Project File · Public records
Every public record we have for Meta Newton Data Center (Stanton Springs)
Social Circle, Newton County, GeorgiaOperatingFirst public 2018Last checked Nov 9, 2026
Records marked draft were traced to their source by an AI research agent and have not passed verification yet.
What the public record holds
22 of 22 records
2026
Recorded voteOct 20, 2026Newton County Board of Commissioners
Deferral of Ordinance O-102026A (data center overlay district and map amendments) to December 15, 2026
5 yes. Andre Cooper (Commissioner): yes; Demond Mason (Commissioner): yes; J.C. Henderson (Commissioner): yes; LeAnne Long (Commissioner): yes; Stan Edwards (Commissioner): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Zoning new business item 2 (motion by Commissioner Henderson, seconded by Commissioner Cooper; the motion passed, vote 5-0)
Recorded voteOct 20, 2026Newton County Board of Commissioners
Deferral of Ordinance O-102026 (Unified Development Ordinance update carrying the proposed data center standards) to December 15, 2026
5 yes. Andre Cooper (Commissioner): yes; Demond Mason (Commissioner): yes; J.C. Henderson (Commissioner): yes; LeAnne Long (Commissioner): yes; Stan Edwards (Commissioner): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Zoning new business item 1 (motion by Commissioner Edwards, seconded by Commissioner Cooper; the motion passed, vote 5-0)
Development ruleIn effectOct 6, 2026Newton County
Extension of the data center application moratorium to December 16 2026
Newton County extended its moratorium on accepting any application request or submission that proposes developing a data center in the county including rezoning special use and conditional use permits development and building permits and site plans while the county finishes studying a data center ordinance.
Resolution R-100626A
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Resolution R-100626A full text printed in the Board of Commissioners minutes for 2026-10-06 (zoning agenda item 2)
Recorded voteOct 6, 2026Newton County Board of Commissioners
Approval of Resolution R-100626A, extending the moratorium on the acceptance of data center applications to December 16, 2026
5 yes. Andre Cooper (Commissioner): yes; Demond Mason (Commissioner): yes; J.C. Henderson (Commissioner): yes; LeAnne Long (Vice-Chair): yes; Stan Edwards (Commissioner): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Zoning agenda item 2, Resolution R-100626A (motion by Commissioner Edwards, seconded by Commissioner Mason; the motion passed, vote 5-0)
LawsuitPendingAug 31, 2026Superior Court of Gwinnett County, Georgia
Morris et al. v. Meta Platforms, Inc. et al. (Stanton Springs wells)
Four families living near Meta's Stanton Springs campus in Newton County sued Meta, its site companies, the four-county development authority, and two contractors. They say clearing, blasting, and excavation for the campus pushed silt and sediment into their private wells, damaging plumbing and appliances. Meta disputes the claims and says a study it commissioned found groundwater flows away from the families' properties.
26-A-07974-11
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Filed complaint, caption and paragraphs 1 to 3 (e-filed August 31, 2026, 10:46 AM)
Development ruleExpiredApr 7, 2026Newton County
Limited moratorium on acceptance of data center applications
The resolution continues the county's moratorium chain (the February 17, 2026 emergency moratorium ran to March 18, and a March 3 revision extended it to April 8) by barring acceptance of data center applications until October 7, 2026, while the county drafts data center standards. Resolution R-100626A later extended the moratorium to December 16, 2026.
Resolution R-040726b
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, April 7, 2026, zoning agenda item 4
Recorded voteApr 7, 2026Newton County Board of Commissioners
Adoption of Resolution R-040726b, limited moratorium on the acceptance of data center applications until October 7, 2026
5 yes. Andre Cooper (Commissioner): yes; Demond Mason (Commissioner): yes; J.C. Henderson (Commissioner): yes; LeAnne Long (Commissioner): yes; Stan Edwards (Commissioner): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Zoning agenda item 4, Resolution R-040726b (motion by Commissioner Long, seconded by Commissioner Mason; the motion passed, vote 5-0)
Development ruleExpiredFeb 17, 2026Newton County
Emergency moratorium on acceptance of data center applications
The resolution bars the county, until March 18, 2026, from accepting applications, requests, or submissions that propose data center development in whole or in part, including rezoning, special use and conditional use permits, development permits, site plans, and building permits. Its stated purpose is to give the county time to study and draft an ordinance on data center development. By its own terms it ended on the earliest of March 18, 2026, Board approval of an additional moratorium after a public hearing, or Board action ending it; no extension was found in the sources read.
