07 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page