Resolution #R021726
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Minutes item 11, Resolution #R021726, operative paragraphs 2 and 4
Recorded voteFeb 17, 2026Newton County Board of Commissioners
Adoption of Resolution #R021726, emergency moratorium on the acceptance of data center applications (in effect until March 18, 2026)
5 yes. Andre Cooper (Commissioner): yes; Demond Mason (Commissioner): yes; J.C. Henderson (Commissioner): yes; LeAnne Long (Commissioner): yes; Stan Edwards (Commissioner): yes.
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Item 11, Resolution #R021726 (motion by Commissioner Long, seconded by Commissioner Mason; the motion passed, vote 5-0)
Development ruleIn effectJan 20, 2026Social Circle
Added data center approval criteria: site area, fencing, setbacks, buffers, utilities, noise, and safety
This ordinance rewrote the city standards for permitting and approving a data center. Its title lists the subjects covered: minimum site area, fencing and security requirements, setbacks, buffers, infrastructure and utility requirements, noise standards, emergency response and public safety standards, and penalties and enforcement. The numeric values inside Section 3.4.6 could not be extracted in this pass because the Municode section page was blocked, so no numbers are claimed here.
Ordinance No. 2026-2, amending Section 3.4.6 of the Uniform Development Code of the City of Social Circle
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Adopted ordinances listing entry "Ordinance No. 2026-2, Adopted 1/20/26"
2025
Development ruleExpiredSep 16, 2025Social Circle
90 day moratorium on submission of new data center projects
The city paused submissions of new data center projects for 90 days so officials could consider the proposals in front of them and study the issue. The pause ran out in mid December 2025, and the city adopted detailed data center criteria the following month (Ordinance No. 2026-2).
City of Social Circle data center moratorium (ordinance or resolution number not stated in the sources read)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Article text: "on September 16, the City of Social Circle also unanimously passed a 90-day moratorium on the submission of new data center projects"
2021
Tax agreementFeb 24, 2021Newton County
Bond resolution, inducement, and payment in lieu of taxes agreement (Joint Development Authority)
The JDA issued $42 billion in bonds in 2021, holds fee simple title, and Baymare held the lease; payments in lieu of taxes run under the same per-building schedule as the 2018 project. The JDA's FY2023-24 budget amendment shows Baymare Project PILOT payments of $0.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Packet of February 27, 2024, pp. 49-50 (resolution recitals recording the February 2, 2021 purchase agreement and the February 24, 2021 Bond Resolution and Inducement and PILOT Agreement)
2018
Tax agreement2018Newton County
Bond lease and payment in lieu of taxes agreement (Joint Development Authority)
The JDA issued $42 billion in bonds in 2018, holds title to the property (which makes it tax-exempt), and the company pays rent equal to the bond draws plus payments in lieu of taxes of $1 million per building per year, triggered by certificates of occupancy by December 31. Payments received: $2 million (2022), $2 million (2023), $3 million (2024), $5 million (2025), $8 million (2026); $10 million per year at buildout. Stanton Springs South shares: Newton 37.5 percent, Walton 37.5 percent, Morgan 15 percent, Jasper 10 percent.
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Packet of December 19, 2023, p. 47 (bond draws and structure); Quarterly Report Q1 2024 (2024 payment and shares); packet of May 27, 2025, April 22, 2025 minutes (2025 payment and per-building trigger)
2009
Setback ruleIn effectFeb 17, 2009Newton County
Setbacks, height, and buffer standards in the Stanton Springs district
Development standards for the Stanton Springs district set minimum front, side, and rear setbacks, a maximum building height, and a wide transitional buffer where district property abuts residential property. Utilities must be placed underground except major electric transmission lines and substations, and occupied buildings must use public water and sewer.
Newton County Unified Development Ordinance, Chapter 1 Zoning Ordinance, Sec. 285-060 (Stanton Springs Business Park District)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Zoning Ordinance pp. 86-96, Sec. 285-060 (Standards of Development)
Development ruleIn effectFeb 17, 2009Newton County
Screening of cooling towers and mechanical and electrical equipment in Stanton Springs
In the Stanton Springs district, cooling towers and rooftop or ground mounted mechanical and electrical units that are visible from a road parcel or any public road must be built into the building design or screened from public view, and landscaping may serve as the screen. Building facades on front and street sides must use durable permanent architectural materials, and unfaced concrete block, structural concrete, corrugated metal, and pole buildings are not permitted.
Newton County Unified Development Ordinance, Chapter 1 Zoning Ordinance, Sec. 285-060.L.3 (Stanton Springs Business Park District)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Sec. 285-060.L.3 and the building standards at Sec. 285-060
Zoning ruleIn effectFeb 17, 2009Newton County
Data Management or Processing Center is a permitted use in the Stanton Springs Business Park District
The Stanton Springs district is written for large mixed use business park tracts, and its purpose section names data centers among the uses the district is well suited to. Both use tables for the district, Tier 1 inside the Business Parkway and Tier 2 outside it, list Data Management or Processing Center as P, a permitted use. County staff told the Board of Commissioners in February 2026 that the county data center rules apply only to the Stanton Springs area.
Newton County Unified Development Ordinance, Chapter 1 Zoning Ordinance, Sec. 285-010 and Sec. 285-030 (Stanton Springs Business Park District, Division 285)
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Zoning Ordinance pp. 86-96, Division 285; Sec. 285-010 (purpose) and Sec. 285-030 (Tier 1 and Tier 2 use tables)
No date in the record(rules in force and undated records)
Business registrationIssuedNo date in the recordGeorgia Secretary of State, Corporations Division
Georgia Secretary of State, Corporations Division, 18005611
Georgia registration of Morning Hornet LLC, the filing entity for the Meta Stanton Springs campus (Corporations Division control number 18005611)
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
Business Search name results: Morning Hornet LLC, Control Number 18005611
Certificate of occupancyIssuedNo date in the recordNewton County (as reported by the Joint Development Authority)
Newton County (as reported by the Joint Development Authority), Final certificates of occupancy, three buildings, Morning Hornet campus
Issued (as of the first quarter of 2024)
- Buildings:
- 3 buildings with final certificates of occupancy, Morning Hornet campus
Draft research, not yet verifiedLast checked Nov 8, 2026Where it says this
JDA Quarterly Report, January to March 2024, Current Tenants section, page 1
Certificate of occupancyIssuedNo date in the recordNewton County (as reported by the Joint Development Authority)
Newton County (as reported by the Joint Development Authority), Certificates of occupancy, three buildings, Baymare campus
Issued (as of the fourth quarter of 2025)
- Buildings:
- 3 buildings with certificates of occupancy, Baymare campus
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
JDA Quarterly Report Q4 2025, Current Tenants section
Zoning ruleIn effectNo date in the recordSocial Circle
A data center in the light industrial district requires a special use approval
A 150 acre data center proposal at 0 Hawkins Academy Road and 0 Roy Malcom Road needed four city approvals: annexation, a future land use map amendment, rezoning, and a special use to allow a data center under light industrial zoning. The Planning Commission voted unanimously on September 23, 2025 against recommending any of the four requests.
City of Social Circle Uniform Development Code, light industrial district (special use), as applied in the September 2025 Hawkins Academy Road application
Draft research, not yet verifiedLast checked Nov 7, 2026Where it says this
Article text on the September 23, 2025 Planning Commission meeting and the four requests
Zoning ruleProposedNo date in the recordNewton County
Unified Development Ordinance update with proposed data center standards
The ordinance would update the county's Unified Development Ordinance, carrying the proposed data center standards. On October 20, 2026 the Board voted 5-0 to defer it to December 15, 2026; it has not been adopted.
Ordinance O-102026
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, October 20, 2026, zoning new business item 1
Zoning ruleProposedNo date in the recordNewton County
Data center overlay district and map amendments
Companion ordinance to O-102026: an overlay district with future land use map and zoning map amendments for data centers. On October 20, 2026 the Board voted 5-0 to defer it to December 15, 2026; it has not been adopted.
Ordinance O-102026A
Draft research, not yet verifiedLast checked Nov 9, 2026Where it says this
Minutes, October 20, 2026, zoning new business item 2
Records we are still collecting
These records are normally public. We have not collected them for this project yet; each will appear above with its source when found.
- Environmental permits
Air permits for backup generators, stormwater, wastewater, wetlands. Usually held by: State environmental agency.
- Water supply and use
Water service agreements, water rights, use reports. Usually held by: Water utility and state water agency.
- Power and utility
Interconnection, large load rate classes, utility agreements, commission dockets. Usually held by: Electric utility and utility commission.
Sources
- 1Business Search
Georgia Secretary of State, Corporations DivisionTier 1 · Captured 2026-11-08 · Open the source - 2JDA Quarterly Report, Q1 2024
Joint Development Authority of Jasper, Morgan, Newton, and Walton CountiesTier 1 · Captured 2026-11-07 · Open the source - 3JDA Quarterly Report, Q4 2025
Joint Development Authority of Jasper, Morgan, Newton and Walton CountiesTier 1 · Captured 2026-11-09 · Open the source - 4Morris et al. v. Meta Platforms, Inc. et al., complaint (Civil Action File No. 26-A-07974-11)
Superior Court of Gwinnett County, Georgia (filed complaint, hosted by ALM)Tier 1 · Captured 2026-11-07 · Open the source - 5JDA Meeting Packet, December 19, 2023
Joint Development Authority of Jasper, Morgan, Newton, and Walton CountiesTier 1 · Captured 2026-11-07 · Open the source - 6JDA Meeting Packet, May 27, 2025
Joint Development Authority of Jasper, Morgan, Newton, and Walton CountiesTier 1 · Captured 2026-11-07 · Open the source - 7JDA Quarterly Report, Q2 2026
Joint Development Authority of Jasper, Morgan, Newton and Walton CountiesTier 1 · Captured 2026-11-09 · Open the source - 8JDA Meeting Packet, February 27, 2024
Joint Development Authority of Jasper, Morgan, Newton, and Walton CountiesTier 1 · Captured 2026-11-07 · Open the source - 9Newton County Unified Development Ordinance, Chapter 1 Zoning Ordinance
Newton County, GeorgiaTier 1 · Captured 2026-11-07 · Open the source - 10Code of Ordinances, City of Social Circle (adopted ordinances listing)
City of Social Circle, Georgia (Municode Library)Tier 1 · Captured 2026-11-07 · Open the source - 11Data center proposal in Social Circle, Georgia, fails to receive recommendation from Planning Commission
Data Center DynamicsTier 3 · Captured 2026-11-07 · Open the source - 12Board of Commissioners Regular Meeting Minutes, February 17, 2026
Newton County, GeorgiaTier 1 · Captured 2026-11-07 · Open the source - 13Board of Commissioners regular meeting minutes 2026-10-06 (full text of Resolution R-100626A)
Newton County Board of CommissionersTier 1 · Captured 2026-11-08 · Open the source - 14Board of Commissioners regular meeting minutes 2026-10-20 (UDO update ordinance O-102026 deferred)
Newton County Board of CommissionersTier 1 · Captured 2026-11-08 · Open the source - 15Newton County Board of Commissioners regular meeting minutes, April 7, 2026
Newton County Board of CommissionersTier 1 · Captured 2026-11-09 · Open the source - 16Deal: Facebook to invest $750 million in Stanton Springs data center
Office of the Governor of Georgia (archived at the Digital Library of Georgia)Tier 1 · Captured 2026-11-07 · Open the source
No corrections have been published for this page. Corrections log · Report an error or send a tip on this page